National Labor Relations Board v. Hudson T. Marsden, a Sole Proprietorship

701 F.2d 238, 112 L.R.R.M. (BNA) 2945, 1983 U.S. App. LEXIS 30220
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 23, 1983
Docket478, Docket 82-4101
StatusPublished
Cited by9 cases

This text of 701 F.2d 238 (National Labor Relations Board v. Hudson T. Marsden, a Sole Proprietorship) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Labor Relations Board v. Hudson T. Marsden, a Sole Proprietorship, 701 F.2d 238, 112 L.R.R.M. (BNA) 2945, 1983 U.S. App. LEXIS 30220 (2d Cir. 1983).

Opinion

WINTER, Circuit Judge:

The National Labor Relations Board petitions for enforcement of its decision and order against Hudson T. Marsden, requiring Marsden to cease and desist from certain unfair labor practices and to reinstate or otherwise compensate certain employees discharged after participating in what Ad *239 ministrative Law Judge D. Barry Morris found to be protected concerted activity under Section 7 of the National Labor Relations Act, 29 U.S.C. § 157 (1976). Marsden applies for review of the Board’s decision and contends, first, that the NLRB lacks jurisdiction because of the purely local nature of his business, and second, that the conduct of the employees in question did not constitute Section 7 protected activity. While we find that the Board acted within its jurisdiction, we agree with Marsden that the conduct of the employees involved was not protected under Section 7.

We therefore deny enforcement and vacate the decision.

BACKGROUND

Hudson T. Marsden is a pavement contractor doing business as a sole proprietorship. During May 1980, he was engaged in repairing and installing sidewalks under a contract with the city of Rochester, New York. At that time, Marsden employed eight workers, three cement finishers, Strothers, Boston, and Cooper, and five laborers, Young, Ruffin, Cole, Porter and Laine. These employees were not represented by a labor organization.

On Monday, May 19, 1980, it was foggy and drizzling when the employees reported to work around 7:30 in the morning. At about 7:45 or 8:00, Marsden came out and asked Strothers and Porter if, given the weather, they thought that work should start for the day. Strothers and Porter agreed to “give it a try.” They then packed their equipment and drove to the jobsite several blocks away.

At 9:30 a.m., Marsden left the jobsite on a banking errand which kept him away for approximately 45 minutes. In the course of this errand, Marsden stopped at a phone booth and believing the weather was actually improving, scheduled delivery of an order of concrete costing $987 for that afternoon. Meanwhile, at the jobsite, the men, apparently led by Strothers, began discussing whether or not to continue working in the rain. Several workers suggested that they put off deciding until the end of their regular 10 a.m. coffee break. During the break, the men took shelter for about 10 minutes and most of them then decided to leave the jobsite. Thereafter, they all left for the day.

All parties are agreed that Marsden’s normal and well-known procedure in inclement weather was for the employees to take shelter either in the doorways of nearby buildings, on someone’s porch, in the tool shanty, or in the trucks. It is evident from the record that on May 19 there were enough trucks and cars at the jobsite for all the men to take shelter. On previous occasions, the men had waited for up to an hour to see whether rain would let up, and, if it did not, Marsden or his son would tell the men to leave for the day. The workers were always paid for this waiting time.

After the coffee break discussion, Stroth-ers, who had been most active in complaining about the weather, went among the other workers, picked up their tools, and, as was his job, loaded the tools in a pickup truck and set out to return them to the central storage area. The rest of the men then left the jobsite in their vehicles, with Strothers and Porter in the lead in Mars-den’s trucks. On the way back to the shop, Strothers encountered Marsden who was returning to the jobsite. Strothers explained to Marsden that the men had decided to knock off for the day, and although accounts of the conversation differ, it is clear that Marsden became somewhat exercised. However, he succeeded in cancelling the order for concrete he had just put in.

The weather conditions on May 19 were neither severe nor unusual. The National Oceanic and Atmospheric Administration recorded only trace precipitation, or less than .01 inch of rain. The ALJ described the precipitation as “drizzle or light rain.” Nearby, outdoor construction jobs continued to work throughout the day, and a civil engineer who inspected the Marsden jobsite testified that the rain was “very light” and that Marsden’s men “had worked in harder rain a lot of times.” Boston in fact continued to work until Strothers picked up his tools. Cole testified that it was “not really” *240 raining too hard to work and that he left because “everybody else was leaving, you know.” When further pressed regarding his reason for leaving work, he stated that he “didn’t feel like” working because of a “bad weekend.” Boston testified that it “wasn’t raining that hard” and that he had not considered putting on his own personal raingear or stopping because of the weather until Strothers picked up his tools. Laine similarly stated that the drizzle was not heavy enough to force the men to discontinue work and that Strothers gave no reason for his conduct that day other than “He just didn’t want to work.” Cooper described the weather as a “light mist” and recalled telling Strothers that conditions were not bad enough to leave. He also stated that after they left, the men went to Young’s house to spend the day, only to find that by eleven o’clock, the sun was shining. Marsden and Laine, who lived nearby, returned to the jobsite in the afternoon and spent the rest of the day refilling dirt around the hardened concrete forms.

When the workers reported the next day, May 20, Marsden had words with them regarding their abandonment of the job. The upshot was that Marsden fired Strothers on the spot, instructed Young, Laine and Boston to go to work, and left Porter, Cole and Ruffin “standing there.” When Porter, Cole and Ruffin reported for work on the twenty-first, Marsden told them that there was no work for them to do and gave them their checks. Strothers also received his check, although under even more acrimonious circumstances. Marsden rehired Cole and Ruffin the following Monday, after a “preliminary investigation as to what happened.” By the twenty-sixth, Marsden had concluded that all the men, save Strothers and Porter, were “under duress and influenced by other people” because they “had no choice of transportation back to [the] shop and they couldn’t hold or conduct any work on their own.”

Strothers filed an unfair labor practice charge against Marsden, and, on July 25, 1980, the General Counsel issued a complaint alleging that Marsden had violated Section 8(a)(1) of the National Labor Relations Act by interfering with his employees’ exercise of rights protected by Section 7 of the Act. The case was referred to Administrative Law Judge D. Barry Morris who held a hearing and issued his rulings, findings of fact, and order on August 7, 1981. That decision became the final decision and order of the Board on January 5, 1982.

Relying upon N.L.R.B. v. Washington Aluminum Co., 370 U.S. 9, 82 S.Ct. 1099, 8 L.Ed.2d 298 (1962), the ALJ concluded that Marsden’s employees walked off the job because they were unwilling to work in the rain and were, therefore, engaged in a protected work stoppage to protest uncomfortable working conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
701 F.2d 238, 112 L.R.R.M. (BNA) 2945, 1983 U.S. App. LEXIS 30220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-labor-relations-board-v-hudson-t-marsden-a-sole-proprietorship-ca2-1983.