Ness v. Ward County Water Resource District

1998 ND 191, 585 N.W.2d 793, 1998 N.D. LEXIS 197, 1998 WL 756526
CourtNorth Dakota Supreme Court
DecidedOctober 30, 1998
DocketCivil 980072
StatusPublished
Cited by7 cases

This text of 1998 ND 191 (Ness v. Ward County Water Resource District) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ness v. Ward County Water Resource District, 1998 ND 191, 585 N.W.2d 793, 1998 N.D. LEXIS 197, 1998 WL 756526 (N.D. 1998).

Opinion

MARING, Justice.

[¶ 1] James Ness appeals the district court’s affirmance of the Ward County Water Resource District’s (District) order mandating the placement of a culvert beneath a township road. The appeal involves Ness’ dispute with the District over the depth and location of the culvert on a township road *794 that runs east-west on the northern border of his property. Ness complains the current placement of the culvert does not allow drainage in its natural drainage pattern, and as such, his land is damaged due to the accumulation of excess water not being drained off his land. We reverse the district court’s amended judgment affirming the District’s order because the District did not possess the authority to make such a determination.

I

[¶ 2] James Ness owns the NW'/4 of Section 35 in Freedom Township, Ward County, North Dakota. Section 26 is directly to the north of Section 35. A Freedom Township road (Road) runs along the northern border of Section 35 and southern border of Section 26. At a point near the northwest corner of Section 35, and southwest corner of Section 26, the Road curves gradually to the north and then back to the south, following the natural contour of the land. The arcing of the Road at this point results in water being artificially impounded upon Ness’ land in the northwest corner of Section 35.

[¶ 3] Prior to the Road’s construction in approximately 1950, surface waters flowed naturally betweén Sections 35 and 26. It was only after the construction of the Road that water began to pond in the northwest comer of Section 35 on what is now Ness’-property. Around the time of construction, a culvert was placed in the Road near the northwest corner of Section 35 to allow draining of surface water to the northwest. In 1986, Freedom Township built up the Road due to high water, and as a result, the culvert was filled in and lost.

[¶ 4] In approximately September 1994, Marvin Ness, on behalf of his son James, requested the Freedom Township Board of Supervisors (Township Board) install a culvert beneath the Road near the northwest corner of Section 35. On September 22, 1994, the Township Board applied to the District for a culvert permit. The application sought authorization from the District to install a culvert under the Road in the location requested by James Ness. The record does not indicate whether the application was granted or denied by the District. Nevertheless, on April 7, 1995, Township Board members installed a culvert beneath the Road near the northwest corner of Section 35. Specifically, the culvert was placed on the northwest side of the wetland formed in the Road’s arc. In the following weeks, Marvin Ness expressed his concerns about the culvert’s depth to Township Board president, John Pietsch. Marvin Ness was concerned the culvert could not effectively drain the pond at the depth it was placed. Mr. Pietsch responded that the District had determined the culvert’s location and depth, and the Township Board intended to follow that determination. In May 1995, Marvin Ness met with representatives of the District, Township Board, Natural Resources Conservation Service, and U.S. Fish and Wildlife at the site to discuss his concerns. The various representatives decided the Road had been handled properly, and the culvert’s location and depth were not changed.

[¶ 5] On June 13, 1995, James Ness, through his counsel, expressed to the Township Board and District representatives that he wished to have the culvert placed at its natural level of drainage. The Township Board met on August 7, 1995, and determined no action was necessary since the Road was in good condition. On November 1, 1995, James Ness made a formal request to the District for a hearing to determine the proper location of the culvert. Ness asserted the culvert was not placed in the natural drain, and as a result, water continued to pond to the detriment of his land.

[¶ 6] The District conducted a formal hearing on February 7, 1996. Testimony was taken from several individuals, including Marvin Ness. At the hearing, Marvin Ness initially argued a northeast drainage route (as opposed to the current northwest drainage) was in fact the natural drainage pattern of the surface waters, and thus the culvert should be placed to allow drainage in that direction. At some point during the hearing, Ness, by and through his attorney, amended his complaint seeking establishment of a drain not in any specific location, but rather at the natural drainage elevation.

*795 [¶ 7] At the close of the February 7, 1996, hearing, the District left the record open and requested further technical assistance from the State Engineer to determine the appropriate depth and location for the culvert. The State Engineer’s report reached a number of conclusions: 1) a northeasterly drain would cause significant downstream damage to Section 26 because the flow would pass over and erode the section’s tilled soil; 2) a northwesterly drain would pass through a grassed swale and graveled ditch, causing significantly less downstream impact and would better respect the affected federal wetland easements; and 3) a depth of 2079 msl (mean sea level) was recommended for a culvert in the northwest corner of the pond. On July 8, 1996, based upon this report, the District ordered the culvert remain in the northwest corner, with a depth of 2079 msl.

[¶ 8] Following an order from the district court on October 23, 1996, the District reopened proceedings to accept further evidence, specifically additional surveys conducted to determine the appropriate depth of the culvert. James Ness and the District each had a survey performed. Ness’ survey- or, a private, licensed surveyor, concluded the natural drainage elevation of the culvert was at a depth of 2076.8 msl. The District’s surveyor, the Ward County Highway Engineer, concluded the natural drainage elevation of the culvert was at a depth of 2077.9 msl.

[¶ 9] The District conducted a second hearing on January 16, 1997, and received both surveys as well as additional testimony. At the conclusion of the hearing, the District was essentially left with three choices as to depth of the culvert: 1) 2079 msl (State Engineer); 2) 2077.9 msl (District’s survey- or); and 3) 2076.8 msl (Ness’ surveyor). The District chose the second depth, issuing its second order on May 18, 1997, leaving the culvert in the northwest corner of Section 35 at a depth of 2077.9 msl.

[¶ 10] James Ness appealed the District’s order to the district court. The district court determined the District had properly exercised its discretion, and affirmed the District’s order. Ness appeals the district court’s amended judgment affirming the District’s order to this Court.

II

[¶ 11] The .parties in this case have focused their arguments on the propriety of the District’s order leaving the culvert in the northwest corner outlet of Section 35 at a depth of 2077.9 msl. The District argues its decision was not arbitrary and capricious because it carefully considered the three elevation alternatives for the culvert and fully considered the downstream impact caused by the project. Ness, on the other hand, argues the District abused its discretion because its decision violates the mandates of N.D.C.C. § 24-03-06, which requires township roads to be constructed in a way that does not obstruct the natural flow of surface water.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eichhorn v. The Waldo Township Bd. of Supervisors
2006 ND 214 (North Dakota Supreme Court, 2006)
State v. Shafer-Imhoff
2001 ND 146 (North Dakota Supreme Court, 2001)
Fandrich v. Wells County Board of County Commissioners
2000 ND 181 (North Dakota Supreme Court, 2000)
Fandrich v. WELLS CTY. BD. OF COUNTY COMM'RS
2000 ND 181 (North Dakota Supreme Court, 2000)
Huber v. Oliver County
1999 ND 220 (North Dakota Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
1998 ND 191, 585 N.W.2d 793, 1998 N.D. LEXIS 197, 1998 WL 756526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ness-v-ward-county-water-resource-district-nd-1998.