Murphy v. A.A. Beiro Construction Co.

679 A.2d 1039, 1996 D.C. App. LEXIS 125, 1996 WL 351208
CourtDistrict of Columbia Court of Appeals
DecidedJune 27, 1996
Docket93-AA-132
StatusPublished
Cited by5 cases

This text of 679 A.2d 1039 (Murphy v. A.A. Beiro Construction Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. A.A. Beiro Construction Co., 679 A.2d 1039, 1996 D.C. App. LEXIS 125, 1996 WL 351208 (D.C. 1996).

Opinions

PER CURIAM.

The District of Columbia seeks review of a decision of the Contract Appeals Board (the Board) awarding respondents, A.A. Beiro Construction Co., Inc. (Beiro) and its insurer, Fidelity and Deposit Insurance Company of Maryland (Fidelity), damages of $6,570,278 plus interest from April 17,1992. The award followed the Board’s entry of default against the District and an ex parte proof hearing at which the District was not permitted to call witnesses. The District argues that the Board abused its discretion in denying its request for a continuance of the hearing and entering a default judgment against it when its lead counsel resigned unexpectedly on the last working day before the hearing. We agree and reverse and remand for a new hearing.

I.

A. The Contract

In 1984, the District and Beiro entered into a contract for Beiro to construct an educational facility in the District. The total contract price was $8,098,000. The District issued Beiro a notice to proceed with the work on July 6, 1984, and the completion date was set for June 9, 1986. The contract had a standard provision for Terminations for Default and Terminations for Convenience. The District terminated the contract on July 31, 1989 for Beiro’s alleged default, ie., Beiro’s claimed failure to accept responsibility for defective workmanship and materials which resulted in major structural damage to the project. According to Beiro, there were serious design problems in plans for the project which ultimately necessitated a major redesign, and Beiro informed the District about them as early as February, 1985. The building was almost completed, and Beiro had been paid $5.3 million, according to the District.

Beiro contended that the District obtained the report of a consulting engineer, Carson Mok, who investigated and issued a report on January 14, 1986 (the Mok report) criticizing [1041]*1041the design and construction of the project. The District then issued a “rejection notice” to Beiro on February 28, 1986, rejecting the majority of the project’s concrete because of cracking. The District also issued an order directing Beiro to stop work on the project. On March 17,1986, Beiro sent a letter to the District pointing out design deficiencies, explaining that the concrete work had been performed pursuant to the plans and specifications, and requesting that the Stop Work Order be converted to a Suspension of Work for the Convenience of the District. As requested, the District issued a formal Suspension of Work Order pursuant to Article 26 of the contract on April 23,1986.

On July 14,1986, the District hired Meyer Associates (Meyer) to conduct a further investigation. Meyer submitted a final report on October 29,1986, concluding that the project had design deficiencies but no substantial contractor errors. The Meyer report further concluded that fifteen new columns were required because of design error and that the only work needed to correct the contractor’s error in the concrete slab was epoxy injection into concrete cracks. On December 5, 1986, the District instructed Beiro to submit a proposal for change-order work based on the Meyer report. Beiro submitted proposals on January 6, February 6, and February 26,1987.

On December 9, 1986, the District of Columbia School Board reevaluated the project and determined that an additional $3-4 million would be needed to complete the building. The District took the position that it would not complete the building unless the School Board provided the additional funds, and the School Board voted to relinquish the project to the District on May 20,1987.

On May 22, 1987, the District informed Beiro that work on the project would be suspended indefinitely and that it would discuss with Beiro its liability. On June 26, 1987, Beiro wrote to the District requesting payment and offering to inject epoxy into the concrete cracks at no cost to the District. Beiro again wrote the District on July 23, 1987 requesting payment and resumption of the work. Without responding, the District terminated Beiro’s contract for default, citing, among other reasons, the poor quality of the concrete construction and Beiro’s failure to apportion liability between itself and the project’s architect.

B. The Appeal Proceedings

On August 16, 1987, Beiro appealed the default termination to the District’s Department of Administrative Services (DAS), pursuant to the District of Columbia Procurement Practices Act of 1986 (DCPPA), D.C.Code § 1-1181.1, et seq. (1987). Beiro requested that the termination for default be changed to a termination for convenience. After a hearing, DAS issued a decision upholding the termination for default and awarding damages to the District in the amount of $89,427.23. Beiro and its insurer appealed to the Board. The District filed an answer and counter-claim seeking $8,089,000 in damages for breach of contract and negligence.

On July 14, 1990, the Board held a pre-hearing conference and set November 26, 1990 as the date for the hearing. The District filed motions for continuances on September 28 and December 17, 1990, for thirty days and sixty days respectively, both on the ground that counsel had resigned. The motions were granted and a new hearing date was set for September 18, 1991. On August 6,1991, the Board, sua sponte, continued the hearing date for ninety days because two Board members’ terms had expired. After a pre-hearing conference on November 18, 1991, the chief administrative judge (judge) issued an order the following day setting the following schedule: February 14, 1992, close of discovery; March 6, 1992, supplemental pre-hearing statements due; March 23-April 17, 1992, hearings. Beiro and Fidelity then filed motions on February 27, March 5, March 13, and March 17,1992. On March 6, 1992 they filed a supplemental pre-hearing statement. According to the District, Beiro’s motion for summary judgment was 587 pages, including exhibits. The motion filed on March 5, 1992 was to exclude from evidence testimony and test results of concrete cores which the District had discovered on January 31,1992.

[1042]*1042On March 12, 1992, the District filed a motion to extend to March 16 the time within which to respond to Beiro’s motion for summary judgment, which the judge granted. However, an order was entered shortening the time for the District to respond to motions filed on March 13 and 19. By an order entered on March 11, the District was ordered to file three copies of its exhibits, instead of multiple copies only of exhibits used for cross-examination. The District filed its opposition to the motion for summary judgment on March 19, its opposition to the motion to exclude or limit the testimony of its expert on March 19, and its opposition to the motion for default judgment or to limit or preclude evidence relating to the termination of the contract on March 20. The District filed a supplemental pre-hearing statement on March 19. On March 17,1992, the District moved for a two-week continuance of the hearing date, from March 23 to April 6, on the ground that it did not have sufficient time to prepare for the hearing, particularly given the numerous and lengthy motions to which it had to respond. This motion was denied on March 18,1992.

On March 20, 1992, the District’s lead counsel, an Assistant Corporation Counsel, (ACC) Eugene Austin, unexpectedly resigned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Recio v. District of Columbia Alcoholic Beverage Control Board
75 A.3d 134 (District of Columbia Court of Appeals, 2013)
King v. District of Columbia Water & Sewer Authority
803 A.2d 966 (District of Columbia Court of Appeals, 2002)
Murphy v. A.A. Beiro Construction Co.
679 A.2d 1039 (District of Columbia Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
679 A.2d 1039, 1996 D.C. App. LEXIS 125, 1996 WL 351208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-aa-beiro-construction-co-dc-1996.