Navillus Tile, Inc. v. CNY Construction 701 LLC

CourtUnited States Bankruptcy Court, S.D. New York
DecidedAugust 7, 2023
Docket17-01245
StatusUnknown

This text of Navillus Tile, Inc. v. CNY Construction 701 LLC (Navillus Tile, Inc. v. CNY Construction 701 LLC) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Navillus Tile, Inc. v. CNY Construction 701 LLC, (N.Y. 2023).

Opinion

SOUTHERN DISTRICT OF NEW YORK ------------------------------------------------------------------x In re: Chapter 11

NAVILLUS TILE, INC., Case No. 17-13162 (DSJ)

Debtor. ------------------------------------------------------------------x NAVILLUS TILE, INC.,

Plaintiff,

-against- Adv. Proc. No. 17-01245 (DSJ)

CNY CONSTRUCTION 701 LLC,

Defendant. ------------------------------------------------------------------x

MEMORANDUM OPINION AND ORDER RESOLVING NAVILLUS TILE, INC.’S MOTION FOR PARTIAL SUMMARY JUDGMENT

A P P E A R A N C E S: PECKAR & ABRAMSON, P.C. Counsel for Navillus Tile, Inc., d/b/a Navillus Contracting 1325 Avenue of the Americas, 10th Fl. New York, NY 10019 By: Howard M. Rosen, Esq.

RICH, INTELISANO & KATZ, LLP Counsel for CNY Construction 701 LLC 915 Broadway, Suite 900 New York, NY 10010 By: Daniel E. Katz, Esq. Robert J. Howard, Esq.

Before the Court is Plaintiff Navillus Tile, Inc.’s (“Navillus”) motion for partial summary judgment (the “Motion”). In this adversary proceeding, Navillus, a trade contractor, is suing Defendant CNY Construction 701 LLC (“CNY”), the general contractor on a project known as 701 Seventh-Mixed Use Development, Seventh Avenue and 47th Street (the “Project”), for, inter alia, money allegedly earned but not paid in connection with certain superstructure concrete work and CNY (the “Contract”). [See generally ECF No. 106-9].1 CNY, in turn, is countersuing

Navillus for, inter alia, “back-charges” for costs which CNY allegedly incurred to remediate alleged deficiencies in Navillus’s Work, and asserted “delay damages” allegedly caused by Navillus. [ECF No. 106-10 at 9–22]. Navillus acknowledges that a trial will be required to fully resolve the parties’ dispute, but it seeks partial summary judgment as to the following contentions: (i) Navillus is entitled to a roughly $2,505,187 payment from CNY (the “Unpaid Total”), consisting of roughly $1,623,3282 in unpaid payment applications for Work allegedly completed (the “Unpaid Applications”)3 and roughly $881,859 allegedly held by CNY as retainage pending completion of the Work (the “Retainage”), all subject to a possible set-off based on disputed back-charges to be proved by CNY at trial; (ii) CNY’s non-payment of the Unpaid Total materially breached the Contract; (iii)

CNY’s non-payment violated the New York Prompt Payment Act, N.Y. Gen. Bus. Law § 756-a et seq. (the “PPA”); (iv) the Court should dismiss CNY’s counterclaims for delay damages on behalf of CNY and 20 TSQ Lessee LLC, who eventually became the owner of the Project (“20 TSQ” or the “Successor Owner”); and (v) all delay damages alleged on behalf of CNY and 20 TSQ are contractually capped at $1,000,000. [ECF No. 105 at 1–2; ECF No. 108 at 1].

1 Unless otherwise specified, references to the Case Management/Electronic Case Filing (“ECF”) docket are to the above-captioned adversary proceeding. Whenever possible, this Decision cites a document’s underlying pagination in the form “ECF No. __ at __.” When that is not possible because of a document’s formatting, this Decision cites the page number in the ECF-stamped banner at the top of the page, in the form “ECF No. __ at __ of __.” At times, the Decision also cites paragraph or section numbers. 2 This Decision uses approximate dollar amounts due to immaterial inconsistencies and inaccuracies in Navillus’s submissions. 3 Navillus uses the terms “payment application,” “invoice,” and “requisition” seemingly to refer to the same thing. [E.g., Hearing Tr. at 13:3–5]. Because Navillus most frequently uses the term “payment application,” and because the documents themselves are labeled “Application for Payment” [e.g., ECF No. 106-19 at 2 of 19], the Decision uses that term. 2 all delay damages asserted on behalf of CNY and 20 TSQ at $1,000,000, but it is denied in all

other respects. BACKGROUND A. The Contract On or about April 3, 2014, Navillus entered into the Contract with CNY to perform certain Work on the Project. [ECF No. 116 at 1]. The scope of Navillus’s Work under the Contract included pouring concrete and installing cast-in-place concrete columns, sheer walls, and floor slabs on various floors of a 40-story tower. [ECF No. 108 at 1; ECF No. 106-1 at 35–53 of 78]. CNY also occasionally had Navillus perform work outside the Contract’s scope (“Extra Work”) resulting from design changes, design issues, and differing site conditions. [ECF No. 107 at 3]. Navillus would submit “change requests” to CNY for the cost of any such Extra Work, and CNY

either would or would not approve the requests. [Id.]. The initial Contract price for Navillus’s Work was $28,900,000 [ECF No. 108 at 1; ECF No. 106-1 at 5 of 78], but by the time Navillus had concluded its Work the total contract price, including the price of all approved Extra Work, was roughly $35,274,394 (the “Final Contract Price”) [ECF No. 107 at 5; ECF No. 106-19 at 2 of 19, 17 of 19].4 The Contract incorporated by reference a schedule that imposed various Project deadlines, but, even before Navillus was to start its Work, delays from other aspects of the Project made the originally drafted Navillus deadlines impossible. [ECF No. 108 at 11]. Even so, once Navillus began its Work, for each month of Work, Navillus submitted a “pencil requisition” to CNY,

4 Navillus is also suing CNY for approximately $899,206 beyond the Final Contract Price for Extra Work allegedly completed by Navillus but unapproved by CNY, but that amount is not at issue on this Motion or included in the Final Contract Price or the Unpaid Total. [E.g., ECF No. 107 at 3–4; Tr. of Mot. Filed by the Pl. for Partial Summ. J. (“Hearing Tr.”) at 10:3–7, June 13, 2023]. 3 payment application to CNY. [ECF No. 107 at 3]. Navillus understood that CNY would then

submit Navillus’s payment applications to the owner and developer of the Project—originally, the Witkoff Group LLC, operating as 701 Seventh Property Owner LLC (“701 Seventh” or the “Original Owner,” and, together with the Successor Owner, the “Owners”)—along with all other trade contractors’ payment applications as part of CNY’s own payment application. [Id.]. CNY paid Navillus for every payment application except for the seven Unpaid Applications, which were for a combined total of approximately $1,623,328. [Id. at 4]. According to an April 5, 2021 verified statement provided by CNY to Navillus pursuant to section 76 of the New York Lien Law, CNY had submitted six of these seven Unpaid Applications to the Owners as part of CNY’s own request for payment (the “Submitted Unpaid Applications”), and the Owners had paid CNY for five of those six. [Id.; ECF No. 106-3 at 82 of 87].

By Navillus’s account as reflected in the final Unpaid Application (which Navillus submitted to CNY on February 28, 2019, but which CNY never submitted to the Owners), all Work was 100% complete, CNY had paid Navillus approximately $32,769,207, and CNY was still holding approximately $881,860—2.5% of the Final Contract Price—as Retainage. [ECF No. 107 at 5; ECF No. 106-19 at 2 of 19, 17 of 19]. Thus, Navillus is seeking to recover the difference between the $35,274,394 Final Contract Price and the $32,769,207 that CNY has already paid, or about $2,505,187—the Unpaid Total. [ECF No. 107 at 5]. As Navillus’s counsel explained during the Hearing, the Unpaid Total consists of “four pieces”: (i) about $914,881 for the five Submitted Unpaid Applications for which the Owners paid CNY; (ii) about $700,022 for the one Submitted

Unpaid Application for which the Owners did not pay CNY; (iii) about $8,422 for the one Unpaid Application which CNY did not submit to the Owners; and (iv) about $881,859 in Retainage. [Hearing Tr. at 14:23–15:20].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merrill Lynch & Co. Inc. v. Allegheny Energy, Inc.
500 F.3d 171 (Second Circuit, 2007)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Federal Insurance v. American Home Assurance Co.
639 F.3d 557 (Second Circuit, 2011)
Norton J. Lehman v. Dow Jones & Company, Inc.
783 F.2d 285 (Second Circuit, 1986)
Davis v. New York
316 F.3d 93 (Second Circuit, 2002)
Topps Co., Inc. v. Cadbury Stani SAIC
526 F.3d 63 (Second Circuit, 2008)
Holcomb v. Iona College
521 F.3d 130 (Second Circuit, 2008)
ADM Investor Services, Inc. v. Collins
515 F.3d 753 (Seventh Circuit, 2008)
Hicks v. Baines
593 F.3d 159 (Second Circuit, 2010)
Bear, Stearns Funding, Inc. v. Interface Group-Nevada, Inc.
361 F. Supp. 2d 283 (S.D. New York, 2005)
Oxford University Bank v. Lansuppe Feeder, Inc.
933 F.3d 99 (Second Circuit, 2019)
Schenectady Steel Co. v. Bruno Trimpoli General Construction Co.
316 N.E.2d 875 (New York Court of Appeals, 1974)
George S. May International Co. v. Thirsty Moose, Inc.
19 A.D.3d 721 (Appellate Division of the Supreme Court of New York, 2005)
Schenectady Steel Co. v. Bruno Trimpoli General Construction Co.
43 A.D.2d 234 (Appellate Division of the Supreme Court of New York, 1974)
Blask v. Miller
186 A.D.2d 958 (Appellate Division of the Supreme Court of New York, 1992)
Rachmani Corp. v. 9 East 96th Street Apartment Corp.
211 A.D.2d 262 (Appellate Division of the Supreme Court of New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Navillus Tile, Inc. v. CNY Construction 701 LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/navillus-tile-inc-v-cny-construction-701-llc-nysb-2023.