Network Documentation & Implementation, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJune 3, 2020
DocketASBCA No. 61804
StatusPublished

This text of Network Documentation & Implementation, Inc. (Network Documentation & Implementation, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Network Documentation & Implementation, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Network Documentation & Implementation, Inc. ) ASBCA No. 61804 ) Under Contract No. 000000-00-0-0000 )

APPEARANCE FOR THE APPELLANT: Mr. Jorge McBain Owner

APPEARANCES FOR THE GOVERNMENT: William E. Brazis, Jr., Esq. DISA General Counsel Travis L. Vaughan, Esq. Trial Attorney Defense Information Systems Agency Fort Meade, MD

OPINION BY ADMINISTRATIVE JUDGE WITWER ON THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION AND FAILURE TO STATE A CLAIM

Network Documentation & Implementation, Inc. (NDI) claims that it is contractually entitled to payment in the amount of $2,036,680.24 for artificial intelligence services it provided to the Defense Information Systems Agency (DISA). The government moves to dismiss the appeal for lack of jurisdiction, contending that NDI is a subcontractor with whom the government has no privity of contract. The government also moves to dismiss the appeal for failure to state a claim, contending that NDI’s complaint fails to allege the elements of an implied-in-fact contract. We deny the government’s motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

A. Implied-in-Fact Contract

The following six numbered paragraphs consist of allegations made by NDI in its complaint:

1. In 2011, NDI installed a cable management system at DISA’s headquarters located at Fort Meade, Maryland (compl. ¶ 5). NDI performed this work as a subcontractor to NCI Information Systems, Inc. (NCI) on the Total Engineering and Integration Services (TEIS) II contract, a contract awarded by the Department of the Army (id.). After completing its work as a subcontractor to NCI on the TEIS II contract, NDI submitted invoices to NCI and was paid by NCI (id.). The TEIS II contract expired in December 2011 (compl. ¶ 8).

2. In late-2011, prior to the expiration of the TEIS II contract, NDI met with officials from DISA, including the Chief Information Officer (CIO) for Operations, Edward Norwood, who requested that NDI provide additional services directly to DISA under a separate agreement (compl. ¶¶ 7-8, 10). The requested services included the installation of an artificial intelligence software program created by NDI (compl. ¶ 4). The requested services were distinct from those provided by NDI as a subcontractor to NCI on the TEIS II contract (compl. ¶¶ 1, 7, 13). Mr. Norwood represented that DISA would compensate NDI for the additional work “at NDI’s standard hourly rates” and that NDI should work directly with Mr. Norwood’s subordinates, Assistant CIO Sharon Sellers and Project Manager Melvin Spratley (compl. ¶ 7).

3. Mr. Norwood had previously negotiated the terms of purchase orders issued under the TEIS II contract, including the terms of one of the purchase orders issued to NDI (compl. ¶¶ 6, 8, 16) and a purchase order issued to another subcontractor, Cisco (compl. ¶16). In doing so, Mr. Norwood negotiated the prices paid to the subcontractors, as well as the scope of work to be performed by them (compl. ¶¶ 6, 8, 16). NDI alleges that Mr. Norwood possessed implied actual authority “in setting the contracts and contract terms for DISA and that such actions were an integral part of his duties at DISA” (compl. ¶ 16).

4. Based on the agreement reached with DISA, NDI provided artificial intelligence services directly to DISA from late-2011 through September 2013 (compl. ¶¶ 7, 10, 14). During this period, Mr. Norwood and Ms. Sellers repeatedly authorized the issuance of Common Access Cards to NDI employees, which provided the employees access to DISA facilities (compl. ¶¶ 11, 15). In October 2012, NDI submitted a copy of its hourly rates, which Messrs. Norwood and Spratley reviewed and accepted (compl. ¶ 11).

5. NDI did not submit invoices regularly to DISA based on DISA’s repeated assurances that NDI would be paid-in-full once the work was completed (compl. ¶¶ 12, 17). Because this arrangement placed “substantial financial strain” on NDI, company representatives met with Ms. Sellers in mid-2012 to request payment (compl. ¶ 12). Ms. Sellers instructed NDI to continue performing the services and informed NDI that it would be paid when the project was completed (id.). Ms. Sellers further informed NDI that the government would hold NDI liable if it did not complete the project (id.). NDI continued to provide the requested services with the understanding that DISA would compensate NDI for the services upon the completion of the work (id.).

6. NDI completed the requested services in September 2013 and, thereafter, submitted an invoice for payment to DISA, which DISA has not paid (compl. ¶ 14).

2 B. Claim and Appeal

7. On June 8, 2018, NDI submitted a claim to DISA, seeking reimbursement in the amount of $2,036,680.24 for the services NDI provided from late-2011 through September 2013 (R4, tab 7). On June 20, 2018, NDI submitted a revised claim, seeking reimbursement in the same amount for the same services described in its initial claim (R4, tab 10).1

8. The contracting officer denied NDI’s revised claim on August 16, 2018 (R4, tab 11), and NDI appealed to the Board on September 19, 2018.

9. In its complaint, NDI alleges that it entered into an implied-in-fact contract with DISA to provide the services at issue here and contends that it is entitled to payment under a theory of quantum meruit (compl. ¶¶ 15, 17). Additionally, there is language in the complaint to suggest that NDI also is pursuing its claim as a subcontractor, alleging that the services it provided to DISA were the result of an extension of its subcontract on the TEIS II contract (compl. ¶ 9).

DECISION

DISA advances two grounds upon which to dismiss. First, DISA moves to dismiss the appeal for lack of jurisdiction on the basis that NDI is a subcontractor with whom the government has no privity of contract (gov’t mot. at 1). Second, DISA moves to dismiss the appeal on the basis that NDI has failed to state a claim on which relief can be granted (id.). With respect to this latter basis, DISA argues that NDI’s complaint fails to allege the elements of an implied-in-fact contract (id.). NDI opposes the motion. For the reasons set forth below, we deny the government’s motion to dismiss.

A. Motion to Dismiss for Lack of Jurisdiction

DISA’s first argument is premised on the well-settled rule that this Board does not possess jurisdiction over a direct appeal filed by a subcontractor absent sponsorship of that claim by the prime contractor. See, e.g., Erickson Air Crane Co. of Washington, Inc. v. United States, 731 F.2d 810, 813 (Fed. Cir. 1984); United States v. Johnson Controls, Inc., 713 F.2d 1541, 1556 (Fed. Cir. 1983); B3 Solutions, LLC, ASBCA No. 60654, 16-1 BCA ¶ 36,578 at 178,138. DISA contends that, because NDI’s claim is not sponsored by NCI, the prime contractor on the TEIS II contract, NDI lacks privity of

1 The initial claim does not appear to have been properly certified, but appellant remedied this defect in its revised claim. We view our jurisdiction to consider this appeal to be premised on the denial of the properly certified revised claim. DISA has not challenged our jurisdiction to consider the appeal on this basis. 3 contract with the government and, thus, does not have standing to bring its claims under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109 (gov’t mot. at 4-5).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baltimore & Ohio Railroad v. United States
261 U.S. 592 (Supreme Court, 1923)
Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
H. Landau & Company v. The United States
886 F.2d 322 (Federal Circuit, 1989)
Engage Learning, Inc. v. Salazar
660 F.3d 1346 (Federal Circuit, 2011)
Gould, Inc. v. United States
67 F.3d 925 (Federal Circuit, 1995)
James L. Lewis v. United States
70 F.3d 597 (Federal Circuit, 1995)
Total Medical Management, Inc. v. United States
104 F.3d 1314 (Federal Circuit, 1997)
City of Cincinnati v. United States
153 F.3d 1375 (Federal Circuit, 1998)
William M. Hanlin v. United States
316 F.3d 1325 (Federal Circuit, 2003)
Advanced Team Concepts, Inc. v. United States
68 Fed. Cl. 147 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Network Documentation & Implementation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/network-documentation-implementation-inc-asbca-2020.