Myers Construction Co. v. Wood River Drainage & Levee

221 Ill. App. 473, 1921 Ill. App. LEXIS 63
CourtAppellate Court of Illinois
DecidedMarch 30, 1921
StatusPublished
Cited by2 cases

This text of 221 Ill. App. 473 (Myers Construction Co. v. Wood River Drainage & Levee) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myers Construction Co. v. Wood River Drainage & Levee, 221 Ill. App. 473, 1921 Ill. App. LEXIS 63 (Ill. Ct. App. 1921).

Opinion

Mr. Justice Boggs

delivered the opinion of the court.

An action in case was brought in the circuit court of Madison county by appellant, Myers Construction Company, against the Wood Biver Drainage and Levee District.

The declaration consists of two counts and charges that appellee, Drainage District, organized for the purpose of protecting a large area of land from overflow by the waters of Wood river, and having control of certain levees and channels for the purpose, among other things, of controlling the said waters in their course through Wood river, on August 23, 1918, entered into a written contract with appellant to excavate and remove a large amount of rock from the bed of the channel of Wood river, at or near a place in said district known as Milton bridge; that by the terms of said contract, appellant was required to begin said work by September 1, 1918, and to complete the same by December 1, of that year; that appellant, for the purpose of complying with said contract, installed at great expense in the channel of said river, at or near Milton bridge, a large amount of machinery and equipment, and employed and maintained a large number of laborers, teams and wagons used in the necessary performance of said work, and that while its said equipment and machinery were so installed in said river, and after appellant had begun the performance of its contract, appellee, through its officers and agents, erected and constructed, or caused to be erected and constructed, a high embankment or dam across the channel of said river at a point about a mile below Milton bridge, thereby obstructing and causing said waters to back up and collect in great quantities towards and beyond Milton bridge, and to overflow appellant’s equipment and machinery, thereby damaging appellant in the sum of $3,000. The contract between the parties was set out in hcec verba. To said declaration appellee filed a plea of the general issue.

At the close of appellant’s evidence, on motion of appellee, the court directed a verdict and rendered judgment against appellant in bar of action and for costs. To reverse said judgment this appeal is prosecuted.

. The questions raised on the record by the assignment of errors are, first, as to whether or not the declaration states a cause of action; second, as to whether the evidence of appellant with the inferences reasonable to be drawn therefrom was sufficient to require that the case be submitted to the jury.

On the first proposition, it is contended by appellee that the declaration fails to state any neglect on the part of appellee which would render it liable to appellant in damages for the injuries suffered by it. In our opinion the averments of the declaration set forth a right of action on the part of appellant.

The second proposition, as, to whether or not the evidence offered by appellant fairly tends to prove the averments of its declaration, raises a question of law as the facts are not disputed. The record discloses that Wood river drains a large area of land and at times of heavy rainfall frequently overflows. Appellee district was organized under the Levee Act of 1909 for the purpose of straightening Wood river, which is a tortuous stream, and for protecting the land comprising Wood river valley against overflow. The district comprised about 5,000 acres of land and embraced substantially all the land in Wood river valley from the bluffs to the Mississippi river and is about 2 miles wide and from 4 to 5 miles long.

At Milton bridge there was in the bed of the channel a large amount of rock formation covering an area of about 40 feet wide and 350 feet long. On August 23,1918, appellant entered into a written contract with appellee district to excavate and remove this rock from the bed of the channel to a depth of from 1 to 5 feet. Under said contract appellant was to begin work by September 1 and was to complete same by December 1, 1918. The contract provided among other things: “The contractor will not be required to work when back water of the Mississippi river is above an elevation of 416, except that drilling should be done and can be done on higher parts of the work when back water is below 419.5. No work will be required when floods are in Wood river, or if it is making a discharge of more than 150 cubic feet per second. * * * Time lost by reason of floods or back water or rainy days will be added to the time of completion, but it is understood that only actual time as above noted will be taken into account.”

About one mile below and southwest of Milton bridge, Wood river makes a rather abrupt curve and forms an elbow or “horseshoe.” Prior to and at the time of the making of said contract, appellee district was engaged in a general scheme of straightening and deepening the channel of Wood river from the upper end of this “horseshoe” to the Mississippi river. This plan involved the cutting of a new channel across the short side or between the points of the “horseshoe,” thereby eliminating the sharp curve made by the old bed of the river. Appellee had let the contract to do this work to the firm of Millville Brothers and they in turn had sublet the same to Smith Brothers, subcontractors. This work was being carried on at the time appellant engaged by contract to remove the rock from the bed of Wood river. The bottom of the channel or river at the upper point of the horseshoe was from 20 to 22 feet. The plans and specifications as testified to by the engineer of appellee district disclosed that the channel of said cut-off. was to be cut to a depth of within 6 feet of the bottom of the channel of Wood river. In other words, the new channel or “cut-off” was not to be excavated to as great depth as the river at the point where the “cut-off” began, by about 6 feet. The evidence further discloses that before the new channel had been completed, according to the plans and specifications as testified to by the engineer, Mulville Brothers or their subcontractors, under the supervision of the engineer of said district and according to the plans and specifications of said district, as testified to by said engineer, constructed a dam across the channel of Wood river at the upper end of the horseshoe. Said dam was constructed to the full height of the embankment; in other words, to the height of 20 to 22 feet. ' At the time the dam was put in, the evidence discloses that the new channel had not been cut as deep as the specifications required. We quote from the testimony of the engineer with reference to this work as given in the abstract at page 12: “As engineer of the district, I laid out the construction of the dam embankment and gave stakes, and told the contractor where to place it. It was constructed under contract with the Wood River Drainage and Levee District. I had charge of the work there, and in the course of my duties, as engineer of the district, I staked out the dam and had general supervision of that work, the same as any other work. The construction of the dam started about October lOfcb. At the time the embankment was built tbe new channel across the points of the elbow or horseshoe in the river was of various depths, from ten to possibly twelve feet. Where it had the least depth wasn’t more than about eight feet. The purpose of the embankment or dam was to turn the water; make it flow through the new channel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People Ex Rel. Hepburn v. Maddox
91 N.E.2d 107 (Appellate Court of Illinois, 1950)
Belding v. State
12 Ill. Ct. Cl. 438 (Court of Claims of Illinois, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
221 Ill. App. 473, 1921 Ill. App. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myers-construction-co-v-wood-river-drainage-levee-illappct-1921.