Naek Construction Co. v. Wilcox Excavating, No. Cv 96 61221 S (Aug. 7, 1997)

1997 Conn. Super. Ct. 8212
CourtConnecticut Superior Court
DecidedAugust 7, 1997
DocketNo. CV 96 61221 S
StatusUnpublished

This text of 1997 Conn. Super. Ct. 8212 (Naek Construction Co. v. Wilcox Excavating, No. Cv 96 61221 S (Aug. 7, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Naek Construction Co. v. Wilcox Excavating, No. Cv 96 61221 S (Aug. 7, 1997), 1997 Conn. Super. Ct. 8212 (Colo. Ct. App. 1997).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION CT Page 8213 The plaintiff, Naek Construction Co., Inc. (hereafter "Naek") was the general contractor for the construction of the Troop C State Police Barracks in Tolland, Connecticut. Its general contract was with the State of Connecticut (hereafter "State"). Naek entered into a subcontract with the defendant, Wilcox Excavating Construction Company, Inc. (hereafter "Wilcox") for the site excavation portion of the project, said subcontract being dated May 27, 1993. Certain disputes arose between the parties resulting in termination of the aforementioned subcontract. In June of 1994, Wilcox commenced an arbitration proceeding under the arbitration clause in the subcontract. Naek filed a counterclaim. Under the rules of the American Arbitration Association (hereafter "AAA"), Attorney Daniel Marmelstein of Suffield, Connecticut, (hereafter "Arbitrator") was chosen as the sole arbitrator. The parties have conceded that he has a background in construction law and extensive experience in arbitration. After thirty-four days of hearings the Arbitrator made his award on June 5, 1996. On July 3, 1996 Naek filed a motion to vacate the arbitration award with this court. On July 24, 1996 Wilcox filed its answer and a cross-application to confirm the arbitration award. Both parties have filed several briefs, and there has been extensive oral argument by both parties before this court. On December 30, 1996, the court, with the consent of the parties and with agreement as to the language, sent to the Arbitrator a Request for Articulation. By documents dated March 14, 1997, the Arbitrator filed his Articulation of the Arbitrator's Award (hereafter "Articulation").

Naek claims that the award should be vacated because there were defects in the award that fall under CGS § 52-418 (a)(3) and (4).1 More specifically, Naek claims that the Arbitrator accepted and used evidence from Wilcox that was proffered after the close of the evidence and that the Arbitrator did not follow the procedures set forth in the submission which require the Arbitrator to follow the procedures of arbitration that would be used in an arbitration of the prime contract between Naek and the State. Naek claims that these procedures or provisions are set forth in CGS § 4-61 (d) and (e).2 Naek claims that since the submission included the sub-contract, § 6.1 thereof should have applied.

Section 6.1 states as follows: CT Page 8214

"Any controversy or claim between the contractor and Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration, which shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the Owner and the Contractor, except that a decision by the Architect shall not be a condition precedent to arbitration. If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise."

In response Wilcox claims that § 6.1 refers only to claims "arising out or related to this subcontract," and, therefore, the submission is pursuant to the subcontract, not to other documents such as the prime contract between Naek and the State, (hereafter "prime contract") and, further, that Naek waived any claim that the submission was not unrestricted by not admitting the prime contract into evidence at the arbitration hearings and by accepting and conforming to the AAA Construction Industry Rules throughout the arbitration.3 Also, Wilcox claims that CGS § 4-61 does not apply in this case. Additionally, Wilcox denies that any "new" evidence was introduced through the Appendix it presented, that what was presented was merely summaries and comparisons of portions of evidence already admitted. Wilcox also asserts that its brief and appendix were filed on March 25, 1996 and that Naek filed its objections thereto on March 26, 1996 but did not request a hearing thereon even though the Arbitrator had informed the parties that he was keeping the hearings open beyond the submission of briefs. On April 30, 1996, the Arbitrator granted three of Naek's objections and denied four and declared the hearings closed. (See Naek's original brief dated July 30, 1996 (Exhibit 12)).

STANDARD OF REVIEW

The determination of the issues before this court has to be CT Page 8215 based upon the evidence submitted to it with the briefs of the parties. Further, it is plaintiff's burden to produce sufficient evidence to invalidate the award. Awards based upon consensual arbitration are subject to only minimal judicial intervention. See Metropolitan District Commission v. AFSCME, 37 Conn. App. 1 (1995). Every reasonable presumption and intendment must be indulged in favor of the award. Cashman v. Sullivan DoneganP.C., 23 Conn. App. 24 (1990). Unless the submission provides otherwise, an Arbitrator has authority to decide factual and legal questions, and courts will not review the evidence, or where the submission is unrestricted, the Arbitrator's determination of legal questions. O G/O'Connell Joint Venturev. Chase Family Limited Partnership, 203 Conn. 133 (1987). "When the scope of the submission award is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission." SCRRA v. AmericanRe-Fuel Co. of Southeastern Connecticut, 44 Conn. Sup. 482, 484,485 (1997) affirmed, 44 Conn. App. 728 (1997). "The authority of an arbitrator to adjudicate the controversy is limited only if the agreement contains expresses language restricting the breadth of the issues, reserving explicit rights, or conditioning the award on court review." Id. 485.

ISSUES:

1. Was the award in accordance with the submission? Wasit, therefore, unrestricted? The submission was the subcontract between the parties. Article I of the subcontract does say that "the subcontract documents consist of . . . (2) the Prime Contract, consisting of the Agreement between the Owner and Contractor . . ." (State of Connecticut and Naek). Article 6.1 of the subcontract provides that arbitration ". . . shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the Owner and the Contractor . . . If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association . . . ". This court finds no evidence that a signed prime contract between the State and Naek, either a copy or the original, was before the Arbitrator. Plaintiff claims it was incorporated by reference, but assuming that is true, an executed prime contract should have been submitted to the Arbitrator to ensure its accuracy and to advise the Arbitrator of its arbitration provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
Cashman v. Sullivan & Donegan P.C.
578 A.2d 167 (Connecticut Appellate Court, 1990)
Metropolitan District Commission v. American Federation of State
654 A.2d 384 (Connecticut Appellate Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Conn. Super. Ct. 8212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/naek-construction-co-v-wilcox-excavating-no-cv-96-61221-s-aug-7-connsuperct-1997.