Murr v. Western Assurance Co.

50 A.D. 4, 64 N.Y.S. 12
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 15, 1900
StatusPublished
Cited by6 cases

This text of 50 A.D. 4 (Murr v. Western Assurance Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murr v. Western Assurance Co., 50 A.D. 4, 64 N.Y.S. 12 (N.Y. Ct. App. 1900).

Opinions

Spring, J.:

In 1896 the plaintiff owned a canal boat in use on the Erie canal, which was insured by defendant in the sum of $1,700. On August 9, 1896, the boat ran against some concealed rocks in the canal near Pendleton, in the county of Niagara, and was badly injured. It was loaded with 8,000 bushels of wheat which became water-soaked and swelled, causing the boat to spread apart about three feet. The plaintiff promptly notified the defendant of the accident, and the next day its agent came from Buffalo and took possession of it for the purpose of making repairs, and it was towed to Buffalo.

By the terms of the policy it was provided that, in case disaster befell the boat, the defendant should select one surveyor and the plaintiff one, to ascertain and report by specifications, in writing, under oath, “ both the amount of the work and the manner in which it shall be done to make said vessel good for any damage caused by the disaster, without making good defects caused by. rottenness,” and for the latter defects, if they were essential and so reported by the surveyors, the whole expense thereof was to be borne by the assured. The policy provided, also, for the way in which the repairs should be made. It further provided that no partial loss should be paid by the assurer unless in excess of $100, and if the repairs cost to exceed that sum, [6]*6$100 thereof should be paid by the assured, which was designated : “ Particular average $100.00.” Surveyors were chosen by the parties and specifications duly prepared by them, and the repairs were made in conformity therewith. The repairs were made by one Murphy, and in connection therewith he did extra work regarded as advisable to make the boat seaworthy, and the bill for this amounted to $319.72, and it was this extra work which gave rise to the controversy between the parties.

It is undisputed that the specifications made by the surveyors did not include those repairs made by Murphy for extra work. There is no pretense, therefore, that the defendant ever expected to pay for these repairs, and it is likewise patent that the extra repairs were due to the inherent decay of the timbers and in no way chargeable to the accident, and yet were proper to make the boat suitable for use. The case, therefore, presents this somewhat anomalous situation: The boat came lawfully into the possession of .the defendant to make the repairs consequent upon the disaster. The defendant complied substantially with the conditions of the policy it issued to plaintiff, causing the repairs to be made in conformity to the specifications and paying therefor. The possession of Murphy was its possession, constructively, and the warrant for it was solely the necessity for repairing the boat. The plaintiff ordinarily would be entitled to the return of his boat upon paying his average of $100. But other repairs were made by Murphy, who was in actual possession. If they were made under proper employment or authority, then he had a right to retain the possession of the boat until his claim was paid. These deductions are. elementary. If Murphy declined to surrender the boat unwarrantably, then the defendant would be liable, for it was responsible for the possession of Murphy, and when the specific purpose of that possession was accomplished it must see that the boat was restored to the plaintiff. If it omitted to do so, upon demand, conversion would lie; that is, ordinarily, the plaintiff would not be obliged to look to Murphy for his boat, who was not employed by him to make the repairs contemplated by the surveyors.

In stating that the possession of Murphy was that of the defendants I have taken the most favorable view of the evidence for the plaintiff, as he is entitled to that on this motion. The defendant’s [7]*7counsel insists that Murphy was in possession by the consent of both parties, and that when the defendant paid its portion of the expenses it was absolved from any further liability and the plaintiff was relegated to his remedy against Murphy. The contract of insurance provides that the insurer may enter into a contract to make the repairs, and this implies that it must pay therefor. The surveyors may determine that there are “ defects caused by rottenness ” requiring repair, and may include them in the specifications. The plaintiff is liable for the payment of such repairs, but it cannot be that the person who makes them by virtue of a contract with the defendant must obtain his compensation from the plaintiff. The ■contract is with the defendant, not with the plaintiff. The defendant is primarily chargeable with the payment of all the repairs provided for in the specifications, and it then holds its claim against the plaintiff for whatever is chargeable to him. That was the evident construction given by the defendant to the policy in this case. It made the contract with Murphy without any consultation with the plaintiff, and it did not even carry out that provision in the policy requiring the contract to he let to the lowest bidder. It ■assumed that the plaintiff had nothing to do with that matter, but that the question of repairs was exclusively committed to it; that Murphy was in its employ—its agent — and the consequent deduction must be that his possession was its possession. Even if this be too rigorous a construction of the contract of insurance against the •defendant, we cannot say, as a matter of law, that Murphy had the custody of the boat by the joint direction of the parties. At best it is a question of fact for the jury. Of course, if Murphy were in possession, either under the joint proprietorship of the parties or under a special agreement with the plaintiff to make repairs for him, this action would not lie, for the defendant could not then be required to exact surrender of the boat by Murphy.

We are, therefore, brought down to the narrow margin, was there -evidence sufficient for the jury to say that the extra work performed by Murphy was not authorized by the plaintiff ? If so, the •detention by Murphy and consequently by the defendant was without authority and this action is proper. If not, then defendant is not liable, for if plaintiff employed Murphy, of course the defendant cannot be made the whipping post for their troubles.

[8]*8When the boat was brought in for repairs the plaintiff claimed he was not well, and desiring to go to New York, by power of attorney, he authorized one Homer to act for him, “ in all matters pertaining to holding survey and repairing damage done to my canal boat George Murr in consequence of sinking in the Erie Canal on or about August 6, 1896, giving and granting unto my said attorney full power and authority to do and perform all and every act and thing whatsoever requisite and necessary to be done in and about the premises, as fully, to all intents and purposes, as I might or could do if personally present.” By this instrument the power vested in Homer was limited to the reparation of damages “ in consequence ”' of the accident, and hence, if he made any agreement with Murphy for extra work he transgressed his special authority. Again, the rottenness of the boat ivas not “ in consequence ” of the accident.. That was an intrinsic defect. To be sure, if the surveyors saw fit to require such defects to be repaired, the plaintiff could be charged therefor,' and Homer within the scojje of his agency could have-provided for them. The surveyors did not require them to be made, and the defendant did not let the contract to the lowest bidder. It assumed exclusive control, and turned the boat over to Murphy, its surveyor, to make the repairs and without consultation with or notice to the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenkins v. Equipment Center, Inc.
869 P.2d 1000 (Court of Appeals of Utah, 1994)
Deitch v. Kessler
13 Misc. 2d 421 (New York Supreme Court, 1958)
Kachurin v. American Iraq Shipping Co.
187 Misc. 178 (New York Supreme Court, 1946)
State v. Kelly
202 P. 524 (New Mexico Supreme Court, 1921)
Kindelberger v. Kunow
122 A.D. 158 (Appellate Division of the Supreme Court of New York, 1907)
Murr v. Western Assurance Co. of Toronto
68 N.Y.S. 1144 (Appellate Division of the Supreme Court of New York, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
50 A.D. 4, 64 N.Y.S. 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murr-v-western-assurance-co-nyappdiv-1900.