Myaer v. Nodak Mutual Insurance Co.

2012 ND 21, 812 N.W.2d 345, 2012 N.D. LEXIS 21, 2012 WL 426727
CourtNorth Dakota Supreme Court
DecidedFebruary 10, 2012
Docket20110153
StatusPublished
Cited by22 cases

This text of 2012 ND 21 (Myaer v. Nodak Mutual Insurance Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myaer v. Nodak Mutual Insurance Co., 2012 ND 21, 812 N.W.2d 345, 2012 N.D. LEXIS 21, 2012 WL 426727 (N.D. 2012).

Opinions

VANDE WALLE, Chief Justice.

[¶ 1] Nodak Mutual Insurance Company appealed from a judgment awarding Barry Myaer $34,938.24 plus interest in his breach of contract action against Nodak. We conclude the district court did not err in ruling Myaer was entitled to deferred commissions payable to him in December 2009, but did err in ruling those commissions could exceed 10 percent under the terms of the parties’ contract. We affirm in part, reverse in part, and remand for further proceedings.

I

[¶ 2] On July 7, 2009, Nodak terminated Myaer’s “Career Producer’s Contract” after he had served as a captive insurance agent for the company in Mohall for almost 29 years. The most recent Career Producer’s Contract Myaer signed was dated December 28, 2004, but Nodak had subsequently sent similar contracts throughout the years, the last of which was effective January 1, 2009. The contract provided different commission calculations depending on the type of policy written by Myaer. The contract provided for a 10 percent commission on gross premiums for sales of multi-peril crop insurance (“MPCI”).

[¶ 3] The premium payments for MPCI policies were normally paid in two installments by the policyholders. An addendum to the contract provided:

A. Career Producer will receive 50% of the commissions payable in the month following those policies processed by AFBIS.
B. Career Producer will receive balance of commissions due on those policies that are paid in full in the month following processed premium.

According to Myaer, the first installment was paid in August after acreage reports were submitted and the second installment was paid in December after policyholders paid their premiums in full. The contract addendum also provided for reductions of the 10 percent commission under certain circumstances:

C. A commission reduction of 1% will be applied to all gross premiums if all submissions and loss reports are not submitted on-line.
D. A commission reduction of 1% will be applied to all gross premiums if all MPCI notes including any outstanding interest are not paid and received in the home office prior to November 1st.

[¶ 4] The contract also explained when commissions were “earned”:

COMMISSIONS, CREDITS, AND REFUNDS. Commissions on any policy or on added coverage shall be earned when: (1) the policy or added coverage has been accepted by the Company or the other insurers identified in the Ad-dendums to this Contract; (2) the policy is issued; and (3) premium is received and processed by the Company.

The contract provided that it “may be canceled by either party, with or without cause, at any time upon giving notice, in writing, to the other party,” and further provided: “Upon cancellation of this Con[349]*349tract, no further commission or premium credit shall accrue.”

[¶ 5] After Myaer’s termination in July 2009, Nodak paid him $20,338.72 in August 2009 for commissions owed to him. Myaer’s “MPCI Commission Statement” for the 2009 crop year indicated $22,500.45 in deferred commissions remained to be paid. However, in December 2009, . Nodak did not pay Myaer the deferred commissions on the policies he had sold, claiming he was no longer entitled to them. Nodak claimed Myaer was not entitled to further commissions because his contract was terminated before policyholders had paid the second installments on their premiums.

[¶ 6] In April 2010, Myaer brought this action against Nodak claiming, among other theories not relevant to the appeal, that it had breached the Career Producer’s Contract by failing to pay him the deferred commissions in December 2009. Both parties moved for summary judgment. Myaer filed an affidavit setting forth his calculations of what he was owed and claiming, “[t]he way MPCI commissions were typically paid, if I did my reports via the Internet and all farmers’ notes were paid, my total commission would be 12 per cent....” Nodak presented a copy of the Career Producer’s Contract, and filed a “Motion in Limine to Exclude Testimony Contrary to Career Producer’s Contract.” Nodak argued Myaer’s claim to a 12 percent commission was barred by the parol evidence rule because it conflicted with the express terms of the 2009 contract, which provided for a maximum 10 percent commission.

[¶ 7] The district court granted summary judgment in favor of Myaer, but did not address Nodak’s motion in limine. The court ruled that, under the terms of the contract, Myaer’s right to receive the second installment of commissions had already “accrued” at the time Nodak terminated the contract. The court awarded him a 10 percent commission on the policies he had sold in the amount of $22,500.45 and also awarded him a “bonus” in the amount of $9,003.70 in accordance with Myaer’s calculations, reasoning “it does not appear that Nodak has actually challenged the work product of Mr. Myaer.” Myaer was also awarded pre- and post-judgment interest.

II

[¶ 8] Nodak argues the district court erred in concluding Myaer is entitled to the deferred commissions payable in December 2009 because the ruling ignores the plain language of the Career Producer’s Contract.

[¶ 9] The standard for reviewing a summary judgment is well-established:

“Summary judgment is a procedural device for the prompt resolution of a controversy on the merits without a trial if there are no genuine issues of material fact or inferences that can reasonably be drawn from undisputed facts, or if the only issues to be resolved are questions of law. A party moving for summary judgment has the burden of showing there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. In determining whether summary judgment was appropriately granted, we must view the evidence in the light most favorable to the party opposing the motion, and that party will be given the benefit of all favorable' inferences which can reasonably be drawn from the record. On appeal, this Court decides whether the information available to the district court precluded the existence of a genuine issue of material fact and entitled the moving party to judgment as a matter of law. Whether the district court [350]*350properly granted summary judgment is a question of law which we review de novo on the entire record.”

Riverwood Commercial Park, LLC v. Standard Oil Co., Inc., 2011 ND 95, ¶ 6, 797 N.W.2d 770 (quoting Missouri Breaks, LLC v. Burns, 2010 ND 221, ¶ 8, 791 N.W.2d 33).

[¶ 10] Generally, the interpretation of a written contract is a question of law for the court, making summary judgment an appropriate method of disposition in contract disputes. See Tri-State Ins. Co. v. Commercial Grp. W., LLC, 2005 ND 114, ¶ 10, 698 N.W.2d 483; Garofalo v. Saint Joseph’s Hosp., 2000 ND 149, ¶ 7, 615 N.W.2d 160. We construe written contracts to give effect to the parties’ mutual intention when the contract was formed, and if possible, we look to the writing alone to determine the parties’ intent. See Doeden v. Stubstad, 2008 ND 165, ¶ 14, 755 N.W.2d 859; N.D.C.C. § 9-07-03. Words in a contract are construed in. their ordinary and popular sense, unless they are used by the parties in a technical sense, or unless a special meaning is given to them by usage. See Riverwood Commercial Park, LLC, 2011 ND 95, ¶ 7, 797 N.W.2d 770; N.D.C.C. § 9-07-09. Under N.D.C.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ordahl v. Lykken
2022 ND 193 (North Dakota Supreme Court, 2022)
Highline Exploration, Inc. v. QEP Energy Company
43 F.4th 813 (Eighth Circuit, 2022)
Blasi v. Bruin E&P Partners
2021 ND 86 (North Dakota Supreme Court, 2021)
Bearce v. Yellowstone Energy Development, LLC
2019 ND 89 (North Dakota Supreme Court, 2019)
Barna, Guzy & Steffen, Ltd. v. Johnson
2018 ND 205 (North Dakota Supreme Court, 2018)
Burk v. State Ex Rel. Board of University & School Lands
2017 ND 25 (North Dakota Supreme Court, 2017)
Holverson v. Lundberg
2016 ND 103 (North Dakota Supreme Court, 2016)
Welch Construction & Excavating, LLC v. Duong
2016 ND 70 (North Dakota Supreme Court, 2016)
Desert Partners IV, L.P. v. Benson
2016 ND 37 (North Dakota Supreme Court, 2016)
Clark v. Farmers Union Mutual Insurance
2015 ND 300 (North Dakota Supreme Court, 2015)
Golden Eye Resources, LLC v. Ganske
2014 ND 179 (North Dakota Supreme Court, 2014)
Finstad v. Gord
2014 ND 72 (North Dakota Supreme Court, 2014)
K & L Homes, Inc. v. American Family Mutual Insurance Co.
2013 ND 57 (North Dakota Supreme Court, 2013)
Bakken v. Duchscher
2013 ND 33 (North Dakota Supreme Court, 2013)
State v. Kusy
2013 ND 23 (North Dakota Supreme Court, 2013)
Tibert v. Nodak Mutual Insurance Co.
2012 ND 81 (North Dakota Supreme Court, 2012)
Estate of Paulson
2012 ND 40 (North Dakota Supreme Court, 2012)
Myaer v. Nodak Mutual Insurance Co.
2012 ND 21 (North Dakota Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 ND 21, 812 N.W.2d 345, 2012 N.D. LEXIS 21, 2012 WL 426727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myaer-v-nodak-mutual-insurance-co-nd-2012.