New York-Connecticut Development Corp. v. Blinds-To-Go

159 A.3d 892, 449 N.J. Super. 542
CourtNew Jersey Superior Court Appellate Division
DecidedApril 10, 2017
DocketA-5660-14T4
StatusPublished
Cited by14 cases

This text of 159 A.3d 892 (New York-Connecticut Development Corp. v. Blinds-To-Go) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New York-Connecticut Development Corp. v. Blinds-To-Go, 159 A.3d 892, 449 N.J. Super. 542 (N.J. Ct. App. 2017).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-5660-14T4

NEW YORK-CONNECTICUT DEVELOPMENT CORP., APPROVED FOR PUBLICATION Plaintiff-Respondent/ AS REDACTED Cross-Appellant, April 10, 2017

v. APPELLATE DIVISION

BLINDS-TO-GO (U.S.) INC.,

Defendant/Third-Party Plaintiff-Appellant/ Cross-Respondent,

v.

ANTHONY NARDOZZI; CHRIS YEATES; JM HALEY CORP.; BRAVANTE AUTOMATIC SPRINKLER CORP.; COUNTY GLASS & METAL INSTALLERS, INC.; THYSSENKRUPP ELEVATOR CORPORATION; JUSTAN ELECTRICAL CONTRACTING, INC.; CURTI & ASSOCIATES, LTD.; UNIQUE MECHANICAL SERVICES, LLC; WHALEN BEREZ GROUP, LLC,

Third-Party Defendants- Respondents. ___________________________________

UNIQUE MECHANICAL SERVICES, LLC,

Second Third-Party Plaintiff- Respondent,

NEW YORK-CONNECTICUT DEVELOPMENT CORP.,

Second Third-Party Defendant- Respondent. ___________________________________

COUNTY GLASS & METAL INSTALLERS, INC.,

Fourth-Party Plaintiff- Respondent,

NEW YORK-CONNECTICUT DEVELOPMENT CORP., and ANTHONY NARDOZZI, JR.,

Fourth-Party Defendants- Respondents. ___________________________________

Argued February 13, 2017 – Decided April 10, 2017

Before Judges Sabatino, Haas, and Currier.

On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-5440-12.

David R. King argued the cause for appellant/cross-respondent Blinds-To-Go (Herrick, Feinstein LLP, attorneys; Mr. King, K. Heather Robinson, and Chantelle L. Aris, on the briefs).

Jessica L. Rothman (Ingram Yuzek Gainen Carroll & Bertolotti, LLP) of the New York bar, admitted pro hac vice, argued the cause for respondent/cross-appellant New York- Connecticut Development Corp. (Ingram Yuzek Gainen Carroll & Bertolotti, LLP, attorneys; Dean G. Yuzek and Kimberly L. Quintano, on the briefs).

2 A-5660-14T4 Jonathan H. Krukas argued the cause for respondent Unique Mechanical Services (Quinn McCabe LLP, attorneys; Mr. Krukas, on the brief).

Sean E. Regan argued the cause for respondent Whalen Berez Group (Giordano, Halleran & Ciesla, attorneys; Mr. Regan, of counsel and on the brief).

Steven R. Rowland argued the cause for respondent Justan Electrical Contracting (Brown Moskowitz & Kallen, P.C., attorneys; Mr. Rowland, of counsel and on the brief).

Christopher G. Fusco argued the cause for respondent Bravante Automatic Sprinkler Corp. (Callahan & Fusco, LLC, attorneys; Matthew Szymczak, of counsel and on the brief).

Kelly A. Zampino argued the cause for respondent County Glass & Metal Installers, Inc. (Hartmann, Doherty, Rosa, Berman, Bulbulia, attorneys; Richard M. Rosa, on the brief).

The opinion of the court was delivered by

CURRIER, J.A.D.

In this matter arising out of the construction of a

building, we address whether a verdict can be sustained where

the jury found that plaintiff, New York-Connecticut Development

Corp. (NYCT), breached the pertinent contract, but nevertheless,

awarded it damages under a quantum meruit theory. We conclude

that once the jury determined that an express contract existed

between the parties, it was erroneous for it to be directed to a

3 A-5660-14T4 consideration of quantum meruit. Consequently, we are

constrained to reverse and remand for a new trial.

I.

Plaintiff submitted a successful bid and was selected by

defendant, Blinds-To-Go (U.S.) Inc. (BTG), as the general

contractor to build its corporate headquarters. In February

2011, the parties signed a document entitled "GC [Guaranteed

Cost] Contract Cost Plus Fee with GMP." The agreement contained

the following language: "Based on the current set of drawings

and information received to this date NYCT will enter into a

contract with BTG with a Guaranteed Maximum Price, and a

completion date of September 15th 2011" subject to conditions

addressed within the agreement.

The agreement provided for a guaranteed price of $3,800,000

for the hard cost budget and a fixed GC fee of $200,000, setting

the project's total price at $4,000,000.

Prior to the start of the project, the parties agreed to

the use of change orders prepared by the contractor to advise

the owner of additional work that was required beyond what was

contained in the plans or the contract. Plaintiff was

instructed to submit the change orders to the architect, Peter

Wells. To request payment, plaintiff submitted a requisition to

defendant. The document listed the new contract price resulting

4 A-5660-14T4 from the addition of change orders and the payment due. As the

construction progressed, plaintiff submitted thirteen change

orders contained in ten requisitions totaling $461,000 for

defendant's review and approval. After several meetings to

discuss the orders, they were approved in August 2011.

Defendant advised plaintiff that as the scope of the project was

settled, the price should also be finalized as it considered the

approved requisitions to be a complete list of additional work.

The building was not delivered to defendant on September

15, 2011, as per the contract. Although several new deadlines

were set, it was not until March 16, 2012, that a certificate of

occupancy (CO) was delivered by plaintiff.

On March 6, plaintiff presented an additional requisition

(Requisition 11) for defendant's consideration. Defendant

informed that it would pay the requisition upon receipt of the

CO, the release of liens and the completion of the punch list.

In response, plaintiff told defendant it did not intend to

return to the job site. Although the requisition was paid

several days later, plaintiff did no further work and failed to

complete the punch list.

Plaintiff submitted a final requisition (Requisition 12) in

June 2012 containing seventeen additional unapproved change

orders with charges in excess of $1,000,000. Defendant offered

5 A-5660-14T4 to compromise the requested amount, but received no response.

Plaintiff filed this action in July 2012.

II.

Plaintiff's complaint alleged a breach of contract or, in

the alternative, a claim for quantum meruit against defendant.

Defendant filed an answer and counterclaim for plaintiff's

failure to complete the work in accordance with the contract,

and a third party complaint against several subcontractors. The

subcontractors in turn counterclaimed against defendant for the

establishment of a lien fund and filed fourth party complaints

against plaintiff for breach of contract.

[At the court's direction, the published version of this opinion omits the remainder of Section II concerning pre-trial procedural facts; Sections III(E) and (F) concerning the Prompt Payment Act and an attorney's charging lien, N.J.S.A. 2A:13-5; Sections IV(C), (D), and (E) regarding a lien fund, a discovery issue, and expert testimony dispute; and Sections V(A) and (B) concerning the PPA and attorney's charging lien. R. 1:36-2(a).]

III.

A.

Prior to trial, defendant presented a summary judgment

motion to dismiss the quantum meruit claim. The motion was

denied as untimely under Rule 4:46-1 as the return date was less

than thirty days prior to the trial date. On the first day of

6 A-5660-14T4 trial, defendant advised the judge it had filed an in limine

motion to dismiss the quantum meruit claim. The judge told

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
159 A.3d 892, 449 N.J. Super. 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-york-connecticut-development-corp-v-blinds-to-go-njsuperctappdiv-2017.