M.V.P. Ltd. v. Matt

855 N.E.2d 507, 167 Ohio App. 3d 396, 2006 Ohio 1634
CourtOhio Court of Appeals
DecidedMarch 31, 2006
DocketNo. OT-05-046.
StatusPublished
Cited by1 cases

This text of 855 N.E.2d 507 (M.V.P. Ltd. v. Matt) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.V.P. Ltd. v. Matt, 855 N.E.2d 507, 167 Ohio App. 3d 396, 2006 Ohio 1634 (Ohio Ct. App. 2006).

Opinion

Skow, Judge.

{¶ 1} Appellants, David A. Matt and Kathleen Matt, appeal from a judgment entry by the Ottawa County Common Pleas Court granting the motion for summary judgment of appellee, M.V.P. Ltd., L.L.C. For the reasons that follow, the judgment of the trial court is reversed.

{¶ 2} Mr. and Mrs. Matt entered into a purchase agreement with developer M.V.P., wherein the Matts agreed to pay M.V.P. the sum of $100,000 for a lot in the Emerald Shores Estates Subdivision, in Ottawa County, Ohio. The deed for that transfer was filed on July 2, 1999. Under the purchase agreement, if the Matts failed to “commence construction” of a home on the property within 60 months from the date that the deed was filed, the seller had the right to repurchase that property.

{¶ 3} It is undisputed that the Matts waited until the first week of June 2004, just one month before the 60-month deadline, to get started on the plans for their home-budding project. At that time, Mr. Matt contacted M.V.P. principal and architectural-control-committee member Jim Veite, and asked for the following: (1) a decision as to whether a breezeway that he was considering satisfied the subdivision’s requirement that the home include an attached garage and (2) a copy of an updated site plan for his lot.

*398 {¶ 4} M.V.P.’s next communication to Mr. Matt came not from Veite but from M.V.P.’s attorney, Russell T. McLaughlin, and was in the form of a letter, dated June 25, 2004, which stated that M.V.P. was exercising its right to repurchase his property.

{¶ 5} During the first week of July 2004, Mr. Matt, never having heard back from Veite, submitted a sketch of his proposed house for approval by the architectural-control committee. Mr. Matt later completed his drawings and, at some point around the end of July or early August 2004, submitted them for approval. On August 19, 2004, Mr. Matt took his plans to the Danbury Township zoning inspector and received his building permit.

{¶ 6} Although the plans were never officially approved or rejected by the architectural-control committee, Veite informally indicated to Mr. Matt that they “looked all right” to him. And as late as August 19, 2004, Veite approved a change in the Matts’ plans — following a vote by the full three-member architectural-control committee — that would allow for a more lenient five-foot side-yard requirement, rather than the original ten-foot side-yard requirement.

{¶ 7} Despite the slow, but apparently continuing, progress in plan-approval process, the attorney for M.V.P. reiterated the developer’s intention to repurchase the lot in a letter to the Matts dated September 10, 2004. This time, he enclosed two contracts for the repurchase, with instructions that the Matts sign and return them for execution by Veite.

{¶ 8} On or about October 7, 2004, the Matts sent a letter to Veite and McLaughlin, which — without referring to the attempted repurchase — indicated that they were unable to build their home as a result of M.V.P.’s failure to move two storm sewer pipe sections from the property.

{¶ 9} On October 14, 2004, M.V.P. filed against the Matts a complaint for specific performance that requested reconveyance of the property to M.V.P. The Matts filed their answer, and on December 1, 2004, filed a motion for summary judgment in which they alleged that under the real estate purchase contract and the declarations for the subdivision, the homeowners’ association, and not the developer, was the real party in interest holding the conditional right to repurchase. The trial court initially granted the Matts’ motion, and the complaint was dismissed. Then, upon a request for consideration and motion for relief from judgment, the court reversed itself, set aside the dismissal, and denied the motion for summary judgment.

{¶ 10} Both M.V.P. and the Matts filed motions for summary judgment based upon the facts of the case as demonstrated by exhibits, affidavits, and depositions. On August 5, 2005, the trial court granted M.V.P.’s motion and denied that filed *399 by the Matts. It is from this decision and judgment entry that the Matts appealed, setting forth the following assignments of error:

{¶ 11} I. “The court erred in failing to rule that any right of repurchase runs to the Emerald Shores Estate Homeowners Owners Association, Inc., not M.V.P. Ltd., L.L.C.”

{¶ 12} II. “The court erred in failing to rule that appellants obtaining home plans and submitting them to plaintiff for architectural control approval prior to the fifth year anniversary combined with obtaining a building permit substantially complied with any requirement to commence construction within the five-year period.”

{¶ 13} III. “When time is not of the essence in a real estate contract and the obligor is substantially and demonstrably moving toward performance, Ohio law will not support a forfeiture of the obligor’s interest.”

{¶ 14} IV. “The trial court erred in failing to add the appellants’ $12,000 payment for the boat slip to the $100,00 lot purchase price.”

{¶ 15} An appellate court reviewing a trial court’s granting of summary judgment does so de novo, applying the same standard used by the trial court. Grafton v. Ohio Edison Co. (1996), 77 Ohio St.3d 102, 105, 671 N.E.2d 241. Civ.R. 56(C) provides:

{¶ 16} “Summary judgment shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, written admissions, affidavits, transcripts of evidence, and written stipulations of fact, if any, timely filed in the action, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. No evidence or stipulation may be considered except as stated in this rule.”

{¶ 17} Summary judgment is proper when (1) no genuine issue of material fact remains to be litigated, (2) the moving party is entitled to judgment as a matter of law, and (3) when the evidence is viewed most strongly in favor of the nonmoving party, reasonable minds can come to but one conclusion, a conclusion adverse to the nonmoving party. Ryberg v. Allstate Ins. Co. (July 12, 2001), 10th Dist. No. 00AP-1243, 2001 WL 777121, citing Tokles & Son, Inc. v. Midwestern Indemn. Co. (1992), 65 Ohio St.3d 621, 629, 605 N.E.2d 936.

{¶ 18} The moving party bears the initial burden of informing the trial court of the basis for the motion and identifying those portions of the record that demonstrate the absence of a genuine issue of fact as to an essential element of one or more of the nonmoving party’s claims. Dresher v. Burt (1996), 75 Ohio St.3d 280, 292, 662 N.E.2d 264. Once this burden has been satisfied, the nonmoving party has the burden, as set forth at Civ.R. 56(E), to offer specific facts showing a genuine issue for trial. Id.

*400

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shrock v. Mullet
2019 Ohio 2707 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
855 N.E.2d 507, 167 Ohio App. 3d 396, 2006 Ohio 1634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mvp-ltd-v-matt-ohioctapp-2006.