National Labor Relations Board v. Goodyear Footwear Corp.

186 F.2d 913, 27 L.R.R.M. (BNA) 2278, 1951 U.S. App. LEXIS 3337
CourtCourt of Appeals for the Seventh Circuit
DecidedJanuary 17, 1951
Docket10229
StatusPublished
Cited by3 cases

This text of 186 F.2d 913 (National Labor Relations Board v. Goodyear Footwear Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Labor Relations Board v. Goodyear Footwear Corp., 186 F.2d 913, 27 L.R.R.M. (BNA) 2278, 1951 U.S. App. LEXIS 3337 (7th Cir. 1951).

Opinions

FINNEGAN, Circuit Judge.

In this proceeding National Labor Relations Board seeks a decree of this court ordering the enforcement of an order of said Board, issued on November 24, 1948, directing respondent, Goodyear Footwear Corporation, its officers, agents, successors and assigns to comply therewith.

It appears that respondent is a Delaware Corporation having its principal office at Providence, Rhode Island. It is engaged in the manufacture, sale and distribution of rubber footwear. Early in 1946 the respondent had a survey made of the midwest industrial area, and decided to attempt to locate a plant at Clinton, Illinois.

At that time Clinton had a population of approximately 6300 people, and contained -only three small factories each of which employed less than 50 persons. The plans of the respondent called for the establishment of a manufacturing plant employing "between 500 and 600 persons.

In March 1946, the citizens of Clinton formed the Clinton Community Association for the purpose of raising funds, purchasing land and erecting a building suitable for respondent’s use. The Association made an agreement with respondent under the terms of which the Association agreed to obtain a tract of land outside the city of Clinton, containing 48 acres, and to erect thereon a factory, 380 by 180 feet in size, together with a boiler house, 40 by 30 feet, and a cement house, 40 by 26 feet. Respondent agreed to purchase the completed ■structures within thirty days after completion at a price equal to the total actual cost <of construction. Seven hundred and nine persons interested in the Clinton Community Association advanced $219,000 to finance the building program. Their investment was secured by bonds, one-tenth of which were to be redeemed each year.

Construction was begun in the spring of 1946, but was hampered by lack of materials and incessant rains. Owing to the difficulties encountered, the main structure was put up in what amounted to reverse order. That is, the cement floor was put in first, followed by walls, steel work and roof in that order. This course of construction was followed because the respondent planned to start a training program. It was intended to begin the program in June 1946, but it was delayed by the difficulties encountered.

By September 1946, the cement floor had been poured and hardened. The respondent, through its officers', anxious to begin the training program, caused temporary wooden sheds to be erected on a portion of the cement floor.

Finally, on October 15, 1946, the training program was begun in such temporary wooden sheds. Some 47 trainees were procured by respondent.

The temporary shed used for the training program was, as we have said, constructed of wood and tar paper. It was 40 by 90 feet. It was at least 100 yards from the nearest highway and the only approach to it consisted of two ruts through the mud. It contained no heating facilities. An Illinois Central locomotive was borrowed and used to furnish steam. It was so cold at times that trainees were unable to work a full day. There were no toilet facilities in the shed, the nearest conveniences being located about a block away along the railroad track. Drinking water had to be carried in .coolers from a shack of the builders about 200 yards distant. Rain seeped through the tar paper roof, the floor was frequently flooded. Electrical current for lighting and power wa9 provided by temporary wires strung along the concrete floor.

The plant was to have been substantially completed with the roof in place by Novem[915]*915ber 1946. At that time only the concrete floor had been completed. The permanent structure could not be completed until the temporary sheds were removed because the roofing cranes could not be moved through the surrounding ground, as originally intended, because of the mud. It therefore became necessary to operate them from the concrete floor. As a consequence there was danger that the beams might slip from the cranes and crush the temporary wooden training quarters.

In mid-November respondent decided, because of these conditions, to terminate the training program until the permanent structure could be erected.

On November 20, 1946, respondent received a letter from the Field Representative of the United Rubber, Cork, Linoleum and Plastic Workers of America, C.I.O. which advised “that the majority of the production and maintenance employees in the Clinton plant” had designated it as their exclusive representative for the purpose of collective bargaining. The Union asked for the institution of negotiations in respect to wages and conditions of employment. The letter advised respondent that if it failed or refused to comply with the Union’s request, proceedings would be begun before the National Labor Relations Board.

Respondent replied that the plant in Clinton was in construction and not yet under roof; that present workers were employed on a training basis; and that it would be many months before the plant could get into production.

On December 4, 1946, the respondent closed its training experiment. It gave each trainee, in addition to regular pay, a bonus equivalent to two weeks pay. The training program had been in progress for less than eight weeks, and no saleable finished product was ever produced.

On December 5, 1946, the day after the training experiment was abandoned, the respondent caused to be published in the Clinton Journal an advertisement entitled “Our Policy.” This advertisement will be considered more in detail later on in this opinion.

During the month of December 1946, the trainees themselves drew up and signed a petition which declared their gratitude and friendliness to the respondent corporation and expressed the hope that they would be reemployed when its plant reopened. On December 11, 1946, 29 of the trainees (a majority in number) addressed a letter to the field representative of the Union in which they cancelled their membership applications and notified the Union that it was no longer their representative. Again, on December 16, 1946, 32 of the former trainees notified the Chicago Regional Office of the Labor Relations Board that they did not wish to be considered members of the Union involved, had never paid dues thereto, and had requested the return of their applications.

These letters, according to the trial examiner’s findings, were not suggested, composed, drafted, executed or published by the respondent company, as suggested by the Board, but were in fact the spontaneous actions of the persons signing them.

On July 1, 1947, the plant, although not yet completed, was opened for limited operation. At that time every trainee who was in respondent’s employ, and who desired to work, except two, was either put to work immediately or informed that they would be given work as soon as it was available.

It is agreed that the action of respondent in not rehiring the two. excepted was justified for reasons not connected with or material to the present controversy.

In the meantime, upon an amended charge by the Union, the National Labor Relations Board issued its complaint against respondent, charging that it had engaged in and was engaging in unfair labor practices affecting commerce within the meaning of Sections 8(1) and (3) and Sections 2, 6 and 7 of the National Labor Relations Act, 29 U.S.C.A. §§ 152, 156, 157, 158 (1, 3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
186 F.2d 913, 27 L.R.R.M. (BNA) 2278, 1951 U.S. App. LEXIS 3337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-labor-relations-board-v-goodyear-footwear-corp-ca7-1951.