National Grain Yeast Corp. v. City of Crystal Lake

147 F.2d 711, 1945 U.S. App. LEXIS 2192
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 1, 1945
DocketNo. 8730
StatusPublished
Cited by9 cases

This text of 147 F.2d 711 (National Grain Yeast Corp. v. City of Crystal Lake) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Grain Yeast Corp. v. City of Crystal Lake, 147 F.2d 711, 1945 U.S. App. LEXIS 2192 (7th Cir. 1945).

Opinion

EVANS, Circuit Judge.

We are here reviewing an order which vacated a previously entered temporary restraining order and which also denied plaintiff’s application for a preliminary injunction, in a suit brought to restrain defendant from shutting off its storm sewers and thus prevent plaintiff from operating its plant which requires an outlet for waste waters used in its process of yeast making.

Briefly stated, this is the story: Plaintiff filed a verified complaint upon which a restraining order was entered after defendant had filed an affidavit made by its mayor. No answer was filed by the defendant. A temporary restraining order was entered. After oral argument the court made findings without further evidence and refused findings proposed by plaintiff. It then entered an order vacating the restraining order, and refusing plaintiff’s motion for a temporary injunction. This appeal followed.

The Facts. Plaintiff is a New Jersey company which manufactures bakers yeast. In 1938 it decided to locate a branch factory in the west and in the vicinity of Chicago because the perishable nature of yeast made its shipment from the east impracticable, save in expensive refrigerator cars. It selected an existing, unused dairy plant in the city of Crystal Lake and entered into negotiations with the officials of that city in regard to its selection of a [712]*712situs. It represented that it would employ 35 to 40 persons permanently, and it would spend a substantial sum of money in the city when it began operations.

Plaintiff invested $200,000 in its Crystal Lake plant and equipment, and the equipment is unfit for use in any other type of business.

In the process of making yeast, heat is generated which must be overcome. Water is used as the cooling agent. There is also waste water in the process, which has an objectionable odor. It is over the presence of this objectionable odor and its elimination that differences arise. This problem was made known to defendant before plaintiff located at Crystal Lake. In the treatment of this waste, plaintiff first utilized, at defendant’s suggestion, several lagoons located on a seven acre tract outside the city. They proved inadequate, so, under a contract with the city, it discharged the cooling, and waste, waters into the storm sewers of the city.

The contract, first negotiated in January, 1939, was re-executed, November 10, 1939, for a term of five years. The renewal provision, paragraph 11, is the covenant of major importance in this controversy. It provided:

“This Agreement shall extend for a period of five years, and expire five years from the date hereof, but is subject to renewal, providing conditions are satisfactory to both parties hereto, at the expiration of this A greement.”

"The City Council, by resolution, has declared that the odors are a nuisance, and that conditions have been unsatisfactory since the beginning of the contract, and that plaintiff has done nothing to abate the nuisance during the existence of the contract.

Plaintiff paints a different picture of the situation and attempts to avoid any culpability. It insists it has done everything within its power to minimize and eradicate the odors incident to the operation of its plant. Its complaint states:

(1) It hired, in November, 1938, two bacteriologists who were authorities on the treatment o'f industrial waste. It constructed a small plant for use in their ex-perimentations, and plaintiff excavated two large lagoons on a tract of land outside the city. This cost plaintiff large sums of money.

(2) The wastes were treated before being discharged into the storm sewer; the waste thus treated at all times met the purification standards of the Sanitary Water Board of the State of Illinois.

(3) That defendant knew, at the time the contract was made, that science had not perfected a means • for entirely eliminating the odor.

(4) On the advice of experts whom plaintiff consulted, it built a “trickling filter” and improvements thereon.

(5) In the course of its research it came upon a so-called closed system, a new and more modern method of removing odor, consisting of two large closed concrete tanks technically called anaerobic digesters; that the construction of such tanks and the apparatus used in connection therewith required a large quantity of steel and materials critical in the war effort.

(6) Plaintiff informed defendant of this new system and its belief that the apparatus would completely dispel the objectionable odors, but defendant, nevertheless, thereafter called a meeting of it Council and passed a resolution whereby it refused to renew its contract “in any event.” “That such action by the City embarrassed and greatly impeded the plaintiff and prevented it from procuring the approval which the plaintiff could otherwise have obtained, of the Sanitary Water Board of the State of Illinois, for the installation of such closed system, and from obtaining priorities from the War Production Board * * * for critical materials required for the installation of such closed system.”

(7) Plaintiff received notice “from the War Food Administration * * * that it would not recommend approval of Plaintiff’s priority, without submitting evidence from the proper officials of the City of Crystal Lake disclosing that it would permit the plaintiff to operate after the installation of such equipment.”

(8) The city and the Sanitary Board later did join1 in requesting the issuance [713]*713of the priorities, but the reply of the Federal authorities was “that the problem of the plaintiff was not, in the opinion of the Administration, of sufficient magnitude to warrant the use, at said time, of the materials sought in the application.”

(9) Plaintiff then requested Washington officials to confer with the city officials, to urge the defendant to permit the plaintiff to continue to use existing facilities until the end of the war, but defendant refused the request thus made.

(10) Plaintiff received the approval of its priority application in July, 1944, with the limitation that it must be made use of prior to October 31, 1944. Plaintiff at once proceeded with bids for the work and was ready to accept them and proceeded with the construction of the closed system, which would take five months, when “Defendant refused to permit Plaintiff to have said time so required to proceed with the construction and to complete the same, and notified the Plaintiff that it was prepared to, and would, close the shut-off valve at the effluent outlet line on November 10, 1944 and would not extend said time; that, as a result of such action, the Plaintiff was not able to proceed to install and complete such closed system as it otherwise would have been able to do; that had the Plaintiff not been prevented by the war conditions and by the action of the Defendant, it would have, prior to November 10, 1944 performed all ‘conditions’ satisfactory to the Defendant within the provision of Paragraph Eleventh * * Plaintiff is manufacturing a product essential to the war effort.

Ordinarily, the district court’s action on an application for a temporary injunction is well-nigh final. It will be modified or vacated only when it appears there was an abuse of discretion. United States v. Corrick, 298 U.S. 435, 56 S.Ct. 829, 80 L.Ed. 1263.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
147 F.2d 711, 1945 U.S. App. LEXIS 2192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-grain-yeast-corp-v-city-of-crystal-lake-ca7-1945.