Muschlitz Excavating, Inc. v. Gary J. Strausser Homebuilders, Inc.

36 Pa. D. & C.5th 116, 2014 Pa. Dist. & Cnty. Dec. LEXIS 295
CourtPennsylvania Court of Common Pleas, Northampton County
DecidedFebruary 14, 2014
DocketNo. C-48-CV-2012-4247
StatusPublished

This text of 36 Pa. D. & C.5th 116 (Muschlitz Excavating, Inc. v. Gary J. Strausser Homebuilders, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Northampton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muschlitz Excavating, Inc. v. Gary J. Strausser Homebuilders, Inc., 36 Pa. D. & C.5th 116, 2014 Pa. Dist. & Cnty. Dec. LEXIS 295 (Pa. Super. Ct. 2014).

Opinion

BARATTA, J.,

ORDER OF COURT

And now, this day of February, 2014, upon consideration of the defendant, Gary J. Strausser Homebuilders, Inc.’s, motion for partial summary judgment, and the plaintiff, Muschlitz Excavating, Inc.’s, response thereto, it is hereby ordered that said motion is denied.

STATEMENT OF REASONS

Facts and Procedural History

On May 4, 2012, the plaintiff, Muschlitz Excavating, Inc., filed its complaint, in which it avers the following:

The defendant, Gary J. Strausser Homebuilders, Inc., hired the plaintiff to install infrastructure and sitework improvements for the defendant’s Northwood Commons development project. On August 23, 2011, the parties entered into a subcontractor agreement/ contract (hereinafter “the contract”). Under the contract, the work was to begin on August 25, 2011, and end no later than May 3, 2012, with intermediary deadlines and payment set forth by a job schedule. The defendant was required under the contract to pay the plaintiff a total sum of $1,917,632.44, in installments as determined by the job schedule, in exchange for the plaintiff’s complete performance. Between October and December of 2011, the parties executed change orders, which altered the performance and payment under the contract. Pursuant to the change orders, the defendant was to pay the plaintiff [118]*118a total of $2,084,922.96 for the new scope of work to be performed, plus $14,600.00 for importing crushed rock.

The plaintiff could not complete the work as scheduled in the contract due to delays, which the plaintiff argues were caused by the defendant’s failure to secure permits and/or zoning approvals for the development project. The plaintiff further alleges that despite its best efforts to keep the project on schedule, it could not perform due to the defendant’s interference. The plaintiff argues that the defendant has breached the contract, the contractual amendments, and the implied covenant of good faith and fair dealing.

The plaintiff has pleaded in the alternative, claims for breach of contract and unjust enrichment. The plaintiff claims that the defendant has been unjustly enriched by the plaintiff’s work performed under the contract in the amount of $127,506.05. The plaintiff also seeks breach of contract damages in the total amount of $450,019.50 (which subsumes the $127,506.05 for work completed and not paid for in full).

The paragraphs of the contract relevant to our determination are as follows:

SUBCONTRACTORS AGREEMENT/CONTRACT
5. PAYMENT: Contractor will pay to subcontractor the contract price in installments consisting of progress payments and a final payment on completion of the work according to the schedule.... Each progress payment will cover the work done during the pay period. Subcontractor shall provide contractor with an application for payment (invoice)..... Contractor may [119]*119withhold payment while subcontractor is in material breach of this contract Subcontractor acknowledges that contractor may also decline to approve all or any portion of a request for payment (1) After legal claims related to subcontractor have been filed and served on contractor or owner, (2) If subcontractor is delinquent in paying sub-subcontractors, employees or material suppliers for work and/or material that the subcontractor has received payment for from contractor, (3) if it becomes apparent that the work cannot be completed or finished by the contract completion date, (4) If subcontractor is responsible for substantial damage to work of owner or a separate contractor.
7. PERFORMANCE OF WORK: The subcontractor... shall vigorously perform the work specified in the contract documents according to the schedule.... Time is of the essence in regards to this agreement. In meeting that schedule, the subcontractor...shall maintain at all times a rate of progress satisfactory to contractor and adequate to assure full and timely performance of the work specified pursuant to this subcontract. If restorative or remedial work becomes necessary to correct any defect, omission or other problem with regard to the subcontractor’s work in whole or in part, the subcontractor...shall provide the necessary labor and materials to cure any such defect, omission or other problem within five (5) days after written notice is received from the contractor, provided such defect, omission or other problem is detected within 18 months from the date the work was completed....Failure to correct or cure such defect, omission or other problem will result in withholding of that portion of payment for
[120]*120the uncompleted or defective work.
9. COOPERATION: Subcontractor...shall fully cooperate with the contractor...and shall not interfere, hinder, delay or obstruct the performance of work by the contractor, other principal contractors, or other subcontractors.
21. ADDITIONAL WORK AUTHORIZATION: Any and all work not specifically covered under this contract will be considered additional work. All additional work must be approved by contractor in writing prior to commencement. Failure to receive written authorization will result in nonpayment.
23. WARRANTY: Except as otherwise provided in this agreement, subcontractor warrants that work performed under this contract shall conform to the contract documents and be free of defects in material, or design furnished, or workmanship performed by subcontractor...for eighteen (18) months....
SPECIFICATIONS
Federal, State and Local Approvals/Pennits
The contractor is responsible to obtain all federal, state and local approvals.

[121]*121Complaint, exhibit “A” — subcontractors agreement/ contract (emphasis in original).

On July 2, 2012, the defendant filed its answer with new matter and counterclaim to plaintiff’s complaint. In the defendant’s new matter, it avers that the plaintiff’s claims are barred: (1) by provisions in the contract, (2) because the plaintiff committed a material breach of the contract, and (3) because of set off and/or recoupment. In the counterclaim, the defendant avers that the plaintiff failed to complete its work in a timely fashion and was in breach of the “time is of the essence” provision, causing the defendant to terminate its contract with the plaintiff. Further, the defendant contends that the work did not conform to the contract and that other work was defective and, therefore, violated warranties.

On July 17, 2012, the plaintiff filed its reply to new matter and counterclaim of defendant. The plaintiff also pleads a new matter, asserting equitable defenses to the defendant’s counterclaim.

The parties engaged in significant discovery, which included depositions and interrogatories. On November 22, 2013, the date by which discovery was required to be completed, the defendant filed its motion for partial summary judgment, to which it attached multiple exhibits relating to the contract. On that same date, the defendant filed its memorandum of law in support of its motion.

On December 13, 2013, the plaintiff filed its answer to defendant’s motion for partial summary judgment, to which it attached exhibits relating to discovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kee v. Pennsylvania Turnpike Commission
722 A.2d 1123 (Commonwealth Court of Pennsylvania, 1998)
White v. Owens-Corning Fiberglas, Corp.
668 A.2d 136 (Superior Court of Pennsylvania, 1995)
Moses v. T.N.T. Red Star Express
725 A.2d 792 (Superior Court of Pennsylvania, 1999)
Lugo v. Farmers Pride, Inc.
967 A.2d 963 (Superior Court of Pennsylvania, 2009)
Birchwood Lakes Community Ass'n v. Comis
442 A.2d 304 (Superior Court of Pennsylvania, 1982)
Harber Philadelphia Center City Office Ltd. v. LPCI Ltd. Partnership
764 A.2d 1100 (Superior Court of Pennsylvania, 2000)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Liddle v. Scholze
768 A.2d 1183 (Superior Court of Pennsylvania, 2001)
Ertel v. Patriot-News Co.
674 A.2d 1038 (Supreme Court of Pennsylvania, 1996)
Wilson Area School District v. Skepton
895 A.2d 1250 (Supreme Court of Pennsylvania, 2006)
Penn Center House, Inc. v. Hoffman
553 A.2d 900 (Supreme Court of Pennsylvania, 1989)
P.J.S. v. Pennsylvania State Ethics Commission
723 A.2d 174 (Supreme Court of Pennsylvania, 1999)
Young v. Commonwealth Department of Transportation
744 A.2d 1276 (Supreme Court of Pennsylvania, 2000)
Marks v. Tasman
589 A.2d 205 (Supreme Court of Pennsylvania, 1991)
Garcia v. Savage
586 A.2d 1375 (Superior Court of Pennsylvania, 1991)
Sebelin Ex Rel. Sebelin v. Yamaha Motor Corp., USA
705 A.2d 904 (Superior Court of Pennsylvania, 1998)
O'ROURKE v. Pennsylvania Department of Corrections
730 A.2d 1039 (Commonwealth Court of Pennsylvania, 1999)
Schenck v. K.E. David, Ltd.
666 A.2d 327 (Superior Court of Pennsylvania, 1995)
Murphy v. Duquesne University of Holy Ghost
777 A.2d 418 (Supreme Court of Pennsylvania, 2001)
TOWNSHIP OF PISCATAWAY v. Duke Energy
389 F. Supp. 2d 607 (D. New Jersey, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
36 Pa. D. & C.5th 116, 2014 Pa. Dist. & Cnty. Dec. LEXIS 295, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muschlitz-excavating-inc-v-gary-j-strausser-homebuilders-inc-pactcomplnortha-2014.