Newell Contracting Co. v. Blankenship

125 S.E. 420, 130 S.C. 131, 1924 S.C. LEXIS 83
CourtSupreme Court of South Carolina
DecidedNovember 13, 1924
Docket11608
StatusPublished
Cited by16 cases

This text of 125 S.E. 420 (Newell Contracting Co. v. Blankenship) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newell Contracting Co. v. Blankenship, 125 S.E. 420, 130 S.C. 131, 1924 S.C. LEXIS 83 (S.C. 1924).

Opinion

The opinion of the Court was delivered by

Mr. Justice Cothran.

This is a suit upon two causes of action, aggregating $8,940.89, which amount is claimed by the plaintiff to be due by the defendants, on account of the transactions hereinafter detailed. Por convenience, the plaintiff, Newell Contracting Company, will be referred to as Newell, and the defendants J. R. & J. D. Blankenship, as Blankenship.

In July, 1916, a large road-building contract, covering several roads, was awarded upon- competitive bids by the board of pike commissioners of Hawkins county, in the State of Tennessee (hereinafter referred to as commissioners), to Newell, who gave a surety bond in the sum of $80,000, for the faithful performance thereof. The com *135 perisation to Newell was based upon the quality, quantity, and haul of material moved in excavations and fills. Monthly estimates were to be made by the engineer employed by the commissioners, and advances to the extent of 90 per cent thereof were to be paid to Newell; the remaining 10 per cerit was to be retained until final remeasurement and settlement.

Shortly after the contract was awarded to Newell, he sublet about 16 miles of the roads, exclusive of bridge and culvert work requiring masonry, to Blankenship, who was present and participated in the bidding for the entire contract. There is some conflict in the argument as to the terms of the subletting contract, but we are satisfied from the evidence, that Blankenship undertook to carry out Newell’s contract with the commissioners, in respect to the portion of the job which Newell had sublet to him, according to its terms.

As Newell received monthly advances of 90 per cent of the estimates of the engineer upon the work assumed by Blankenship, he paid to him 80 per cent thereof, retaining, according to their agreement, 10 per cent as his profit on the subletting, and the 10 per cent originally provided to be retained by the commissioners. This last-mentioned 10 per cent was due to be paid by Newell to Blankenship, when the work should be finally completed and accepted. This arrangement having been made by Newell and Blankenship, the work progressed for about a year; payments being made by the commissioners to- Newell on the monthly estimates of the engineer, and by Newell to Blankenship, as per the agreement, at the end of which time Blankenship had received $24,699.38.

The commissioners had an engineer by the name of Corn-well in charge of the entire work, and a subengineer by the name of Buley had immediate supervision of the Blankenship portion of the work, under whom and whose instructions Blankenship operated. The defendants offered *136 evidence tending to show that the work assumed by them was fully completed and accepted by Buley.

About this time friction arose between Newell and the commissioners; the latter charging that there had been collusion between Cornwell and Newell, which resulted in gross overestimates of the work as it progressed. They accordingly engaged another engineer by the name of Williams to remeasure, resurvey, reestimate, and reclassify the entire work, who1 reported that, based upon a completed job for the entire work, Newell had been overpaid to the extent of $39,853.95, and that the total amount due to be paid by the commissioners on that part of the work sublet to Blankenship was $20,171.87.

The commissioners then, in the name of Hawkins County, brought suit against Newell for the $39,853.95 overpayment. Newell countered with a suit for damages on account of the breach of a certain part of the contract, covering the macadamizing of certain roads.

In the suit for overpayment, the county recovered a judgment against Newell for the full amount of its claim, $39,-853.95, and, pending an appeal, the two matters were compromised, Newell withdrawing his suit for damages, and the county accepting $30,000 in settlement of the judgment.

Newell asserts that, when the controversy arose between him and the commissioners, Blankenship had not completed his work, and quit the job, leaving unfinished work which .cost him $2,396.20 to finish. After Newell had settled with the county for the judgment on account of overpayment on the entire job, including the part covered by the Blankenship contract, Newell demanded of Blankenship a return of what represented the overpayment on his contract.

Williams, as stated, had reported: That the amount due Newell on the Blankenship portion of the roads was $20,-171.87. Of this ¡Blankenship, under his contract with Newell, was entitled to 90 per cent., $18,154.69. Blankenship had received $24,699.39, and therefore had been overpaid *137 $6,544.69. That the cost to Newell of the unfinished work was $2,396.20. Total claim $8,940.89.

The complaint contains two causes of action — the- first, the above balance of $6,544.69; and the second, the cost of unfinished work, $2,396.20.

In their answer the defendants deny their liability upon both causes of action. They allege collusion between Newell and the engineer, by which the work was overestimated; that the greater bulk of the overestimate was on work outside of the Blankenship contract; that the plaintiff is estopped from claiming a return of any part of said overpayment from the defendants; and that the measurements of the defeendant’s work, made at the time of doing the work, were approximately correct. They also set up a counterclaim for the retained 10 per cent of $2,468.93. Exactly how this amount was arrived at does not appear in the record for appeal. If the amount paid Blankenship, $24,-699.38, represents 80 per cent of the total contract, that total would be $30,874.22, 10 per cent of which would be $3,-087.42.

The jury returned a verdict of $72.73 in favor of Blankenship, evidently disregarding the plaintiff’s first cause of action for the overpayment, and allowing the second for the cost of completing the work. Thus:

Counterclaim.............................$ 2,468.93

Second cause of action .................... 2,396.20

Verdict.....'.....'........................$ 72.73

The exceptions raise the following questions : (1) Did the complaint present an equitable cause of action entitling the plaintiff to a trial according to the forms of equity procedure ? (2) Was there error in the admission of evidence ? (3) Was there error in the exclusion of evidence? (4) Was there error in charging the jury that the litigation in Tennessee between Hawkins county and Newell was not binding upon the Blankenships? (5) Was there error in *138 submitting té the jury issues of fact which were admitted, or as to which there was opposing evidence? (6) Was there error in submitting to the jury the issue of fraud raised in the pleadings, as to which the plaintiff contends there was no evidence ?

As to the first question: Did the complaint present an equitable cause of action entitling the plaintiff to a trial according to the forms of equity procedure?

Counsel on both sides appear to have been confused at the post as to the character of the action, and both, at the trial, shifted their positions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piedmont Interstate Fair Ass'n v. Bean
209 F.2d 942 (Fourth Circuit, 1954)
Tietzel v. Southwestern Const. Co.
94 P.2d 972 (New Mexico Supreme Court, 1939)
American Surety Co. v. Hamrick Mills
4 S.E.2d 308 (Supreme Court of South Carolina, 1939)
Peeples v. Hornik
150 S.E. 802 (Supreme Court of South Carolina, 1929)
Moss v. Burdette
149 S.E. 235 (Supreme Court of South Carolina, 1929)
Georgian Company v. Britton
139 S.E. 217 (Supreme Court of South Carolina, 1927)
People's Bank v. Helms
138 S.E. 622 (Supreme Court of South Carolina, 1927)
Johnson v. Atlantic Coast Line R.
140 S.E. 443 (Supreme Court of South Carolina, 1927)
Moody v. Dudley Lumber Co.
134 S.E. 369 (Supreme Court of South Carolina, 1926)
First National Bank v. Edwards
132 S.E. 824 (Supreme Court of South Carolina, 1926)
Etheredge v. Porter
131 S.E. 768 (Supreme Court of South Carolina, 1926)
Sumter Hardwood Co. v. Fitchette
130 S.E. 881 (Supreme Court of South Carolina, 1925)
Farmers & Merchants National Bank v. Foster
129 S.E. 629 (Supreme Court of South Carolina, 1925)
Keese v. Parnell
128 S.E. 172 (Supreme Court of South Carolina, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
125 S.E. 420, 130 S.C. 131, 1924 S.C. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newell-contracting-co-v-blankenship-sc-1924.