Nevada Power Co. v. Flour Illinois

837 P.2d 1354, 108 Nev. 638, 1992 Nev. LEXIS 134
CourtNevada Supreme Court
DecidedAugust 20, 1992
Docket21524
StatusPublished
Cited by34 cases

This text of 837 P.2d 1354 (Nevada Power Co. v. Flour Illinois) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nevada Power Co. v. Flour Illinois, 837 P.2d 1354, 108 Nev. 638, 1992 Nev. LEXIS 134 (Neb. 1992).

Opinion

*640 OPINION

Per Curiam:

This appeal arises from the entry of a district court order and judgment. The order dismissed with prejudice the civil action of appellants Nevada Power Company (“NPC”) and California Department of Water Resources (“CDWR”), and awarded respondents their attorneys’ fees and costs. In the subsequent judgment, the court ordered NPC and CDWR to pay the respondents more than 5.2 million dollars in attorneys’ fees and costs. On appeal, NPC and CDWR contend that the district court erred in imposing NRCP 37(b) sanctions without first holding an eviden-tiary hearing. We agree.

Factual Background

The underlying action in this case involved an allegedly defective concrete mechanical draft cooling tower at the Reid Gardner Generating Plant Unit # 4, located in Clark County, Nevada. The Reid Gardner plant generates electric power and is jointly owned by NPC and CDWR. When the Reid Gardner plant was constructed, the cooling tower was built as an integral part of the plant. 1 This cooling tower was constructed, tested, engineered, and designed by respondents.

According to NPC and CDWR, the concrete in the cooling tower began to deteriorate soon after the cooling tower was put into operation, and the tower had to be taken out of service after only five years of use. In 1986, NPC and CDWR sued the respondents for breach of contract, breach of implied and express warranties, negligence, affirmative misrepresentation, and strict products liability. 2 The parties then proceeded with discovery, *641 which did not progress smoothly. Counsel for NPC and CDWR committed several discovery abuses for which monetary sanctions were imposed.

Believing that the concrete cooling tower was defective, NPC and CDWR constructed a wooden cooling tower to replace it. According to NPC, the concrete cooling tower had to be taken out of service so that a portion of the “existing water catchment basin” needed to operate the replacement tower could be connected to the replacement tower. In addition, part of the concrete tower had to be demolished because its size and location interfered with the necessary air flow to the replacement tower.

In early March 1988, counsel for NPC and CDWR informed respondents that the concrete cooling tower would be demolished on or about October 1, 1988. Respondents then filed motions for an order prohibiting the planned demolition. Subsequently, on September 29, 1988, the district court entered an order establishing an expedited schedule for discovery and providing that “[n]o portion of the cooling tower or cooling tower appurtenances shall be destroyed, demolished, dismantled, or altered in any way until such time as this court specifically grants approval of the same.”

Then, on December 11, 1988, NPC filed a motion with the district court for partial demolition of the concrete cooling tower. At the same time, NPC sought a stipulation from all of the respondents. This stipulation, entered as an order on December 20, 1988, states, in relevant part:

[NPC] shall, with any necessary leave of court, demolish the southerly four cells of the cooling tower which is the subject of this dispute any time after February 7, 1989, and [NPC] anticipate^] demolition of the remaining three cells during an outage scheduled for the fall, 1989. [NPC] shall store the demolished material from the cells on the mesa adjacent to the Reid Gardner Unit No. 4 site. [Respondents] shall have free and immediate access to the stored material between the hours of 8:00 a.m. and 5:00 p.m., 7 days a week, upon 48 hours notice to [NPC], to conduct any investigation or tests they deem necessary.
Moreover, it is understood by all parties that this Stipulation is entered into for the purposes of facilitating scheduling of further inspections by the [respondents], and to permit NEVADA POWER COMPANY to establish a schedule for all necessary work to demolish the existing cooling tower, and to place the new Reid Gardner Unit No. 4 cooling tower in operation.

NPC and CDWR demolished the first portion of the cooling tower in March 1989 and stored the demolished material on the *642 mesa as ordered by the district court. Thereafter, on November 19, 1989, NPC notified respondents that it intended to demolish the remainder of the tower sometime during the “Spring outage,” which would begin on April 1, 1990, and end on May 19, 1990. On April 5, 1990, during a hearing on several discovery motions, the district court and respondents learned that NPC and CDWR were actually proceeding with the final demolition. The court then terminated the hearing. After the hearing was terminated, NPC and CDWR continued to demolish what remained of the cooling tower. The debris was then moved by truck to an adjacent site and buried under backfill.

On April 6, 1990, respondents filed a joint “ex parte application for order to show cause and motion to dismiss complaint pursuant to NRCP 37(b)(2) and EDCR 7.60.” On the same day, the court issued an order to show cause. In a subsequent brief, respondents contended that the appellant’s misconduct, including the destruction of the tower and various discovery abuses, justified a finding of contempt and sanctions. Specifically, respondents sought dismissal of the complaint and an award of attorneys’ fees and costs. In support, respondents attached affidavits describing additional tests and analyses they would have performed if the remaining portion of the tower had not been demolished and buried.

On April 16, 1990, NPC and CDWR submitted a response to the order to show cause and an opposition to the motion to dismiss. In these papers and exhibits, NPC and CDWR disclaimed any intention to disobey willfully the court’s orders, proposed alternate sanctions to dismissal, and requested that the court hold an evidentiary hearing on willfulness and prejudice.

On May 3, 1990, the court held a hearing on contempt and the motion to dismiss. Respondents introduced a videotape showing the tower’s demolition and argued that the case should be dismissed. Respondents also relied on their experts’ affidavits to demonstrate “irreparable prejudice” resulting from the tower’s destruction. Counsel for NPC and CDWR argued that they had interpreted the December 20, 1988, order in good faith as allowing the demolition and that the respondents had already sufficiently inspected and tested the demolished tower.

On June 15, 1990, the court entered findings of fact and conclusions of law, including the following:

(1) Its September 27, 1988 order had not been vacated or modified by the December 20, 1988 order, which gave NPC permission to demolish only four cells, and the order had been willfully violated;
(2) The tower’s destruction and the burial of its remains caused irreparable prejudice to respondents;
*643 (3) Dismissal with prejudice was “the only means to cure the irreparable prejudice”;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SOLDO-ALLESIO v. FERGUSON
141 Nev. Adv. Op. No. 9 (Court of Appeals of Nevada, 2025)
Myers v. Haskins
513 P.3d 527 (Court of Appeals of Nevada, 2022)
MYERS v. HASKINS (CHILD CUSTODY)
2022 NV 51 (Nevada Supreme Court, 2022)
Reed v. Reed (Child Custody)
Nevada Supreme Court, 2022
Fox Vs. Warren C/W 81212
Nevada Supreme Court, 2021
DETWILER VS. DIST. CT. (BAKER BOYER NAT'L BANK)
2021 NV 18 (Nevada Supreme Court, 2021)
Agwara v. Agwara
Nevada Supreme Court, 2019
MEI-GSR HOLDINGS, LLC VS. PEPPERMILL CASINOS, INC.
2018 NV 31 (Nevada Supreme Court, 2018)
Mei-Gsr Holdings, LLC v. Peppermill Casinos, Inc.
416 P.3d 249 (Nevada Supreme Court, 2018)
MIZRACHI VS. MIZRACHI (CHILD CUSTODY)
2016 NV 66 (Nevada Supreme Court, 2016)
Mizrachi v. Mizrachi
Court of Appeals of Nevada, 2016
Mizrachi v. Mizrachi
2016 NV 66 (Nevada Supreme Court, 2016)
Anderson v. Sanchez
2015 NV 51 (Nevada Supreme Court, 2015)
Jernee v. Kennametal, Inc.
Nevada Supreme Court, 2015
Blanco v. Blanco
311 P.3d 1170 (Nevada Supreme Court, 2013)
Berkson v. LePome
245 P.3d 560 (Nevada Supreme Court, 2010)
Bahena v. Goodyear Tire & Rubber Co.
235 P.3d 592 (Nevada Supreme Court, 2010)
Bass-Davis v. Davis
134 P.3d 103 (Nevada Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
837 P.2d 1354, 108 Nev. 638, 1992 Nev. LEXIS 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nevada-power-co-v-flour-illinois-nev-1992.