Nelson v. Cail

583 P.2d 1384, 120 Ariz. 64, 1978 Ariz. App. LEXIS 566
CourtCourt of Appeals of Arizona
DecidedJune 27, 1978
Docket1 CA-CIV 3753
StatusPublished
Cited by17 cases

This text of 583 P.2d 1384 (Nelson v. Cail) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson v. Cail, 583 P.2d 1384, 120 Ariz. 64, 1978 Ariz. App. LEXIS 566 (Ark. Ct. App. 1978).

Opinion

OPINION

FROEB, Chief Judge.

Northern Arizona University awarded a contract in August 1971 to Hunt Building Corporation for the construction of a married students’ housing facility consisting of 13 buildings and a utility building. Kenneth E. Cail was a plumbing contractor who was awarded the piping and plumbing subcontract for the job. Nelson was an architect employed by Northern Arizona University to design the housing project and supervise its construction.

During the course of construction difficulties arose between Nelson and Cail which resulted in a considerable amount of extra work on Cail’s part. Cail contended that Nelson intentionally and without justification imposed additional burdens upon the plumbing job in terms of work and materials not called for by the contract and that, as a result, Cail not only lost the $30,000 profit he expected but incurred other losses as well. The dispute led to a lawsuit in which Cail sought damages against Nelson for (1) defamation of his business reputation and (2) wrongful interference with his contract for the plumbing work on the construction project. Cail also sought punitive damages on both claims.

After a two-week trial, a jury returned a verdict in favor of Cail on the first claim for damages in the amount of $1000 and punitive damages of $3000. It also returned a verdict for Cail on the second claim for general damages of $40,000 and punitive damages of $40,000.

The trial court granted a judgment notwithstanding the verdict on the defamation claim and awarded Cail the sum of $1.00 after vacating the award for punitive damages. The trial court denied a similar motion relating to the claim for interference with contractual relations, leaving the verdict intact. A motion for new trial was also denied. Nelson appealed from the judgment against him on the claim for interference with contractual relations and Cail cross-appealed from that portion of the judgment which reduced the jury verdict on the defamation claim to $1.00.

The issues on appeal are narrow. Nelson does not raise any contention concerning his liability on the claim of interference with contractual relations. His sole issue is whether there was sufficient evidence of damages to support the award and whether the amount of the award bears a reasonable relationship to the evidence. The Cail cross-appeal deals only with the issue of whether Cail was required to prove actual damages to support a verdict on the defamation claim. We turn first to the Nelson appeal.

A substantial portion of the evidence at trial was devoted to proof of Cail’s claim that Nelson wrongfully interfered with the *67 performance of the plumbing subcontract. Since liability for this is not in issue, we need not review this evidence. Proof of damages was very limited and consisted entirely of the following:

1. Cail testified that, as a result of an unreasonable demand by Nelson, he purchased $10,000 worth of cinders to fill a trench.
2. Cail also testified that the project cost him $100,000 over the contract price. He stated as support that he “had gone through his individual company records.”
3. Frederic Colgrave, the insulation subcontractor Cail employed for this project, testified that he asked Cail for $16,000 over the contract price for excess costs.
4. Cail was asked what profit he had expected on the contract. His complete testimony on the subject of lost profit was, “$30,000 on this contract.”

Nelson did not undertake to cross-examine the witnesses on this testimony and when Cail rested his case, Nelson moved for a directed verdict, which was denied.

Nelson’s argument is that the amount of actual damages must be proven with substantial accuracy and that this evidence does not make out a prima facie ease. He then argues that without proof of actual damages there can be no award for punitive damages.

As background for analyzing this argument, we must reflect upon the nature of the underlying cause of action. The claim was brought in tort for intentional interference with contractual relations. Cail was entitled to recover pecuniary losses which proximately resulted from the interference. This included the benefits of the contract which were denied by reason of the interference. Cail was also entitled to recover punitive damages where Nelson’s acts were shown to have been the result of spite, ill will or a reckless indifference to Cail’s interest.

It is the general rule of damages in Arizona that once the right to damages has been established, uncertainty as to amount of damages will not preclude recovery. Grummel v. Hollenstein, 90 Ariz. 356, 367 P.2d 960 (1962); Maricopa County Municipal Water Conservation District No. One v. Roosevelt Irrigation Dist, 39 Ariz. 357, 6 P.2d 898 (1932); Jacobson v. Laurel Canyon Mining Co., 27 Ariz. 546, 234 P. 823 (1925). Yet there must be a reasonable basis in the evidence for the trier of fact to fix compensation when a dollar loss is claimed. Spain v. Griffith, 42 Ariz. 304, 25 P.2d 551 (1933).

Cail testified that his reasonable profit expected from the plumbing subcontract was $30,000. In our opinion, this was sufficient as prima facie proof of the loss. Two weeks of evidence concerning details of the materials supplied and the work performed by Cail provided a foundation for his opinion concerning his anticipated profit from the job. While the dollar sum was his conclusion obviously drawn from his experience with this and other jobs, it did not fail because there was no documentary evidence supporting it. Nelson made no objection to the foundation for the answer Cail was asked to give. Cail’s competency to give it could therefore be assumed. The evidence was adequate for consideration by the jury. There was no challenge to its weight as there was no cross-examination or contradictory proof on the issue offered by Nelson. The jury verdict for an amount at least equal to $30,000 was, therefore, appropriate. Whether the verdict for $40,000 can stand is our next question.

It is not as readily discernible from this record how the jury determined that Cail suffered the additional loss of $10,000. There was testimony to the effect that Cail, according to his records, incurred additional expenses of $100,000 over the contract price and that it was necessary for him to borrow $100,000 from United Bank. To what extent Cail recovered these extra expenses from the contractor is not clear. There was testimony that Nelson required Cail to re-excavate a large ditch after it had been partially filled and to refill it with cinders instead of native material at an additional cost of $10,000. There was also *68 testimony that Nelson caused an increased cost of approximately $10,000 for insulation of pipes. Here, again, there was little or no cross-examination and no contradictory evidence offered by Nelson.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E&M Services v. A&N Services
Court of Appeals of Arizona, 2020
Brimley v. Jirauch
Court of Appeals of Arizona, 2018
Deepwater v. Wells Fargo
Court of Appeals of Arizona, 2015
VAL Floors, Inc. v. Westminster Communities, Inc.
810 A.2d 625 (New Jersey Superior Court App Division, 2002)
Lewis v. N.J. Riebe Enterprises, Inc.
825 P.2d 5 (Arizona Supreme Court, 1992)
Koepnick v. Sears Roebuck & Co.
762 P.2d 609 (Court of Appeals of Arizona, 1988)
Short v. Riley
724 P.2d 1252 (Court of Appeals of Arizona, 1986)
Alaska Children's Services, Inc. v. Smart
677 P.2d 899 (Alaska Supreme Court, 1984)
Rancho Pescado, Inc. v. Northwestern Mutual Life Insurance
680 P.2d 1235 (Court of Appeals of Arizona, 1984)
University of Arizona Health Sciences Center v. Superior Court
667 P.2d 1294 (Arizona Supreme Court, 1983)
Broadway Realty & Trust, Inc. v. Gould
665 P.2d 580 (Court of Appeals of Arizona, 1983)
Poorbaugh v. Mullen
653 P.2d 511 (New Mexico Court of Appeals, 1982)
Cardinal Consulting Co. v. Circo Resorts, Inc.
297 N.W.2d 260 (Supreme Court of Minnesota, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
583 P.2d 1384, 120 Ariz. 64, 1978 Ariz. App. LEXIS 566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-v-cail-arizctapp-1978.