National Underground Construction Co. v. E.A. Cox Co.

576 N.E.2d 283, 216 Ill. App. 3d 130, 159 Ill. Dec. 614, 1991 Ill. App. LEXIS 1082
CourtAppellate Court of Illinois
DecidedJune 25, 1991
Docket1-90-1009
StatusPublished
Cited by13 cases

This text of 576 N.E.2d 283 (National Underground Construction Co. v. E.A. Cox Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Underground Construction Co. v. E.A. Cox Co., 576 N.E.2d 283, 216 Ill. App. 3d 130, 159 Ill. Dec. 614, 1991 Ill. App. LEXIS 1082 (Ill. Ct. App. 1991).

Opinion

JUSTICE COCCIA

delivered the opinion of the court:

Plaintiff National Underground Construction Company, a subcontractor, appeals from a circuit court order entering summary judgment in favor of defendant E.A. Cox Company, a general contractor, in this suit based on a cause of action for breach of contract alleging that defendant owes plaintiff an additional fee for the “extra” work performed by plaintiff in making adjustments to catch basins in a sewer construction project. On appeal, plaintiff contends that the court erred in granting summary judgment and the cause should be remanded for further hearing regarding whether or not plaintiff is entitled to an additional fee for its “extra” work.

On November 21, 1986, plaintiff filed a complaint for declaratory judgment and other relief, alleging that it is a subcontractor for the construction of underground improvements. Defendant is a general contractor for construction. On January 13, 1984, defendant entered into a contract with the City of Chicago for a construction project. On February 23, 1984, defendant entered into a written contract with plaintiff as subcontractor to perform certain work. Plaintiff alleged in its complaint that defendant was to pay it $356,539.12 for “its work under the contract and for extra work,” and that the “parties agreed that [defendant] was to pay $70,218.68 for the performance of the extra work.”

The complaint alleges that plaintiff was actually paid “for all work performed by it except for the sum of $6,310.87, which [defendant] retained pending receipt of payment from the City of Chicago to [defendant], and the sum of $33,354.44 representing extra work, performed by [plaintiff] in accordance with the agreement by [defendant] to pay for the installation of frame and lid settings, hereinafter described, for the resurfacing on the 55th Street job.”

Plaintiff alleged further that the installation of the frame and lid settings for the 55th Street resurfacing job was “extra work, not in-eluded in the original cont[r]act of February 23, 1984,” and that $33,354.44 was due for that work.

The complaint requests a declaration of the rights of the parties: “that [defendant] agreed to pay [plaintiff] for the extra work performed by [plaintiff] for the sum of $33,354.44 consisting of the installation of the frame and lid settings for the 55th Street resurfacing job”; that the price was reasonable; and that defendant also owed plaintiff $6,310.87. Plaintiff also requested an accounting from defendant for the $33,354.44, if received from the city, and the placement of such funds into a trust.

Frank Rizzo, president of plaintiff, explained at an October 10, 1989, deposition that the project consisted of performing certain sewer work which involved building catch basins. A catch basin is a precast concrete structure set into the ground. On top of the concrete structure is a cast iron frame. Later, after road work has been done, the catch basin must be adjusted to the new grade of the street. Then the frame is set, and the lids are put into place. In that frame, a lid or grate must be placed. The concrete structure is placed in the ground at the beginning of the road job.

The relevant portion of the subcontract reads:

“Section 1. The Subcontractor [plaintiff] agrees to furnish all necessary materials and/or to furnish all labor, tools, equipment, and supplies necessary to perform all work in the construction of [the project] *** in accordance with the terms and provisions of the Contract between the Owner and the Contractor, dated January 13, 1984, including all the General and Special Conditions, Drawings and Specifications and other Documents forming or by reference made a part of the Contract between the Contractor [defendant] and the Owner, all of which shall be considered part of this Subcontract by reference thereto, and the Subcontractor agrees to be bound to the Contractor and the Owner by the terms and provisions thereof.
Section 2. It is agreed that the materials to be furnished and/or work to be done by the Subcontractor are as follows: SEWER WORK AS SPECIFIED BELOW AS PER PLANS AND SPECIFICATIONS OF THE CITY OF CHICAGO.
Item No. 10 — Catch Basins ***.
Item No. 18 — Trench Backfill ***.
Item No. 19 — Storm Sewers ***.
Item No. 24 — Filling Existing Catch Basinsf.]
* * *
Item No. 25 — Removal of Existing Inlets ***.”

The relevant specification for Item 10 in the contract between the city and defendant reads as follows:

“ITEM 10 CATCH BASINS, k FOOT DIAMETER
This item shall consist of constructing new City of Chicago
standard catch basins at locations shown on the Plans ***.
* * *
Basis of Payment. This item will be paid for the Contract unit price each for CATCH BASINS, 4 FOOT DIAMETER, which price shall include all excavation, backfill and the setting and adjusting of all frames and lids. New frames and lids for catch basins will be paid for separately under Item 35 *** and Item 36 ***.”

Specification for item 35 provides that “The installation of the frame will be paid for as part of the various construction items involved.” Specification for item 36 provides that “New lids will be counted in place for payment at the Contract unit price per pound for CITY OF CHICAGO STANDARD MANHOLE AND CATCH BASIN PERFORATED OR SOLID LIDS, which price shall include the furnishing and transportation of the lid to its place of use on the project.”

On December 4,1989, defendant moved for summary judgment.

In response to defendant’s motion for summary judgment, plaintiff submitted the January 11, 1990, affidavit of F.M. Aduana, the City of Chicago’s resident engineer overseeing the project. Aduana stated that defendant failed to provide grades as required under the contract with the city. As a result, “the catch basins were installed not according to the proposed grade, and adjustments had to be made.” Aduana states further that the city rejected defendant’s bill for the extra work because the error was defendant’s responsibility, not the city’s. Attached to Aduana’s affidavit are his notes detailing his extensive problems in attempting to get defendant to provide proper grading. “I repeatedly told [Cox] that if the elevations were not right, I will require them to correct them at no extra cost to the City.”

Plaintiff also submitted the January 6, 1990, affidavit of Gene Currie, construction superintendent for defendant on the jobsite, reciting facts about an oral contract. Defendant’s president, John LeFevour, asked plaintiff to install frames and lids, although plaintiff “was not awarded the contract for frame and lid item.” The affidavit states further:

“At that time, E.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Popovych v. Hamraev
2024 IL App (3d) 220503-U (Appellate Court of Illinois, 2024)
Vanderplow v. Miller
2023 IL App (3d) 230004-U (Appellate Court of Illinois, 2023)
Doe v. Northwestern University
682 N.E.2d 145 (Appellate Court of Illinois, 1997)
Reynolds v. Decatur Memorial Hospital
660 N.E.2d 235 (Appellate Court of Illinois, 1996)
NAT. UNDERGROUND CONST. v. EA Cox Co.
652 N.E.2d 1108 (Appellate Court of Illinois, 1995)
National Underground Construction Co. v. E.A. Cox Co.
652 N.E.2d 1108 (Appellate Court of Illinois, 1995)
Nuccio v. Chicago Commodities, Inc.
628 N.E.2d 1134 (Appellate Court of Illinois, 1993)
Dalen v. Ozite Corp.
594 N.E.2d 1365 (Appellate Court of Illinois, 1992)
Rayner Covering Systems, Inc. v. Danvers Farmers Elevator Co.
589 N.E.2d 1034 (Appellate Court of Illinois, 1992)
Williams v. Prudential Property & Casualty Insurance
585 N.E.2d 1110 (Appellate Court of Illinois, 1992)
Bransky v. Schmidt Motor Sales, Inc.
584 N.E.2d 892 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
576 N.E.2d 283, 216 Ill. App. 3d 130, 159 Ill. Dec. 614, 1991 Ill. App. LEXIS 1082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-underground-construction-co-v-ea-cox-co-illappct-1991.