Nessmith v. Central Louisiana Electric Company

257 So. 2d 744
CourtLouisiana Court of Appeal
DecidedApril 11, 1972
Docket3630
StatusPublished
Cited by17 cases

This text of 257 So. 2d 744 (Nessmith v. Central Louisiana Electric Company) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nessmith v. Central Louisiana Electric Company, 257 So. 2d 744 (La. Ct. App. 1972).

Opinion

257 So.2d 744 (1972)

Leroy NESSMITH, Plaintiff-Appellee,
v.
CENTRAL LOUISIANA ELECTRIC COMPANY, Inc., Defendant-Appellant, and
E. J. Gunter and Wilfred "T Boy" Ardoin, Defendants-Appellees.

No. 3630.

Court of Appeal of Louisiana, Third Circuit.

January 21, 1972.
Rehearings Denied March 1, 1972.
Writs Refused April 11, 1972.

*745 Stafford, Pitts & Bolen, by John L. Pitts, Alexandria, for defendants-appellants.

Garrett, Ryland & Downs by B. Dexter Ryland, Alexandria, for plaintiff-appellee.

Gold, Hall, Hammill & Little by Jimmy M. Stoker, Alexandria, for intervenor-appellee.

Gist, Methvin & Trimble by H. B. Gist, Jr., Alexandria, for defendant-appellee.

Jones, Kimball, Patin, Harper, Tete & Wetherill by Carl Hanchey, Lake Charles, for defendant-appellee.

Before SAVOY, HOOD and MILLER, JJ.

HOOD, Judge.

Leroy Nessmith instituted this suit for damages for personal injuries sustained by him when a portable derrick, being used by his employer, came in contact with a high voltage electrical transmission line owned by Central Louisiana Electric Company, Inc. The suit was dismissed as to some defendants, but those remaining are Central Louisiana Electric Company, Inc. (Cleco), E. J. Gunter, and Wilfred "T Boy" Ardoin. Hardware Mutual Casualty Company, the compensation insurer of plaintiff's employer, intervened seeking reimbursement for the workmen's compensation benefits which it had paid to plaintiff.

Judgment was rendered by the trial court condemning Cleco to pay damages to plaintiff, but dismissing plaintiff's suit as to defendants Gunter and Ardoin. Judgment also was rendered in favor of intervenor, Hardware Mutual, for the amounts which it claimed. Defendant Cleco appealed. Plaintiff answered the appeal praying that the award of damages be increased. Hardware Mutual filed an answer to the appeal and a motion to remand to permit it to show additional payments made after the trial.

The principal issues presented are whether Cleco was negligent in failing to properly construct, maintain and insulate its main electrical transmission line at the *746 place where the accident occurred, or in failing to de-energize that line or to warn plaintiff that the main line was energized and dangerous at that point.

The accident which caused plaintiff's injuries occurred in Rapides Parish on April 23, 1968.

In 1967 the City of Alexandria entered into a contract with Layne Louisiana, Inc., under the terms of which Layne was to drill approximately 36 water wells to supply water for industrial expansion. These wells were to be located on property owned by the city near Melder, in Rapides Parish, Louisiana. Pursuant to that contract the drilling of these wells was commenced early in 1967. Plaintiff was employed by Layne at that time, and he worked as a roughneck or laborer in the drilling of these wells.

Defendant Gunter was working as a "driller" for Layne, and he was in charge of the drilling crew when the accident occurred. Defendant Ardoin was employed by Layne to work as "foreman" of that job.

Cleco has owned and maintained a 34,500 volt (34.5 KV) electrical transmission line in that area since 1956. This line is located in and along the center of a 100 foot right of way owned by Cleco, which right of way runs generally north and south, through the large tract of land on which the City of Alexandria has established its water well field. Cleco agreed to furnish the electricity for operating the pumps on the wells which were to be drilled by Layne.

The 34.5 KV main line was to provide the principal source of power for this electrical service. In order to get the electricity from the main power line to the well sites, Cleco agreed to build two substations within its right of way, directly under the 34.5 KV line, and to construct lateral or service lines running from those substations to all of the well sites. All of these lateral lines were to carry approximately 13,000 volts of electricity. The main line and all of the lateral lines were constructed in substantially the same manner. Each consisted of four wires, three of them being primary conductors and the fourth being a neutral conductor.

Cleco began constructing the lateral lines leading to the various well sites during the latter part of the year 1967. By that time most of the water well sites had been cleared, and some of the wells had been completed. Cleco had been furnished a plat showing the well sites, and from that document it had prepared another plat showing the 34.5 KV main line, the proposed lateral lines and substations, and the well sites.

The lower voltage lateral lines were never energized before April 23, 1968, and they were not energized when the accident occurred. The 34.5 KV main line had remained energized at all times except for two short periods, each lasting four or five hours and occurring on consecutive days, when the line was de-energized for the purpose of permitting the employees to tap in the substation switches. The main line served other customers in that vicinity, and arrangements had to be made by Cleco to provide electrical service to those customers during the two brief periods when the main line was de-energized to enable the substation switches to be installed.

The accident involved here occurred at a point directly under the 34.5 KV main transmission line, near one of the substations which was being constructed by Cleco. Only two well sites were located near this transmission line. The closest well was located about 53 feet from the point where the accident occurred, and the other nearby well was located about 30 feet further from the line, or about 83 feet from the place where the derrick contacted the electrical wire. The maps which were filed in evidence indicate that all other wells were located more than 1,000 feet from the 34.5 KV main transmission line, some of them being located up to two or three miles from it.

*747 The substation located near the scene of the accident consisted of a concrete slab, on which were located some posts and cross pieces made of lumber, various switches and arresters, and a large transformer. The transformer was installed in January, 1968, and it had not been energized before the accident occurred. The construction of the substation, in fact, had not been completed by that time. Plaintiff and other members of the well drilling crew knew that the transformer had not been energized, because they occasionally sat on the concrete slab and leaned against the transformer while eating their lunches. They also knew that the lateral lines which were being built had not been energized up to the time of the accident, because Layne Louisiana had provided its own portable generators in order to operate the test pumps.

There were no signs on the 34.5 KV main line warning of high voltage electricity. Plaintiff and the members of the well drilling crew had never been specifically advised that that line was energized, but neither had they been advised that it was dead. The evidence does not show that they ever made any inquiries as to whether or not the main line carried electricity. The main line was located there before the crew began drilling the wells, however, and it must have been obvious to them that it was an established electrical transmission line, located in the center of a wide cleared right of way and extending far beyond the boundaries of the property owned by the City of Alexandria.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abby Gail Garcie v. City of Natchitoches
Louisiana Court of Appeal, 2019
Dobson v. Louisiana Power & Light Co.
567 So. 2d 569 (Supreme Court of Louisiana, 1990)
Vincent v. Beauregard Elec. Co-Op., Inc.
536 So. 2d 798 (Louisiana Court of Appeal, 1988)
Creppel v. Louisiana Power and Light Co.
514 So. 2d 239 (Louisiana Court of Appeal, 1987)
Snow v. Gulf States Utilities Co.
492 So. 2d 31 (Louisiana Court of Appeal, 1986)
Rose v. Louisiana Power and Light Co.
474 So. 2d 1006 (Louisiana Court of Appeal, 1985)
Brock v. New Orleans Public Service, Inc.
433 So. 2d 1083 (Louisiana Court of Appeal, 1983)
Hebert v. Gulf States Utilities Co.
426 So. 2d 111 (Supreme Court of Louisiana, 1983)
Verrett v. Cameron Telephone Co.
417 So. 2d 1319 (Louisiana Court of Appeal, 1982)
Simon v. Southwest La. Elec. Membership Corp.
390 So. 2d 1265 (Supreme Court of Louisiana, 1980)
Simon v. Southwest Louisiana Electric Membership Corp.
380 So. 2d 1242 (Louisiana Court of Appeal, 1980)
Williams v. City of Alexandria
376 So. 2d 367 (Louisiana Court of Appeal, 1979)
Cates v. Beauregard Electric Cooperative, Inc.
328 So. 2d 367 (Supreme Court of Louisiana, 1976)
Burley v. Louisiana Power & Light Co.
319 So. 2d 334 (Supreme Court of Louisiana, 1975)
Cates v. BEAUREGARD ELECETRIC COOPERATIVE, INC.
316 So. 2d 907 (Louisiana Court of Appeal, 1975)
Sonier v. Louisiana Power & Light Co.
293 So. 2d 24 (Louisiana Court of Appeal, 1974)
Cooksey v. Central Louisiana Electric Company, Inc.
279 So. 2d 242 (Louisiana Court of Appeal, 1973)
Nessmith v. Central Louisiana Electric Co.
259 So. 2d 921 (Supreme Court of Louisiana, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
257 So. 2d 744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nessmith-v-central-louisiana-electric-company-lactapp-1972.