New Jersey Highway Authority v. Renner

114 A.2d 555, 18 N.J. 485, 1955 N.J. LEXIS 272
Supreme Court of New Jersey·Decided May 31, 1955·Published·Cited by 77 cases

Opinion

*488 The opinion of the court was delivered by

Jacobs, J.

The Chancery Division granted plaintiff’s claim for specific performance of the defendant’s agreement to convey premises in Woodbridge and denied the defendant’s counterclaim for the alleged wrongful act of the plaintiff in delaying or preventing her removal of the building located thereon and then demolishing it. The defendant appealed to the Appellate Division contending that there was error in the dismissal of her counterclaim and that she was entitled to a jury trial on the issue which it raised. This contention was sustained in an opinion by Judge Clapp reported in 32 N. J. Super. 197 (App. Div. 1954), and the counterclaim was remanded for trial. We granted certification under R. R. 1:10-2. See 17 N. J. 226 (1955).

Since 1952 the plaintiff has been engaged in building the Garden State Parkway. See Town of Bloomfield v. New Jersey Highway Authority, 18 N. J. 237 (1955). In 1953 it determined that the defendant’s property in Woodbridge would be required for the Parkway and it negotiated with the defendant for its purchase. On March 21, 1953 a contract was entered into between the plaintiff and the defendant which provided that the property would be conveyed for the sum of $17,500; the contract stated that the defendant could remove the building on the property on or before April 1, 1953. The building was never removed by the defendant but was demolished by the plaintiff’s contractor on May 27, 1953 and the land was actually occupied by the plaintiff and used for Parkway purposes. On May 19, 1953 the plaintiff instituted an action in the Law Division demanding judgment for possession and specific performance, preliminary injunctive relief, and mesne damages. This action was dismissed by a stipulation dated June 4, 1953. The plaintiff contends that the stipulation was signed pursuant to an agreement between counsel that the defendant would perform the contract and the parties would “exchange general releases”; the defendant contends that no one had authority to enter into such agreement on her behalf and general releases were never executed.

*489 On September 24, 1953 the plaintiff instituted its action in the Chancery Division which demanded that the defendant be required to perform specifically her agreement of March 21, 1953 and that she pay damages in the sum of $10,000 plus costs. She filed answer and counterclaim which indicated that she was willing to deliver a deed for the premises provided the plaintiff would reimburse her for “consequential damages to her property”; her claim (apart from matters which have been abandoned) rested generally upon the assertion that the plaintiff had “interfered with and placed obstacles” to the removal of the building to her substantial damage. Her story was substantially as follows: In March 1953'she asked Mr. Adamowicz, a house mover, for an estimate of the cost of removing her building to a new site which had been selected tentatively; he inspected the building and surroundings and told her the removal would cost $6,500. Thereafter she signed the contract of March 21, 1953 with the plaintiff. At about that time the plaintiff dug an enormous moat or ditch in the rear of the building and in the path of the contemplated movement of the building; the porch on the building was “knocked off in order that the line of the moat may be made straight.” When Mr. Adamowicz saw the moat he told the defendant that because of it he could not abide by his original estimate of $6,500 and that it would cost an additional $10,000 ($16,500 in all) for the moving of the building. Although the defendant made efforts to obtain other house movers she was unable to make satisfactory arrangements in time and the building (which was of substantial value to her) was partially dismantled and then demolished by the plaintiff without compensation for her damages.

The defendant contends and the Appellate Division found that the Chancery Division’s determination that the plaintiff was entitled to specific performance of the March 21 agreement did not dispose of her counterclaim which must await trial by jury. The pretrial order set forth that there were equitable as well as legal issues involved and that “all equitable issues arising out of the complaint, the defense and counter *490 claim will be tried by the court; all law issues will be tried by a jury.” Both parties agreed “to permit the jury trial to be had in Mercer County where the equity case will be tried.” On its own case the plaintiff simply introduced the March 21 agreement and called the defendant as its witness to testify with respect to her refusal or failure to execute a deed to the premises. The defendant then called her witnesses; they were Mr. Sladkus, attorney for the defendant in the negotiations which resulted in the March 21 agreement, the defendant Mary Eenner and her daughter Marianne Eenner. Their testimony included references to the digging of the moat and its effect on the contemplated moving of the building; Mr. Sladkus also testified that although the agreement provided that the defendant could remove the building on or before April 1 he was told by the plaintiff’s representative that the defendant could have “a few weeks after that.” At the close of the testimony on the defendant’s behalf her counsel remarked, “That is the defendant’s ease at this time, Judge.” Counsel for the plaintiff then inquired whether “that includes the counterclaim as well as the defense” and counsel for the defendant said, “Of course not.” The trial judge then said, “The counterclaim is a jury trial” and counsel for the defendant remarked, “That is right. That has all been set forth.” Finally, the trial judge remarked, “The theory of the trial of this case was that we first try the equity case. If the plaintiff succeeds on the equity case there would be no necessity for the law case. We take one step at a time.”

After the foregoing colloquy, counsel for the plaintiff called an employee of the Lawyers-Clinton Title Insurance Company of New Jersey who testified that she had asked the defendant to sign a deed but that the defendant had refused, and Mr. Gillette, the attorney for the defendant who signed the stipulation dismissing the Law Division action and testified with respect thereto. The defendant’s counsel then recalled Mr. Sladkus, the defendant Mary Eenner and her daughter Marianne, who testified generally with respect to Mr. Gillette’s participation in the Law Division action. No further witnesses were called and although the record is somewhat obscure *491 there does not appear to have been any real trial of the issue presented in the counterclaim. The plaintiff called no one to testify with respect to the digging of the moat and any effect it may have had on the contemplated removal of the building; it introduced no testimony to controvert the defendant’s story as hereinbefore outlined or the inferences to be drawn therefrom; and it produced no evidence to indicate that the moat was not across a proper route of removal contemplated by the parties or that there were other equally suitable routes. None of the persons who authorized the moat and directed its path and construction and none of the house movers testified.

Free access — add to your briefcase to read the full text and ask questions with AI

New Jersey Highway Authority v. Renner, 114 A.2d 555, 18 N.J. 485, 1955 N.J. LEXIS 272 (N.J. 1955).

114 A.2d 555 (New Jersey Highway Authority v. Renner) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Little Harris v. New Jersey Department of Corrections
New Jersey Superior Court App Division, 2025
Kohn & Kohn Realty, LLC v. Margaret A. Uhrich
New Jersey Superior Court App Division, 2024
B.G. VS. P.G. (FM-02-2243-13, BERGEN COUNTY AND STATEWIDE)
New Jersey Superior Court App Division, 2020
In the MATTER OF Corey CORBO, Union City Police Department.
209 A.3d 839 (Supreme Court of New Jersey, 2019)
Salazar v. MKGC + Design
206 A.3d 447 (New Jersey Superior Court App Division, 2019)
New Jersey Division of Youth & Family Services v. C.H.
50 A.3d 93 (New Jersey Superior Court App Division, 2012)
Klier v. Sordoni Skanska Const. Co.
766 A.2d 761 (New Jersey Superior Court App Division, 2001)
Rocci v. Ecole Secondaire MacDonald-cartier
755 A.2d 583 (Supreme Court of New Jersey, 2000)
Sperling v. Board of Review
720 A.2d 607 (Supreme Court of New Jersey, 1998)
Environmental Ins. Declaratory Judgment Actions
693 A.2d 844 (Supreme Court of New Jersey, 1997)
Ciba-Geigy Corp. v. Liberty Mutual Insurance
693 A.2d 844 (Supreme Court of New Jersey, 1997)
Nubenco Enterprises, Inc. v. Inversiones Barberena, S.A.
963 F. Supp. 353 (D. New Jersey, 1997)
Wolfersberger v. Borough of Point Pleasant Beach
702 A.2d 1294 (New Jersey Superior Court App Division, 1996)
International Fidelity Insurance v. Goldberg
680 A.2d 1124 (New Jersey Superior Court App Division, 1996)
Lyn-Anna Properties, Ltd. v. Harborview Development Corp.
678 A.2d 683 (Supreme Court of New Jersey, 1996)
Prevratil v. Mohr
678 A.2d 243 (Supreme Court of New Jersey, 1996)
DiTrolio v. Antiles
662 A.2d 494 (Supreme Court of New Jersey, 1995)
Circle Chevrolet Co. v. Giordano, Halleran & Ciesla
662 A.2d 509 (Supreme Court of New Jersey, 1995)