Murphy Elevator Co., Inc. v. 11320 Chester L.L.C.

2018 Ohio 1362, 110 N.E.3d 787
CourtOhio Court of Appeals
DecidedApril 11, 2018
DocketNO. C–170251
StatusPublished
Cited by2 cases

This text of 2018 Ohio 1362 (Murphy Elevator Co., Inc. v. 11320 Chester L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy Elevator Co., Inc. v. 11320 Chester L.L.C., 2018 Ohio 1362, 110 N.E.3d 787 (Ohio Ct. App. 2018).

Opinion

Myers, Presiding Judge.

{¶ 1} Defendant-appellant 11320 Chester LLC ("Chester") has appealed from the trial court's entry granting judgment in the amount of $13,626.14 to plaintiff-appellee The Murphy Elevator Company ("Murphy") on Murphy's claim for breach of contract.

{¶ 2} Because the trial court used the wrong measure of damages when calculating the damages owed to Murphy for the remaining months under the second year of the parties' three-year contract, we reverse that portion of the trial court's judgment. The judgment of the trial court is otherwise affirmed.

Factual and Procedural Background

{¶ 3} Chester and Murphy entered into a contract for Murphy to perform maintenance services on certain elevators located in a hotel and waterpark owned by Chester. The contract commenced on August 1, 2014, and provided that it would continue for a period of three years.

{¶ 4} Chester was required to pay Murphy $4,000 per quarter for the first year of the contract. However, if Chester paid for an entire contract year up front, it was only required to pay $15,000 for the year. With respect to the price owed by Chester for the second and third years of the contract, the contract provided that the price "is subject to adjustment at the end of each year in which this agreement is in force. The following formula for adjustment will be used: not more than 3% of the current price."

{¶ 5} The contract specified the exact services covered and stated that "[n]o work, service or liability, on the part of The Murphy Elevator Company other than that specifically mentioned herein is included or intended as a part of the contract." The contract further listed the hours and days during which services would be performed, and it provided that Chester would incur an additional charge for covered work performed outside of the specified days and times.

{¶ 6} Chester paid $15,000 up front for the first year of the contract. On July 1, 2015, Murphy submitted an invoice for the second year of the contract in the amount of $16,371. This amount was a three-percent increase to the price paid during the first year of the contract, plus sales tax. During the first and second years of the contract, Murphy submitted additional invoices to Chester for work performed that was outside the scope of the contract and for work covered under the contract that was performed outside of the contractually provided days and times.

{¶ 7} After paying for the first year of the contract up front, Chester made only two additional payments to Murphy. It made a payment of $168.13, which corresponded to an invoice for work that had been performed on a day or time not covered under the contract. And it made an additional payment of $8,500 on September 17, 2015.

{¶ 8} In June of 2016, Murphy sued Chester for breach of contract for Chester's failure to pay the submitted invoices. Murphy sought approximately $22,126 in damages.

{¶ 9} During a bench trial, Murphy's Vice President of Administration Travis Carlisle testified regarding the unpaid invoices that Murphy had submitted to Chester. He explained that with respect to work that Murphy had performed that was not covered under the contract, Murphy billed Chester the rate it would charge for a technician's regular time, holiday time, or overtime, depending on when the work was performed. And for work covered under the contract but performed outside of the contractually provided days and times, Carlisle stated that Murphy billed Chester the difference between a technician's regular and overtime rates, as was provided for in the parties' contract.

{¶ 10} Carlisle explained the circumstances surrounding each invoice that had been submitted, including whether the work had been covered under the contract. He conceded on cross-examination that Chester's payment of $8,500 should be applied to the amount invoiced for the second year of the contract.

{¶ 11} Carlisle testified that Murphy had stopped performing under the contract in March of 2016 because of Chester's nonpayment. He additionally explained that Murphy generally receives a 33 percent profit margin on this type of service contract.

{¶ 12} Vijaya Kumar Vemulapalli testified on behalf of Chester that neither he nor anyone else had requested that Murphy perform any services on weekends or during premium, noncovered time. He explained that prior to signing the contract with Murphy, he informed the company that he did not want to pay for services performed on the weekend. Vemulapalli testified that Murphy had told him that despite their standard contract language excluding weekends from coverage, it would not charge him for weekend service calls.

{¶ 13} The trial court found that the parties' contract covered only the days and times specified in the contract and that Murphy's submitted invoices were valid. It voided the third year of the contract as a matter of equity, and it awarded Murphy $22,126.14 in damages.

{¶ 14} Chester filed a motion for reconsideration. It argued that the trial court should have credited its payment of $8,500 towards the amount billed for the second year of the parties' contract, that the trial court should not have charged Chester premium rates for services performed outside the contract, and that Chester should not have been required to pay for the second half of the second year of the contract.

{¶ 15} The trial court issued a modified judgment crediting Chester for the $8,500 payment and awarding Murphy $13,626.14 in damages.

Billing Rates

{¶ 16} In its first assignment of error, Chester argues that the trial court erred in failing to enforce the clear and unambiguous terms of the contract to services performed outside the scope of the contract.

{¶ 17} Where a contract's terms are clear and unambiguous, interpretation of the contract is a matter of law. Ruehl v. Air/Pro, Inc. , 1st Dist. Hamilton Nos. C-040339 and C-040350, 2005-Ohio-1184 , 2005 WL 627789 , ¶ 4. In such instances, this court conducts a de novo review. Id. But where the terms of a contract are ambiguous, "the meaning of the words in the contract becomes a question of fact, and the trial court's interpretation will not be overturned on appeal absent a showing that the court abused its discretion." Kelly Dewatering and Constr. Co. v. R.E. Holland Excavating, Inc., 1st Dist. Hamilton No. C-030019, 2003-Ohio-5670 , 2003 WL 22415591 , ¶ 21. A contract will be considered ambiguous where "its terms cannot be clearly determined from a reading of the entire contract or if its terms are susceptible to more than one reasonable interpretation." Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Hodory v. Duke Realty Corp.
2025 Ohio 5068 (Ohio Court of Appeals, 2025)
DATFT, L.L.C. v. AM Reflections Cleaning Servs. L.L.C.
2023 Ohio 1348 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 1362, 110 N.E.3d 787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-elevator-co-inc-v-11320-chester-llc-ohioctapp-2018.