Newbay Corp. v. Annarummo

587 A.2d 63, 1991 R.I. LEXIS 30, 1991 WL 20462
CourtSupreme Court of Rhode Island
DecidedFebruary 20, 1991
Docket90-359-A
StatusPublished
Cited by7 cases

This text of 587 A.2d 63 (Newbay Corp. v. Annarummo) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newbay Corp. v. Annarummo, 587 A.2d 63, 1991 R.I. LEXIS 30, 1991 WL 20462 (R.I. 1991).

Opinion

OPINION

FAY, Chief Justice.

This case comes before us on appeal by the defendants, Michael Annarummo, 1 in his capacity as director of the Department of Environmental Management of the State of Rhode Island (the director), and the Department of Environmental Management of the State of Rhode Island (DEM), from a Superior Court judgment entered in favor of the plaintiffs, Newbay Corporation, Rhode Island Cogeneration Associates, and OEIG Limited Partnership, ordering the director and DEM to issue an air permit to the plaintiffs. For the reasons set forth herein, we deny the defendants’ appeal and affirm the judgment of the Superior Court.

Newbay Corporation is a Delaware corporation with its principal place of business in Rockland, Massachusetts. The OEIG Limited Partnership is a Delaware limited partnership. Rhode Island Cogeneration Associates is a Delaware general partnership and is also a joint venture with New-bay Corporation as its managing general partner and OEIG Limited Partnership as the other partner. Collectively plaintiffs are known as and shall be referred to as Newbay.

Newbay plans to build and operate a cogeneration facility in the city of East Providence. The facility would have the capability of generating 72 megawatts of electricity and 20,000 pounds per hour of steam. The facility would also be a source of sulfur dioxide (S02) pollution.

In accordance with these plans Newbay filed an application for an air permit with DEM in March 1987. Thereafter a hearing officer was appointed by the director to conduct formal hearings on Newbay’s application. The formal hearings began in January 1989 and concluded the following June. On or about December 29, 1989, the hearing officer submitted a decision on the matter to the director, recommending that the air permit be issued. The hearing officer’s report concluded that Newbay would meet or exceed every established regulation.

On March 5, 1990, the director released a final decision and order (final decision) regarding Newbay’s air-permit application along with the hearing officer’s recommendation. The director adopted in full the recommendation of the hearing officer, with the exception of two additional conditions. The director’s final decision stated as follows:

“1. [T]he Decision of the hearing officer, except as modified herein is adopted.
“2. The permit shall issue only when and if:
(A) There is a demonstration by New-bay to the Division of Air & Hazardous Material * * * that the proposed facility will meet the short term S02 standards adopted by DEM.
(B) No conflict exists among the permits, insuring that the interaction of the DEM permits is protective of human health and the environment.” 2

The short-term S02 standard set forth in the first additional condition was nonexistent when imposed and continues to be so at the present time. Despite this fact the director stated in the final decision that Newbay would not be entitled to an air permit “until such time as a short term S02 standard is adopted by R.I. DEM which is demonstrated to be protective of human health, and a further demonstration is made by Newbay that emissions from the proposed plant will not violate this standard.”

Approximately one week after the release of the director’s final decision, New-bay filed a complaint pursuant to G.L.1956 (1988 Reenactment) § 42-35-7 in the Superior Court. Section 42-35-7 allows a party *65 to contest the validity or applicability of any agency rule when the rule or its threatened application impairs or threatens to impair a legal right or privilege of the contesting party. 3 In its complaint New-bay sought a declaratory judgment, as well as a writ of mandamus and injunctive relief, to compel the director and DEM to issue the air permit. In support of this claim Newbay alleged that the additional condition imposed by the director regarding short-term SO2 emissions was, in effect, a new agency rule and that this new rule was illegal because it was adopted and applied in violation of the rule-making procedures of the Administrative Procedures Act. See § 42-35-3. Additionally Newbay asserted that because it had met all other requirements, it was legally entitled to issuance of the air permit.

The defendants countered by seeking dismissal of the action, averring that the suit, premised upon § 42-35-7, was inappropriate because the additional condition was not a new agency rule and therefore was not subject to the rule-making procedures of § 42-35-3. In addition defendants alleged that because the hearing on New-bay’s application for an air permit was a contested case pursuant to § 42-35-9, any review of the final decision would be appropriate only pursuant to § 42-35-15. Section 42-35-15 provides an avenue of review for any person who is aggrieved by a final order in a contested case after all administrative remedies available within the agency have been exhausted.

The trial justice determined that the additional condition was in fact a new agency rule. Because this rule impaired the legal rights of Newbay, the trial justice held, the court was entitled to determine the rule’s validity. The trial justice further held that in order for a new agency rule to be valid, it must have been enacted in compliance with the rule-making procedures of § 42-35-3. After finding that the necessary procedures had not been followed, the trial justice concluded that the new agency rule was invalid.

Relying upon this conclusion, the trial justice stated that because Newbay had met every other requirement for the issuance of the air permit, the permit should be issued. Thereafter the trial justice issued a writ of mandamus ordering the director and DEM to issue an air permit to Newbay. That order was subsequently stayed pending the outcome of this appeal.

We turn our attention initially to the question of whether § 42-35-7 was the appropriate avenue of relief. Section 42-35-7 states:

“The validity or applicability of any rule may be determined in an action for declaratory judgment in the superior court of Providence County, when it is alleged that the rule, or its threatened application, interferes with or impairs, or threatens to interfere with or impair, the legal rights or privileges of the plaintiff. The agency shall be made a party to the action. A declaratory judgment may be rendered whether or not the plaintiff has requested the agency to pass upon the validity or applicability of the rule in question.”

A “rule” is defined in § 42-35-l(h) as

“each agency statement of general applicability that implements, interprets, or prescribes law or policy or describes the organization, procedure, or practice requirements of any agency. The term includes the amendment or repeal of a prior rule, but does not include (1) statements concerning only the internal management of an agency and not affecting private rights or procedures available to the public, or (2) declaratory rulings issued pursuant to § 42-35-8, (3) intra-agency memoranda, or (4) an order.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Richmond v. Rhode Island Department of Environmental Management
941 A.2d 151 (Supreme Court of Rhode Island, 2008)
Birchwood Realty, Inc. v. Grant
627 A.2d 827 (Supreme Court of Rhode Island, 1993)
Newbay Corp. v. Sisson
621 A.2d 1250 (Supreme Court of Rhode Island, 1993)
Lynch v. Dionne, 92-643 (1992)
Superior Court of Rhode Island, 1992

Cite This Page — Counsel Stack

Bluebook (online)
587 A.2d 63, 1991 R.I. LEXIS 30, 1991 WL 20462, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newbay-corp-v-annarummo-ri-1991.