National Stamping & Electric Works v. Wicks

128 S.W. 775, 144 Mo. App. 249, 1910 Mo. App. LEXIS 350
CourtMissouri Court of Appeals
DecidedMay 2, 1910
StatusPublished
Cited by2 cases

This text of 128 S.W. 775 (National Stamping & Electric Works v. Wicks) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Stamping & Electric Works v. Wicks, 128 S.W. 775, 144 Mo. App. 249, 1910 Mo. App. LEXIS 350 (Mo. Ct. App. 1910).

Opinion

NIXON, P. J.

This is a controversy over the purchase price of certain electrical machinery purchased for use in respondents’ electric light plant at Willow Springs. The correspondence leading up to the purchase commenced February 22, 1905, when the respondents wrote the appellant the following letter:

“We are in the market for a 25 k. w. alternator 1100 v., 60 cycle, about 1200 r. p. m., with exciter and switchboard instruments complete. Please give best prices at once, and oblige, Wicks & Peters, Per Howard.” ■

On March 1, 1905, appellant replied as follows:

“We are in receipt of your letter of the 22d and we are pleased to quote you as follows: One 25 k. w., 60 cycle, 100 General Electric reconstructed alternator, with toothed armature, speed approximately 900 r. p. m., $400. f. o. b. Chicago, including exciter. This machine has a new toothed armature, self oiling, and is a ten pole machine, and has been thoroughly overhauled and tested by us and is guaranteed to be in first-class condition. We can furnish you with a 230 k. w., 150 cycle, 1100 volt Thompson-Houston alternator, speed 1500 r. p. m., with exciter for $225. f. o. b. Chicago.”

The purchase of the 30 k. w., 60 cycle, General Electric alternator was made by respondents’ letter-to appellant of March 7, 1905, as follows:

[252]*252“Replying to your favor of March 1, will say that the 25 k. w., 60 cycle, General Electric alternator would just about fill our needs. But we think the switch-board only 25x30 will be too small. We will want on the board 1 volt meter, 1 ammeter, 2 lightning arresters, 1 switch-board transformer, 1 main line switch, exciter switch, 1 rheostat, 2 pilot lights, 1 circuit breaker, and 1 ground detector. Please quote us on the entire outfit with marble panel long enough to receive all these instruments.”

The whole bill purchased was finally concluded by letter of respondents to appellant of March 12, 1905, as follows:

“Replying to your favor of March 10 and also of March 1 will say that we accept your offer on the 25 k. w., 60 cycle, General Electric dynamo to include exciter at $400; also switch-board and instrument as per yours of March 10 at $97, total, $400, f. o. b. cars Chicago. We do not want this shipped before April 15th, but will send you a deposit of the amount you may require to hold the trade.”

The respondents paid the entire amount of the purchase price in cash prior to the institution of the suit except the amount of sixty dollars, and at the December term, 1905, appellant commenced suit against the respondents stating as its cause of action that the respondents were indebted to it for electrical appliances and apparatus sold and delivered by the appellant to the respondents on or about the 14th day of July, 1905, to the amount of sixty dollars, and for which with interest appellant demanded judgment. The account filed with the petition was for ten twelve-light transformers at six dollars each.

Respondents filed an answer admitting the purchase of the ten twelve-light transformers, but also filed a counterclaim as follows:

“Defendants for a further cause of action and as a counterclaim allege that they purchased from plain[253]*253tiff in the year 1905 a complete electric light plant for use in the city of Willow Springs, Missouri, and that plaintiff in accordance with such purchase, shipped to defendants at Willow Springs, Missouri, a second-hand electric light plant which had been worked over, and changed, and which was guaranteed a twenty-five kilowatt, sixty cycle, eleven hundred volt machine in first-class working order. That defendants did not know anything about such outfit and could in no way determine its cycle power or voltage until it was set up and put in operation. That after such machine was put in operation it was discovered to be a machine of some other cycle power than a sixty cycle machine, and that the original stamp or plate mark of such machine had been removed and another plate marking put on it by the plaintiff or some one for them, and that the machine sent them by plaintiff was not the electrical machine or outfit which defendants had purchased of plaintiff but was a very much inferior outfit and of no value. And that by reason of this deception and fraud, and by reason of plaintiff sending this inferior and mismarked electric machine to defendants and failing to send the machine defendants had purchased, they had been damaged in the sum of five hundred dollars, for which they ask judgment.
“For a further and separate counterclaim, defendants allege that when they purchased the electric lighting plant of plaintiff they also purchased as a necessary and essential part of such electrical plant at a stipulated gross price for the complete electrical outfit, a circuit breaker; but that for some reason plaintiff failed, neglected and refused to furnish and ship to defendants such circuit breaker, and that by reason of such neglect and failure on the part of the plaintiff to furnish a circuit breaker to defendants, they were damaged in the sum of thirty dollars, for which they ask judgment.
. “For a further counterclaim against the plaintiff, defendants say that plaintiff furnished with the electric [254]*254lighting plant which they sold defendants as a necessary; and essential part of such electric lighting plant, one, ammeter and one volt meter, but that such ammeter and volt meter so furnished and sent to defendants as a part of such electric lighting plant were not built and made, to be used with the electric lighting plant which was. furnished defendants and would not correctly measure-the electric current of the plant, and that when placed, in connection with such electric plant, the volt meter., incorrectly measured the voltage, and by reason of such false registration and by such defective volt meters, two transformers were burned out and destroyed and all other transformers of such plant were found to be useless, and that five hundred incandescent lamps of the valué of eighty dollars were burned out and destroyed: That defendants had no way of knowing that such volt meter' and ammeter were not built to register the power of such plant until after they were used and were found to be defective, and such damage had been done to such plant. Wherefore defendants asked judgment against plaintiff for the sum of eighty dollars.”

Judgment was for four hundred dollars for respondents on their counterclaim, with a credit to appellant of sixty dollars for the account sued upon, leaving a balance of three hundred and forty dollars. Afterwards respondents entered a remittitur of eighty dollars and the judgment was amended to correspond and was entered for two hundred and sixty dollars. The plaintiff has appealed.

In plaintiff’s motion for. new trial, there are thirteen grounds of error assigned. The assignments number 7 inclusive to number 11 inclusive are for the improper admission and exclusion of testimony. On a careful examination we find that no error was comm.it-ted by the trial court in the admission or exclusion of evidence.

There are also two assignments in the motion for new trial which charge that the verdict is contrary tp [255]*255the evidence and is not supported by sufficient evidence. These assignments are overruled for reasons hereinafter stated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gummerson v. Kansas City Bolt & Nut Co.
171 S.W. 959 (Missouri Court of Appeals, 1914)
Sinnamon v. Moore
142 S.W. 494 (Missouri Court of Appeals, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
128 S.W. 775, 144 Mo. App. 249, 1910 Mo. App. LEXIS 350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-stamping-electric-works-v-wicks-moctapp-1910.