New Jersey Power & Light Co. v. State of New Jersey Department of Public Utilities

104 A.2d 1, 15 N.J. 82, 1954 N.J. LEXIS 258
CourtSupreme Court of New Jersey
DecidedMarch 29, 1954
StatusPublished
Cited by11 cases

This text of 104 A.2d 1 (New Jersey Power & Light Co. v. State of New Jersey Department of Public Utilities) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Jersey Power & Light Co. v. State of New Jersey Department of Public Utilities, 104 A.2d 1, 15 N.J. 82, 1954 N.J. LEXIS 258 (N.J. 1954).

Opinion

The opinion of the court was delivered by

Vanderbilt, C. J.

This appeal by the New Jersey Power & Light Company from a decision of the Board of Public Utility Commissioners dismissing its application for a surcharge of 5% on its newly established rates comes before us on the company’s petition for certification granted by us, 14 N. J. 15 (1953).

I. The Pacts

In October 1952 the company applied to the Board for a revision of its rates so that it could obtain additional revenue of $1,400,000 annually. In a decision handed down in May, 1953 the Board granted rate increases that would allow the company additional revenue of $991,141 a year, based on a return of 5.85%. Uo appeal was taken from this decision.

[84]*84On June 3, 1953, two days after the new schedule of rates went into operation, the company filed with the Board a notice that effective July 15, 1953 it would increase its rates by the addition of a surcharge of 5% to the new rates, effective for two years to permit the company to recoup a deficiency of $1,238,000 in gross revenue that had resulted under the order of the Board denying the application of the company for increased rates. The purpose of this surcharge was to restore to the company an alleged deficiency in net income of $578,000 in 1951, 1952 and the first five months of 1953 under the Board’s order in the application of 1950 and thus to permit the company to obtain the minimum return contemplated by the earlier order of the Board.

In the proceedings commenced in 1950 the Board found the company’s rate of return for the year 1950 after adjustments in revenues and expenses to be 6.52% on a net original cost rate base (91 P. U. R. (N. S.) 331, 340). This return the Board found not unreasonable, stating: “Actual operating results thus far available for 1951 do not support the company’s claim that 1951 earnings will be lower than experienced in 1950. If anything there are significant indications that the reverse may be true.” (91 P. U. R. (N. S.) 331, 341). The actual return determined on the basis of the same adjustments to earnings as those made by the Board in the 1950 case and on a rate base determined in the same manner as that found by the Board in that case, earned by the company in 1951 was 5.19%, in 1952 was 4.65% and, for the five months ending May 31, 1953 was 1.99%, which is equivalent to 4.78% on an annual basis.

The company’s calculations of the deficiencies in returns which the company suffered as a direct result of the Board’s action in the 1950 rate case were submitted on different bases:

Eirst, the deficiencies suffered during 1951, 1952 and the first five months of 1953 were calculated by taking the amount by which the gross revenue was less than the anticipated gross revenue applying the lower range of reasonable return found by the Board in the 1950 proceedings, i. e., 5.53% on the net original cost rate base. On this basis, the deficiencies [85]*85in returns aggregated $589,000. Because of income taxes and gross receipt taxes, it would require $1,261,700 in gross revenues to recoup these deficiencies;

Second, the deficiencies suffered by the company were calculated by limiting them to 1952 and the first five months of 1953 and utilizing the amount below the allowable rate of return of 5.85% on the net original cost rate base found by the Board on May 13, 1953 in the company’s 1952 rate proceeding as a result of which, as hereinbefore stated, the company was permitted to put increased rates into effect on June 1, 1953. In the 1952 proceedings the Board expressly admitted the existence of a deficiency in returns in 1952 of $463,150 below the allowed 5.85% rate of return and conceded the existence of a deficiency in returns for the first five months of 1953 of $185,000 when calculated on the same basis. Thus the total deficiencies for 1952 and the first five months of 1953 aggregated $647,000 and the gross revenues required to make good such deficiencies amounted to $1,384,-600;

Third, calculations of deficiencies in returns based upon the upper range of reasonableness of rate return found by the Board in the 1950 proceeding, i. e., 6.52%, were also submitted. The deficits under this calculation were still greater both as to deficits in returns and required gross revenue to recoup the deficiency in such returns.

The amount of deficiencies in returns which the company sought to recover in this proceeding was slightly below the lowest of the three amounts so calculated, i. e., $587,000, and it is this amount which is the subject of appeal.

The decision of the Board in the 1950 rate case stated that rates of return from 5.53% to 6.52% lie within the range of reasonableness (91 P. U. R. (N. S.) 331, 365). The company’s proofs in this proceeding established deficiencies in returns for the years 1951, 1952 and five months ending May 31, 1953, below the lower range of rate of return above stated. The company’s proposed recoupment of deficiencies in returns through a 5% surcharge was estimated to be realized over a period of about two years in which event [86]*86the surcharge of 5% would be terminated. The Board in the 1952 rate ease found that the company was entitled to a rate of return of 5.85% on a net original cost rate based on operations for the year 1952; that this rate of return had not been earned by the company in the year 1952 and that it had suffered a deficiency in return of $463,150 for that year, the equivalent of $991,141 deficiency in gross revenue.

At the conclusion of the company’s case the State and two large consumers, the Riegel Paper Corporation and the Sanco Piece Dye Works, Inc., which had been permitted to intervene, moved for the dismissal of the petition for the surcharge “upon the ground that the proposed surcharge is based upon erroneous premises of fact and law, and upon unwarranted assumptions made in the statements, testimony and exhibits presented by New Jersey Power & Light Company.” They argued that the company erred in its contention that in the 1950 proceeding the Board had actually set a minimum return of 5.53% and also that the Board lacked the power to permit such a surcharge. The Board granted the motion and from this decision the company appeals.

II. The Doctrine of the Hackensack Water Company Case

The company rests its case primarily on Hackensack Water Company v. Board of Public Utility Commissioners, 98 N. J. L. 41 (Sup. Ct. Dec. 7, 1922), 100 N. J. L. 177 (E. & A. April 17, 1924). The case, which was decided by a single justice in the former Supreme Court and affirmed in the Court of Errors and Appeals on the opinion below, held that a public utility is entitled to recoup deficits in operations by temporary surcharges added to its regular rates. In that case the Board had relied on Galveston Electric Co. v. City of Galveston, 258 U. S. 388, 42 S. Ct. 351, 66 L. Ed. 678 (1922), in denying such surcharges to the company, but the court, though likewise relying on that case, gave it an interpretation diametrically opposed to that of the Board. The Galveston case, decided seven months before the Haclcensach [87]*87ease, was the first expression of the.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of the Petition of Middlesex Water Company, Etc.
New Jersey Superior Court App Division, 2025
Penpac v. Passaic County Utilities
843 A.2d 1153 (New Jersey Superior Court App Division, 2004)
Elizabethtown Water Co. v. New Jersey Board of Public Utilities
527 A.2d 354 (Supreme Court of New Jersey, 1987)
Public Service Commission v. Diamond State Telephone Co.
468 A.2d 1285 (Supreme Court of Delaware, 1983)
Narragansett Electric Co. v. Burke
415 A.2d 177 (Supreme Court of Rhode Island, 1980)
State Ex Rel. Utilities Commission v. Edmisten
232 S.E.2d 184 (Supreme Court of North Carolina, 1977)
Mississippi Public Service Commission v. Home Telephone Co.
110 So. 2d 618 (Mississippi Supreme Court, 1959)
Arrow Builders Supply Corp. v. Hudson Terrace Apartments, Inc.
105 A.2d 387 (Supreme Court of New Jersey, 1954)
In Re NJ Power & Light Co.
104 A.2d 1 (Supreme Court of New Jersey, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
104 A.2d 1, 15 N.J. 82, 1954 N.J. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-jersey-power-light-co-v-state-of-new-jersey-department-of-public-nj-1954.