Munn v. Thornton

956 P.2d 1213, 1998 Alas. LEXIS 75, 1998 WL 176722
CourtAlaska Supreme Court
DecidedApril 17, 1998
DocketS-7574
StatusPublished
Cited by13 cases

This text of 956 P.2d 1213 (Munn v. Thornton) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Munn v. Thornton, 956 P.2d 1213, 1998 Alas. LEXIS 75, 1998 WL 176722 (Ala. 1998).

Opinion

OPINION

FABE, Justice.

I. INTRODUCTION

Jonathan Thornton, a general contractor, entered into an oral contract to build a house for Steve and Jeannie Munn. Thornton maintains that he agreed to build the house for the cost of time and materials plus 15 percent with no cap on the total cost. The Munns contend that their agreement included a cap on total cost for the house. The cost escalated above this alleged cap, and the Munns refused to pay the outstanding balance. Thornton filed a complaint against the Munns. After a trial, the superior court ruled in Thornton’s favor, finding that he was entitled to recovery under an oral contract or under the doctrines of unjust enrichment and promissory estoppel. The trial court also found that Thornton did not breach his duties under the contract, that he had a paramount lien on the Munns’ house, and that the Alaska Unfair Trade Practices Act did not apply to this litigation. We affirm.

II. FACTS AND PROCEEDINGS

After a fire damaged a house owned by the Munns, they solicited bids to replace it. Thornton submitted an estimate of $149,800 to rebuild the 1200-square-foot house. Steve Munn then gave Thornton a modified set of plans for a 2316-square-foot house with a 372-square-foot deck. The Munns hired Thornton to drive steel pilings for the house’s foundation, agreeing orally to pay Thornton his cost for labor and materials plus 15 percent for this work. The Munns paid Thornton’s bill of $4,815.53 for the work, including $30 per hour straight time for labor.

Thornton submitted a new estimate of $169,620 to build the “new custom house as per plans,” including his work on the pilings. *1216 Thornton testified that he did not consider this to be a “firm estimate” because the plans were not complete. He also testified that Steve Munn responded that the bid was less than he had expected and that “he had another $50,000 to $80,000 to play with.”

The Munns and Thornton agree that Thornton offered two options for building the house. They also agree that the first option involved building it for the total price of $169,620 with written change orders to accommodate modifications at either a negotiated price or on a time and materials basis. They disagree, however, about the terms of the second option, under which they eventually proceeded. Specifically, they dispute whether the second option included a cap on cost, and whether labor was to be billed at a flat rate. Although Steve Munn conceded that Thornton “didn’t say in those specific words there’s a cap of [$]169,620,” Munn testified that, under the second option, Thornton offered to build the house for the cost of time and materials plus 15 percent, subject to a cap of $169,620. He believed that the contract was subject to this cap because Thornton told him “that the [$]169,-620 was a very good number, he was very comfortable with it, he had a very good crew, and he could build the house for less than that.” According to Steve Munn, Thornton made this alternative offer because Steye Munn planned to be away from the site during much of the building, and he and Thornton believed that this alternative would avoid the need for Jeannie Munn to “deal with change orders.” Finally, Steve Munn testified that he understood that Thornton’s actual cost for labor was generally $30 per hour.

In contrast, Thornton testified that under the second option he offered to build the house for the cost of time and materials plus 15 percent. Thornton testified that he explained that he would provide the Munns with a statement of his expenses and copies of invoices for materials or subcontractors at the end of each month. He also testified that he informed the Munns that he would bill carpenters at $30 per hour. Thornton and the Munns agree that Thornton said he would prepare a written contract, but never did.

On October 18, 1993, Steve Munn called Thornton and told him to begin construction on the house. Thornton began construction and sent detailed bills in November, December, January, and February. The bills itemized labor costs for each employee, generally billed at $30 per hour straight time and $45 overtime. The bills also included itemized costs for materials and subcontractors, and additional charges for “15% Profit” on these subtotals. The Munns paid these first four bills, totaling (along with the bill for the pile driving) $173,440.72. Steve Munn testified that he believed that this amount was within the cap, considering the extra $10,000 cost of an entertainment center he had instructed Thornton to build.

In January 1994 a loan officer with the Munns’ bank called Thornton and asked him to estimate how much it would cost to complete the house. Thornton guessed that it would cost $20,000 over the original estimate of $169,620. Later in February, Thornton estimated in a conversation with Munn that it would cost an additional $47,000. 1 Finally, Thornton testified that Munn came to his office after the February billing:

Well, Mr. Munn came in my office and his first comment was “how bad is it”, and we sat down and we began discussing and I told him that right now we were at, I believe, $173,440, something like that. And I told him to the best I could come up with, that it was gonna take another [$]77,-400 to finish. And he stated that, oh, that was more than he expected, but he loved the house, if he were to do it again he wouldn’t change a thing, the quality was great, and — and then we went on to discuss the entertainment center in more detail of what he was wanting. And then about the money, he said that he’d used up all of his insurance proceeds, and that he was arranging some type of a note at the bank. He said that he couldn’t close on that, and that his funds would be available when the house was done, so he wanted to *1217 know if I could give him one final bill. And at that point I was thinking, well, we’re about 45 days or so from completion, I bill about every 30 days, I’d just be holding — holding the final bill for another 15 days. I told him I didn’t think that’d be a problem. He told me that if I needed to get interim financing to go ahead and do that and bill him for the interest and the fees associated with that, and — And he said that I could check with [his loan officer] if I needed to inquire about the funds.

Steve Munn agreed that he told Thornton that he was planning to obtain additional financing to complete the house and requested that all remaining charges be combined in one final bill. Steve Munn also acknowledged that he did not protest any of Thornton’s bills, explaining that if the cost of the entertainment center and other items Munn had supplied were subtracted, the total amount he would owe Thornton would still be close to $170,000. 2 Finally, he testified that he received a loan.

Thornton borrowed $85,000 in order to continue work on the house and finished it in early May. The Munns refused to pay the outstanding amount of $109,503.28 claimed by Thornton.

Thornton initiated a civil action based on claims of breach of contract, foreclosure of his mechanics lien, unjust enrichment, misrepresentation and equitable estoppel. The Munns moved for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gavora, Inc. v. City of Fairbanks
502 P.3d 410 (Alaska Supreme Court, 2021)
Williams v. Baker
446 P.3d 336 (Alaska Supreme Court, 2019)
State v. Ranstead
421 P.3d 15 (Alaska Supreme Court, 2018)
Christopher McIntyre v. Bp Exploration and Production
697 F. App'x 546 (Ninth Circuit, 2017)
Bingman v. City of Dillingham
376 P.3d 1245 (Alaska Supreme Court, 2016)
Chilkoot Lumber Co. v. Rainbow Glacier Seafoods, Inc.
252 P.3d 1011 (Alaska Supreme Court, 2011)
Seybert v. Cominco Alaska Exploration
182 P.3d 1079 (Alaska Supreme Court, 2008)
Ware v. Ware
161 P.3d 1188 (Alaska Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
956 P.2d 1213, 1998 Alas. LEXIS 75, 1998 WL 176722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/munn-v-thornton-alaska-1998.