National Surety Corp. v. Massachusetts Bonding & Insurance

134 S.W.2d 611, 280 Ky. 785, 1939 Ky. LEXIS 201
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 3, 1939
StatusPublished
Cited by3 cases

This text of 134 S.W.2d 611 (National Surety Corp. v. Massachusetts Bonding & Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Corp. v. Massachusetts Bonding & Insurance, 134 S.W.2d 611, 280 Ky. 785, 1939 Ky. LEXIS 201 (Ky. 1939).

Opinion

Opinión op the Court by

Chiep Justice Ratlipb

■Reversing.

The appellant has prosecuted this appeal from, a judgment of the Payette circuit court refusing to allow it to file its intervening petition in an action in that court styled, Massachusetts Bonding and Insurance Company v. Blair and Pranse Construction Company, involving certain funds due by the State Highway Department of Kentucky to the Blair and Pranse Construction Company, as an unpaid balance due on certain road construction work done under contract between the State Highway Department and the Blair and Pranse Construction Company.

On June 12, 1937, the appellee, Massachusetts Bonding and Insurance Company, obtained a judgment in the Payette circuit court against Blair and Pranse Construction Company for the sum of $2,967. On July 29, 1937, an execution was issued by the clerk of the Payette circuit court and placed in the hands of the sheriff of Payette county and later returned, endorsed, “No property found.” On July 29, 1937, appellee filed its petition in equity against Blair and Pranse Construction Company, alleging that it had obtained the judgment, referred to above, against the Blair and Pranse Construction Company, on which judgment an execution had issued and had been returned, endorsed, “No property found.” A general order of attachment was issued and served on the proper officials of the State Highway Department, the State Auditor and the State Treasurer of Kentucky, for the purpose of staying payment by the state highway department of any sums of money it may owe to the Blair and Pranse Construction Company. The State Highway Department filed its answer, disclosing that it was holding the sum of $1,078.62 as final estimate for the construction of a certain road project by the Blair *787 and Franse Construction Company for the Highway Department, which sum was being held for final release forms properly executed by the Blair and Franse Construction Company, but that it would be necessary for said contractor, or someone having power to do so for it, to sign the final release to the State Highway Department. By subsequent orders the court sustained the order of attachment and appointed a special commissioner to sign the final release for the Blair and Franse Construction Company to the Department of Highways and to endorse the check for $1,078.62, payable to it by the Department of Highways, and directing the Department of Highways as garnishee to pay said fund into court, and after the payment of the costs, the balance of $1,078.62 should be paid to attorneys by appellee as a credit on its judgment.

After the entry of the above orders, on December 16, 1937, the appellant, National Surety Corporation, filed its motions in the Fayette circuit court, seeking to have the funds in question applied to the payment of certain outstanding labor and material claims, and further sought to set aside the previous orders of the court, and following the above motions, on December 18, 1937, appellant tendered, and offered to’file, its intervening petition, setting up its claim to the funds in question, to the filing of which appellee objected.

The tendered intervening petition alleges, in substance, that in October, 1936, Blair and Franse Construction Company (hereinafter called the contractor) executed a performance bond covering a gravel resurfacing contract project in McLean County, Kentucky, and that the petitioner, appellant, signed said bond as surety; that the contract was completed by the contractor in accordance with the terms thereof, except that said contractor failed to pay outstanding labor and material claims in the carrying out of the contract. That the said sum of $171 due Kentucky Concrete Pipe Company and the sum of $296.80 due Kentucky Culvert Manufacturing Company are among the labor and material bills incurred by said contractor in carrying out said contract which have not been paid by the said contractor, and that this petitioner under its surety agreement with the highway department of the state of Kentucky, became and is liable for the payment of those claims and other claims incurred by said contractor, which have not been paid by it. That the said unpaid creditors and *788 claimants and this petitioner have a lien upon the funds payable by the State of Kentucky, or the State Highway Department, to said contractors to secure said contractors and claimants and this petitioner in payment of said claims and said unpaid claimants and this petitioner should have been made parties to the action.

In April, 1938, appellant tendered its amended intervening petition, which reads as follows:

“That on or about October 30, 1936, but as of November 12th, 1936, Blair and Pranse Construction Company executed a performance bond covering a gravel re-surfacing contract entered into between it and the Commonwealth of Kentucky, through its Department of Highways, and known as Project SP-587-AS, McLean County, Kentucky, and that this petitioner signed said bond as surety.
“That by reason of the signing of said bond as surety, this petitioner has been compelled to pay to-Kentucky Concrete Pipe Company the sum of $174.00 and to pay to Kentucky Culvert Manufacturing Company the sum of $296.80.
“That said Kentucky Concrete Pipe Company and Kentucky Culvert Manufacturing Company were entitled to be paid out of the attached fund of $1,078.62 which was the final estimate, number four, on McLean County Project 587-AS, and at the time of the service of the attachment on July 31st, 1937, by plaintiff herein, and at the time said fund was paid into the Payette Circuit Court, and paid out by the Special Commissioner to attorneys for plaintiff, said two creditors or materialmen had an equitable lien upon said fund.
“That said fund of $1,078.62 was paid by the check of the Department of Highways of the State of Kentucky, -as representing the final estimate on said project and that at the time of the service of said attachment, and at the times when said orders were entered on December 4 and December 11,1937, plaintiff knew that said fund came from the balance due Blair and Pranse Construction Company on said project; that said payment was made by the Department of Highways into Court by mistake, and the Department of Highways was entitled to, and could have recovered said sum from Massachusetts Bonding and Insurance Company; that said *789 fund was paid into the Fayette Circuit Court under and pursuant to said order, and not voluntarily.
“This intervenor states that said two material-men- were entitled to and had an equitable lien upon said fund of $1078.62, to secure the payments of their respective claims, and that this surety is entitled to be subrogated -to the rights of said two materialmen, and is entitled to- have a sufficient amount of said fund paid back into court by plaintiff to satisfy said two claims paid by this surety.
“ Plaintiff states that previous to the execution of the contract herein involved, on November 12, 1936, Blair & Franse Construction Company executed an indemnity agreement to National Surety Corporation wherein in Paragraph Five, it is provided :
“ £5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
134 S.W.2d 611, 280 Ky. 785, 1939 Ky. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-corp-v-massachusetts-bonding-insurance-kyctapphigh-1939.