Kelly Dewatering Const. v. R.E. Holland, Unpublished Decision (10-24-2003)

2003 Ohio 5670
CourtOhio Court of Appeals
DecidedOctober 24, 2003
DocketAppeal No. C-030019, Trial No. A-0106063.
StatusUnpublished
Cited by4 cases

This text of 2003 Ohio 5670 (Kelly Dewatering Const. v. R.E. Holland, Unpublished Decision (10-24-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelly Dewatering Const. v. R.E. Holland, Unpublished Decision (10-24-2003), 2003 Ohio 5670 (Ohio Ct. App. 2003).

Opinion

DECISION.
This case has been sua sponte removed from the accelerated calendar. {¶ 1} Plaintiff-appellee Kelly Dewatering Construction Co. ("Kelly") filed a complaint against defendant-appellant R.E. Holland Excavating Co. ("Holland") for breach of contract, quantum meruit, and unjust enrichment. In its complaint, Kelly asserted, among other things, that it was entitled to the $43,194.60 bond issued by defendant Ohio Farmers Insurance Co. (Holland's surety) and held in escrow by defendant-appellees the city of Cincinnati and the Hamilton County Board of Commissioners.

{¶ 2} A bench trial was conducted on July 23, 2002. Following the trial, the court entered judgment in favor of Kelly and against Holland and Ohio Farmers Insurance in the amount of $47,743.14, plus costs and interest. The court also ordered the city of Cincinnati and the Hamilton County Board of Commissioners to release the bond funds to Kelly.

{¶ 3} Holland has appealed, raising two assignments of error. In the first assignment of error, Holland maintains that the trial court erred in interpreting its contract with Kelly. In the second assignment of error, Holland contends that the trial court erred in finding that Kelly had proved its damages. We find neither assignment to be well taken.

{¶ 4} The relevant facts are as follows. Holland is an excavation contractor that installs sanitary sewer lines and systems. Kelly installs deep-well dewatering systems that lower the water table using high-capacity pumps so that work can be performed in excavated areas. Holland was awarded a contract by the Metropolitan Sewer District to install a sewer line for the Springdale/Sharonville Sewage Project. The water level in the area needed to be reduced before the sewer line could be installed. In November 1999, Kelly submitted an offer to Holland for the services and equipment necessary to lower the water level. On February 14, 2000, Holland responded by issuing a purchase-order contract to Kelly outlining the terms and conditions under which it would do business with Kelly. Kelly's original bid was attached to and incorporated into the contract. Kelly accepted the purchase order.

{¶ 5} The purchase-order contract specified that, for a base price of $66,450 (there was a $225-per-day charge for additional pumping), Kelly's work for Holland would include the following:

{¶ 6} "1. Drill and install necessary deep wells.

{¶ 7} "2. Furnish and install necessary well screens.

{¶ 8} "3. Furnish and install 15 submersible pumps and risers.

{¶ 9} "4. Furnish and install necessary discharge hose to connect wells to Mill Creek.

{¶ 10} "5. Furnish 3,300 of overhead power line.

{¶ 11} "6. Provide standby pump and exchange of pumps that may become inoperative.

{¶ 12} "7. Supervision of installation of partial system.

{¶ 13} "8. Development of testing of system.

{¶ 14} "9. Freight of equipment to and from jobsite.

{¶ 15} "10. We are providing insurance coverage for general liability and automobile coverage in the amount of one million dollars per occurrence. We have a two million-dollar umbrella for increased limits of coverage.

{¶ 16} "11. No builders' risk policy coverage is provided."

{¶ 17} The contract further provided that Holland was to be "responsible for damage, theft, or loss of [Kelly] equipment from jobsite," and that the charges for equipment usage would terminate "at the time the equipment is available to be loaded on [Kelly] trucks."

{¶ 18} Kelly delivered the specified equipment to Holland and installed pumps at the excavation site around the end of April 2000. According to Lester Ehorn, the project manager for Kelly, his team tested the dewatering system without turning it on. The system was then activated by Holland on May 11, 2000, and remained on for five days. On May 18, 2000, the Kelly crew left the excavation site. The pumps were activated again on May 25, 2000, and ran for five days until May 30, 2000. Due to a delay caused by problems arising from Holland's choice of where to excavate, the pumps were not turned on again until July 24, 2000, and they ran continuously until February 12, 2001. According to Holland's superintendent, James Coate, all of Kelly's equipment was not ready to be picked up until April 2, 2001. And both parties agreed that it was, in fact, picked up on that date.

{¶ 19} Kelly invoiced Holland for the specified contract price of $66,450, and for five additional months of usage at $225 per day. The additional charges amounted to $31,050. Ehorn testified at trial that, due to an error in computing the day the equipment had been returned, seven days should have been credited to Holland, which reduced the charges to $29,475. Kelly also charged a retainage fee of $7218.60 and an additional fee of $4926 for damage to several of its fifteen-horsepower motors. Upon receiving all the invoices, Holland paid $68,231.40, but refused to pay the additional charges of $41,619.90 for the additional five months of usage, the retainage fee, and damages.

{¶ 20} In its first assignment of error, Holland maintains that the trial court improperly interpreted the contract because the contract was unambiguous. We note that Holland initially argued below that the contract was ambiguous and asked the court to "interpret certain provisions of [the] contract" at trial. Holland now contends that the contract was not ambiguous. Despite Holland's inconsistent arguments, we must review whether the terms of the purchase-order contract were ambiguous or whether they should have been enforced as a matter of law.

{¶ 21} Where a contract is clear and unambiguous, its interpretation is a matter of law.1 In such a case, the standard of review is de novo.2 But where a contract is ambiguous, the meaning of the words in the contract becomes a question of fact, and the trial court's interpretation will not be overturned on appeal absent a showing that the court abused its discretion.3 A contract is ambiguous if its terms cannot be clearly determined from a reading of the entire contract or if its terms are susceptible to more than one reasonable interpretation.4

{¶ 22} In this case, Holland maintains that it only used the pumps for seven months, from July 24, 2000, to February 12, 2001, and that, as a result, it should only have been charged for one month of additional pumping services. Holland contends that it should not have been charged when the pumps were being tested in May 2000, or when the pumps were unused in June and part of July 2000, and in March and April 2001. Conversely, Kelly justifies charging Holland for an additional five months of usage because the contract was for goods and services.

{¶ 23} The term at issue in this case is "pumping." The purchase order, which was written by Holland, provided that Kelly would install a deep-well dewatering system.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Longnecker v. Velontra Inc.
2025 Ohio 5072 (Ohio Court of Appeals, 2025)
Murphy Elevator Co., Inc. v. 11320 Chester L.L.C.
2018 Ohio 1362 (Ohio Court of Appeals, 2018)
Ruehl v. air/pro, Inc., Unpublished Decision (3-18-2005)
2005 Ohio 1184 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Ohio 5670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-dewatering-const-v-re-holland-unpublished-decision-10-24-2003-ohioctapp-2003.