Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (TV2)

CourtDistrict Court, E.D. Tennessee
DecidedSeptember 22, 2022
Docket3:15-cv-00547
StatusUnknown

This text of Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (TV2) (Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (TV2)) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (TV2), (E.D. Tenn. 2022).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF TENNESSEE

MUNSON HARDISTY, LLC, ) ) Plaintiff, ) ) v. ) No.: 3:15-CV-547-TAV-DCP ) LEGACY POINTE APARTMENTS, LLC, ) ) Defendant. )

MEMORANDUM OPINION AND ORDER

This civil action is before the Court on Defendant’s Motion to Dismiss Under Rule 12(b)(7) for Failure to Join an Indispensable Party [Doc. 211]. Defendant seeks dismissal of this action under Federal Rule of Civil Procedure 12(b)(7), for failure to join a party under Rule 19 [Id.]. Plaintiff responded to this motion [Doc. 220], and defendant replied [Doc. 226]. Defendant’s motion is therefore fully briefed and ready for disposition. See E.D. Tenn. L.R. 7.1(a), 7.2. For the reasons explained below, defendant’s motion will be denied. I. Background Plaintiff Munson Hardisty, LLC (“Plaintiff”) brought this action against defendant Legacy Pointe Apartments, LLC (“Defendant”) for the following claims: (1) discrimination and retaliation action under the False Claims Act, 31 U.S.C. § 3730(h); (2) breach of contract; (3) quantum meruit; (4) unjust enrichment; (5) violation of the Prompt Pay Act of 1991, Tenn. Code Ann. §§ 66-34-101 et seq.; (6) constructive trust; (7) lien lis pendens; and (8) violation of the Racketeer Influenced and Corrupt Organizations Act (“RICO”), 18 U.S.C. § 1962(c) [Doc. 86, pp. 17–27]. The dispute between the parties relates to a project to construct an apartment complex located in Knoxville, Tennessee (the “Project”) [Id. at 1–2]. Defendant was formed for the purpose

of constructing the Project and operating the apartment complex after the Project’s completion [Id.]. The Project was funded through a loan offered and insured by the Department of Housing and Urban Development (“HUD”) [Id. at 2]. Defendant hired plaintiff as the general contractor on the Project [Id.]. Plaintiff and defendant entered into a contract governing the construction of the Project on September 13, 2007 (“Construction

Contract”) [Id. at 6]. According to the Construction Contract, defendant agreed to pay plaintiff the actual cost of construction and a fee of the Builder’s and Sponsor’s Profit and Risk Allowance (“BSPRA”), not to exceed $18,047,049 [Id.]. During the Project, defendant modified the work plaintiff was required to complete under the Construction Project (“Modifications”) [Id. at 7]. Plaintiff alleges that defendant

did not submit the Modifications to HUD or the Project’s lender for approval, even though any changes to the work were required to be approved in writing by the Lender and the HUD Commissioner [Id.]. The Modifications required significant extra work from plaintiff [Id.]. As a result, completing the Project caused plaintiff to incur costs and debts exceeding the maximum amount defendant agreed to pay under the Construction Contract [Id.].

These additional costs and debts amounted to roughly $2,120,538 (“Claims for Extra Work”) [Id.]. Plaintiff alleges it owed the Claims for Extra Work to certain subcontractors, vendors, and suppliers that performed work on the Project (“Subcontractors”) [Id.]. 2 In early 2009, defendant’s manager and majority member, Harold Moore (“Moore”), promised John Hardisty (“Hardisty”) that State Insulation, LLC, a limited liability company in which Moore was a member, would pay the Claims for Extra Work to

the Subcontractors in return for plaintiff waiving its right to receive payment for amounts owed under the Construction Contract (the “Incentive Agreement”) [Doc. 86, p. 2; Doc. 125-2, p. 11; Doc. 191, p. 3]. However, plaintiff alleges that defendant and State Insulation entered into an agreement to appropriate for themselves the amounts plaintiff alleges it is owed under the Construction Contract [Doc. 86, pp. 25–26]. State Insulation

purchased assignments of the Subcontractor’s claims for payment for the Claims for Extra Work [Id. at 9]. State Insulation then continued to hold these assignments [Id. at 3]. After State Insulation took assignment of the Subcontractors’ claims, defendant represented to HUD that there were no outstanding liabilities to the Subcontractors [Id.]. When the Project’s permanent financing closed in August 2009, defendant certified to

HUD that all claims relating to the Project had been or would be paid within 45 days and that no debts were outstanding to plaintiff for work on the Project [Id. at 9]. In late 2012, defendant obtained refinancing through HUD [Id. at 12]. In obtaining this refinancing, defendant again certified that all claims resulting from the construction of the Project had been paid and that nothing was owed to plaintiff [Id. at 12–13]. Plaintiff, as a member of

defendant, refused to consent to the refinancing [Id. at 14]. In October 2009, State Insulation filed a claim in the Knox County Chancery Court (“Bond Claim Action”) against Great American Insurance Company (“GAIC”), which was 3 the surety of the bonds associated with the Project [Id. at 11]. State Insulation asserted that plaintiff failed to pay the Claims for Extra Work [Id.]. In June 2012, State Insulation and GAIC dismissed the Bond Claim Action without prejudice [Id. at 12].

In September 2011, GAIC filed a complaint for interpleader in the Knox County Chancery Court seeking to deposit with the court funds in the amount of approximately $750,000, which GAIC held as security for the payment and performance bonds (“Interpleader Action”) [Id. at 11]. On December 20, 2011, defendant and State Insulation filed a counterclaim against GAIC and a crossclaim against plaintiff [Id.]. Defendant and

State Insulation asserted that State Insulation was entitled to the deposited funds, plus interest [Id.]. On January 17, 2014, defendant and State Insulation filed an amended counterclaim and crossclaim in the Interpleader Action, alleging that plaintiff failed to pay the Claims for Extra Work [Id. at 16]. Additionally, on September 3, 2015, defendant filed an action in the Knox County Circuit Court to divest plaintiff of its membership interest in

defendant, which plaintiff obtained under the Construction Contract (“Divestment Action”) [Id. at 15]. Plaintiff filed this suit on December 10, 2015 [Doc. 1]. Defendant subsequently filed, inter alia, unsuccessful motions to transfer this case to the Southern District of California [Docs. 91, 106], for judgment on the pleadings [Docs. 109, 117], and summary

judgment [Docs. 125, 164]. After those motions were denied, the parties proceeded to trial. Almost three weeks before trial was scheduled to occur, defendant filed the instant motion [Doc. 211]. Plaintiff responded [Doc. 220], and defendant replied [Doc. 226]. 4 The Court notes that defendant has chosen to file this dispositive motion well after the deadline imposed by the scheduling order [Doc. 41, p. 6]. However, the Court recognizes that that this type of motion can be raised at trial pursuant to the Federal Rules

of Civil Procedure. Fed. R. Civ. P. 12(h)(2)(C). Therefore, the Court will now consider the merits of defendant’s motion. II. Standard of Review A motion to dismiss for failure to join a party under Rule 19 is brought pursuant to Rule 12(b)(7). Fed. R. Civ. P. 12(b)(7). Rule 19(a)(1) provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (TV2), Counsel Stack Legal Research, https://law.counselstack.com/opinion/munson-hardisty-llc-v-legacy-pointe-apartments-llc-tv2-tned-2022.