National Refrigeration, Inc. v. Standen Contracting Co.

942 A.2d 968, 2008 R.I. LEXIS 20, 2008 WL 450213
CourtSupreme Court of Rhode Island
DecidedFebruary 21, 2008
Docket2006-318-Appeal
StatusPublished
Cited by46 cases

This text of 942 A.2d 968 (National Refrigeration, Inc. v. Standen Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Refrigeration, Inc. v. Standen Contracting Co., 942 A.2d 968, 2008 R.I. LEXIS 20, 2008 WL 450213 (R.I. 2008).

Opinion

OPINION

Justice GOLDBERG,

for the Court.

This case came before the Supreme Court on December 3, 2007, on appeal by the plaintiff, National Refrigeration, Inc. (plaintiff or National), from the entry of summary judgment in favor of the defendants, Standen Contracting Company, Inc. (Standen), and United States Fidelity and *970 Guaranty Company (USF & G and collectively defendants). 1 The plaintiff has appealed to this Court, contending that the motion justice erred in granting the defendants’ motion for summary judgment because (1) a genuine issue of material fact existed at the time of the hearing; (2) the contract that is the subject of the dispute between Standen and National was ambiguous; and (3) the motion justice failed to determine whether the law of Rhode Island or that of Massachusetts governs the issues in this case. For the reasons stated in this opinion, we affirm the judgment.

Facts and Travel 2

In the year 2000, the Rhode Island Airport Corporation (RIAC) agreed to a contract to install sound-abatement materials in residences in the vicinity of T.F. Green Airport. RIAC selected Standen as the general contractor and, following a bidding process, Standen engaged National as a subcontractor for the project. Between 2000 and 2002, National was awarded three contracts — RIAC Contract No. 11698 (first contract); RIAC Contract No. 13670 (second contract); and RIAC Contract No. 15028 (third contract) — for heating, ventilation, and air conditioning (HVAC) work in connection with the sound-abatement project. It is the third contract that is the subject of this appeal.

Because the sound-abatement project was federally funded, subcontractors were required to compensate their employees for labor according to prevailing hourly wage rates, in compliance with the Davis-Bacon Act, 40 U.S.C. §§ 3141-3148. The first contract contained a wage decision document, but it did not list the prevailing hourly wage for HVAC related work. After requesting a pre-bid wage determination from the U.S. Department of Labor (DOL), RIAC was informed that the wage rate would be determined after bidding was completed.

The uncertainty surrounding the prevailing wage for HVAC employees caused RIAC to add a new provision to the first contract that also was included in the second contract. That new provision was set forth in “Addendum No. 1” (addendum); pursuant thereto, RIAC would consider altering the contract amount “through a Change Order for the difference (if any) for the rate used in the bid for the unlisted classification and the rate determined by the Federal Department of Labor.” Significantly, “Part IIA” of the first contract specifications provided that contractors could include in their bid a wage rate for HVAC mechanics and, if the wage rate paid by the contractor was lower than the rate established by the DOL, the contractor could seek a change order for the difference. 3 Finally, bidders were required to submit a wage and certification form, listing the precise hourly wage rate and total number of hours the contractor used in compiling its final bid.

National was awarded the first contract based upon a wage rate of $15.49 per hour. The DOL later determined that the appropriate wage rate was $32.91 per hour, resulting in an increased cost to National of $39,639.27. National submitted a change *971 order for that amount to Standen that was forwarded to RIAC. RIAC approved the change and National was reimbursed.

Approximately one year later, in June 2001, National was awarded the second contract after basing its bid on a wage rate that was lower than the classification later determined by the DOL. Again, the appropriate amount was determined to be $32.91 per hour. National incurred an increased cost of $11,462, submitted a change order for that amount and was compensated in the same manner as under the first contract. 4 However, this practice changed for the third contract — the contract that is the subject of this appeal. 5

On March 22, 2002, National submitted and Standen accepted a lump sum bid of $251,985 for the HVAC work to be completed on residences referred to as Group IS; it is to this work that the third contract relates. The parties entered into a subcontract on July 23, 2002, that differed from the previous two contracts in a crucial respect: it did not include the addendum authorizing a change order for any wage determination made after the contract was executed. The bid specifications notified all contractors and subcontractors that wages paid were not to be “less than those prevailing on the same type of work on similar construction in the immediate locality as determined by the United States Secretary of Labor, in accordance with the [Davis-Baeon Act].” On November 27, 2002, National submitted a change order to Standen for $35,226.14, the difference between the wage rate used to calculate its bid and the wage rate required by the DOL for HVAC mechanics. Standen forwarded the request to RIAC, which rejected the change order.

On October 31, 2003, plaintiff filed an action for breach of contract based on Standen’s refusal to honor the change order request. The defendants moved for summary judgment, and a hearing on the motion was held on July 24, 2006. The motion justice noted that the previous contract documents outlined procedural steps for change order requests for increased labor costs, but that the third contract did not so provide. The hearing justice concluded that under the unambiguous terms of the third contract, plaintiff was not entitled to the wage reimbursement. She granted defendants’ motion for summary judgment, and plaintiff appealed.

Standard of Review

This Court’s de novo standard for review of a motion justice’s decision to grant summary judgment is well established. Roe v. Gelineau, 794 A.2d 476, 481 (R.I.2002). “Only when a review of the admissible evidence viewed in the light most favorable to the nonmoving party reveals no genuine issues of material fact, and the moving party is entitled to judgment as a matter of law, will this Court uphold the trial justice’s grant of summary judgment.” Carlson v. Town of Smithfield, 723 A.2d 1129, 1131 (R.I.1999). “[A] party who opposes a motion for summary judgment carries the burden of proving by competent evidence the existence of a disputed material issue of fact and cannot rest on allegations or denials in the pleadings or on conclusions or legal opinions.” Accent Store Design, Inc. v. Marathon House, Inc., 674 A.2d 1223, 1225 (R.I.1996).

Whether a contract’s terms are ambiguous is a question of law. Dubis v. *972

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Debora D'Alessandro v. Douglas Caniglia
Supreme Court of Rhode Island, 2021
Management Capital, L.L.C. v. F.A.F., Inc.
209 A.3d 1162 (Supreme Court of Rhode Island, 2019)
Bacon Construction Co., Inc. v. Arbella Protection Insurance Company, Inc.
208 A.3d 595 (Supreme Court of Rhode Island, 2019)
Austin Yattaw v. The City of East Providence
203 A.3d 1167 (Supreme Court of Rhode Island, 2019)
Dorrance H. Hamilton v. Carol C. Ballard
161 A.3d 470 (Supreme Court of Rhode Island, 2017)
Pocahontas Cooley v. Paul Kelly
160 A.3d 300 (Supreme Court of Rhode Island, 2017)
Stephen F. Limoges v. Nalco Company
157 A.3d 567 (Supreme Court of Rhode Island, 2017)
Charles S. Faber v. Francine A. McVay
155 A.3d 153 (Supreme Court of Rhode Island, 2017)
OSJ OF PROVIDENCE, LLC v. Aly T. DIENE
154 A.3d 460 (Supreme Court of Rhode Island, 2017)
Eunique Williams v. Chicara Alston, No
154 A.3d 456 (Supreme Court of Rhode Island, 2017)
Michael F. Rose, Jr. v. Stephen M. Brusini
149 A.3d 135 (Supreme Court of Rhode Island, 2016)
Richard Bisbano Sr. v. Strine Printing Company, Inc.
135 A.3d 1202 (Supreme Court of Rhode Island, 2016)
Rhode Island Joint Reinsurance Association v. Manuel Rosario
116 A.3d 168 (Supreme Court of Rhode Island, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
942 A.2d 968, 2008 R.I. LEXIS 20, 2008 WL 450213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-refrigeration-inc-v-standen-contracting-co-ri-2008.