Nastrom v. City of Blaine

498 N.W.2d 495, 1993 WL 107031
CourtCourt of Appeals of Minnesota
DecidedMay 28, 1993
DocketC6-92-1806
StatusPublished
Cited by1 cases

This text of 498 N.W.2d 495 (Nastrom v. City of Blaine) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nastrom v. City of Blaine, 498 N.W.2d 495, 1993 WL 107031 (Mich. Ct. App. 1993).

Opinion

OPINION

PARKER, Judge.

The City of Blaine appeals the trial court’s determination that the city council authorized public improvements by an inadequate number of votes, thereby invalidating special assessments. We affirm in part, reverse in part, and remand.

FACTS

Since 1978, respondents Dennis and Char Nastrom have owned approximately five acres of land, used as a homestead, in the City of Blaine. Before 1987, no street or *498 public improvements adjacent to their land had been proposed or approved.

In 1987, the city engineering staff began preliminary work on Project 87-11, an un-petitioned plan for improvements to an area including the Nastroms’ property and the plats of Aberdeen Oaks, Nu-Life Estates, and Olympic Glen. In December 1987 and April 1988, the owners of Aberdeen Oaks, Nu-Life Estates, and Olympic Glen submitted separate petitions to the city for street construction, water main, storm drainage, and sanitary sewer construction. These petitions were submitted independent of the city’s project. Each petition described the property owned by the landowner by legal description only and did not reference any other property. Only one petition named streets abutting the properties.

In November 1988, the Blaine City Council consolidated the three individual petitions into Project 87-11 and ordered a public hearing on the project. This combined project included the Nastroms’ property and that of other landowners who had not petitioned for improvements. The trial court found the Council’s action constituted a joinder of the four proposed projects into Project 87-11. Among other things, the combined project involved relocation of existing streets and construction of new streets. City engineer Charles Lenthe testified the land in the improvement petitions submitted by landowners constituted 48 percent of land benefiting from Project 87-11.

At a public hearing on the consolidated project in December 1988, the Nastroms appeared and opposed it. Following the hearing, the Council voted five to two to approve construction of Project 87-11.

The cost of the project was $3,116,759.98, of which $2,757,603.89 was assessed against benefiting property owners. The Nastroms were assessed $75,012.75 on Lots 4, 5, 6, and 7, Block 1, Autumn Oaks.

The Nastroms challenged the assessment in district court. In their complaint they alleged, among other things:

The City did not follow proper procedures in ordering the assessment * * *
The City failed to comply with the notice of assessment hearing requirements pursuant to M.S.A. § 429.061. The City failed to comply with the notice of improvement hearing requirements pursuant to M.S.A. § 429.031.

The city asked the Nastroms in interrogatories to specify the allegations of defects in the city’s compliance with the notice provisions of Minnesota Statutes Chapter 429. The only answer which appeared to address the question was the following:

That the notice of assessment was improper as including additional properties and providing a total assessment.'

On the morning of the first day of trial, the Nastroms, over the objections of the city, raised for the first time the issues of the adequacy of the Project 87-11 petition and the Council vote necessary for approval. The Nastroms claimed they learned of the possible deficiencies for the first time that morning. The city did not move for a continuance. The trial court admitted evidence on this issue.

The trial court found the Council failed to comply with statutory procedures and that, therefore, the project was not properly authorized. • Specifically, the trial court found that the Council had failed to ascertain, in violation of statute, whether the requisite percentage of owners in frontage of land abutting on streets named in the petition as the location of the improvement had petitioned for the project. Consequently, the court found that the Council’s 5-2 vote ordering the public improvements was insufficient because the project was an “unpetitioned” project, requiring a vote of four-fifths of the council. Accordingly, the trial court ordered the city to remit to the Nastroms any amounts they had paid on the lots in question.

The improvement project, meanwhile, has long since been completed. The City of Blaine appeals.

ISSUES

I. Did the trial court err in determining that the Nastroms’ challenge to the suffi *499 ciency of the petition was timely under Minn.Stat. § 429.036 (1988)?

II. Was Project 87-11 an unpetitioned project requiring a four-fifths vote of the council?

A. Was the city required to determine the requisite percentage of land represented in a consolidated project?
B. Did the city’s failure to pass a resolution determining the percentage of land in Project 87-11 justify invalidating the assessments?
C. Did owners of the required percentage of land in Project 87-11 petition for the improvement?
D. Was the city required to present evidence to satisfy the statutory standard of “property abutting streets named in the petition?”

DISCUSSION

This court may reverse a trial court’s findings of fact only if the findings are clearly erroneous. Minn.R.Civ.P. 52.01. This court may independently review the trial court’s rulings on questions of law. See Frost-Benco Elec. Ass’n v. Minnesota Pub. Utils. Comm’n, 358 N.W.2d 639, 642 (Minn.1984). In actions contesting an assessment, a municipality is presumed to have set the assessment legally until proved otherwise. Tri-State Land Co. v. City of Shoreview, 290 N.W.2d 775, 777 (Minn.1980).

The city makes essentially two arguments: (1) the Nastroms failed to allege procedural failures in a timely manner; and (2) the trial court erred in concluding that the city’s failure to comply with statutory procedures rendered the assessments invalid. We disagree with the city on the first issue but agree with it on the second.

This matter involves three categories of improvements in the Minnesota Statutes: (1) “unpetitioned” improvements initiated by a municipality; (2) improvement petitions initiated by owners of at least 35 percent of land abutting streets named in the petitions (“35 percent” petitions); and (3) improvement petitions initiated by all owners of land affected by improvements (“all owners” petitions). 1 See Minn.Stat. § 429.031, subds. 1, 3 (1988). Each category requires somewhat different procedures for authorizing improvements, including, for example, a different number of votes required for Council approval.

For unpetitioned improvements, which are initiated by a municipality, four fifths of all council members must vote to order the improvement. Minn.Stat. § 429.031, subd. 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nastrom v. City of Blaine
515 N.W.2d 374 (Supreme Court of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
498 N.W.2d 495, 1993 WL 107031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nastrom-v-city-of-blaine-minnctapp-1993.