Munk v. Kanzler

58 N.E. 543, 26 Ind. App. 105, 1900 Ind. App. LEXIS 24
CourtIndiana Court of Appeals
DecidedNovember 16, 1900
DocketNo. 3,198
StatusPublished
Cited by3 cases

This text of 58 N.E. 543 (Munk v. Kanzler) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Munk v. Kanzler, 58 N.E. 543, 26 Ind. App. 105, 1900 Ind. App. LEXIS 24 (Ind. Ct. App. 1900).

Opinion

Comstock, J.

This action was to enforce a mechanic’s lien for a balance due for work performed and material [107]*107furnished in the construction of a certain building on the real estate described in the complaint. The complaint contained two paragraphs. It appears from the special findings of the court that judgment was rendered upon the second, which was based upon a written contract made a part of the complaint. Mo further reference, therefore, need be made to the first.

Appellant filed his amended answer to this paragraph, in which he sets up the following provision contained in the contract, to wit: “In consideration whereof the said party of the first part agrees to pay to the party of the second part, his heirs, administrators or assigns the sum of $6,850, which said sum is to be paid in instalments as the work progresses upon certificate of the said Mursinna & Metzner, which shall be given for seventy-five per cent, of the cost of the work done at the time of issuing the same, and the same shall be issued as the work progresses as follows, to wit: (1) When the foundation shall have been completed; (2) when the first story of said building is completed; (3) when the second story of said building is completed; (4) when the third story of said building is completed; (5) when the roof shall be on said building; (6) when said building shall be in all things completed, and the remaining twenty-five per cent, due to be paid at the acceptance of said building.” 1 This paragraph also set up the fallowing provision of the contract: “Should the owners at any time during the erection of the building desire to make any alterations, additions, or omissions from the original contract, they shall have a perfect right to do so, and the same shall not in any way affect or make void the contract, but shall be added to or deducted from the amount of the contract as the case may be. In case the owners and contractors cannot agree upon the value of any changes made or to be made, the same shall be appraised by Mursinna & Metzner, the architects.” It is further averred that the cause of action is for work done and ma[108]*108terial furnished by virtue of the last provision of the contract and was entirely for extra work don© and material furnished and was in addition to the original contract; that after the work was done and material furnished, a dispute arose between the parties as to the value of this extra work, and that appellant served notice on appellee that he would request Mursinna & hietzner to appraise- the extra work, material, etc., under the provision of the contract; that in pursuance of said request, the architects appraised the extra work, etc., at $1,217.78%, which sum appellant tendered to appellee; that appellee refused to accept the amount so tendered, and that thereupon appellant deposited the sum with the clerk of the court for the benefit of appellee as a complete performance upon his part of the contract, and that thereafter appellee accepted and still retains the same. The answer further sets up that at no time prior to the bringing of the suit did appellee obtain or request a certificate of the architects according to the provision of the contract.

The second paragraph of the answer sets up the same provision of the contract that refers to alterations, additions, etc., and the mode of ascertaining the value thereof by the architects; that all the work, etc., was performed under this contract, and that appellee arbitrarily fixed unreasonable prices for the extra work, etc., and that it was impossible for the parties to agree, and therefore, disagreeing, appellant requested the architects to ascertain the value; that the architects, upon such request, gave notice to appellant fixing the time and place for him to appear and submit such argument and evidence as he saw proper; that thereupon appellee appeared before the architects, submitted his evidence and argument, and thereafter the said architects fixed the value at $1,217.78%, and gave both parties notice thereof; that the said sum was tendered, the tender refused, the money deposited in court for appellee’s benefit; that the sum was subsequently accepted by him, which sum he still [109]*109retains. That no certificate for the amount sued for, or any part thereof, was made or requested. The third paragraph is a general denial. The fourth paragraph of answer addressed to the second paragraph of the complaint pleads certain omissions and changes in the construction of the building, amounting to $331.95, which is pleaded as a counterclaim filed with particulars of items.

The reply is in three paragraphs; the first is a general denial; the second pleads a waiver of appellant’s right to a certificate by the architects, as a condition precedent to the bringing of the action. The fact constituting the waiver is an alleged agreement between the parties to settle their difference without referring the same to the architects. The third paragraph sets up that a large portion of the services rendered by the appellee was not considered by the architects in making up the final account between the parties, and that the architects refused to make the estimate based upon the services actually rendered under the contract by appellee.

Upon the request of the parties, the court made a special finding of facts, stated its conclusions of law thereon, and rendered judgment thereon in favor of appellee for $236.64. The errors assigned are: (1) That the court erred in its conclusions of law on the findings and each of them; (2) the court erred in rendering judgment for appellee upon the findings.

It is urged upon behalf of the appellant (1) that “the contract requiring the architects to ascertain and fix by certificate or otherwise the amount of each payment is a condition precedent to appellee’s right to sue. (2) Whether appellant had the legal right to compel appellee to submit the questions to the architects, or not, he did so. He was heard by them as fully as desired, accepted the amount found by them, and is thereby estopped'. (3) Independently of all these questions, appellee accepted the conditional tender made by appellant in full settlement of his demand.”

[110]*110As to the first' proposition, we think it sufficient to say that while the decisions of the courts are not in harmony, yet from the weight of them the rule may fairly be deduced that if the contract provides that no action shall be maintained upon it until after an award by arbitrators, then the award becomes a condition precedent to the right of action. When no such condition is expressed in the contract, or can not be necessarily implied from' its terms, the provision for submitting the amount to arbitration is collateral and independent ; that while a breach of such conditions will support a separate action, it can not be pleaded in bar to an action on the principal contract. Supreme Council, etc., v. Forsinger, 125 Ind. 52, 9 L. R. A. 501, 21 Am. St. 196; Manchester Fire, etc., Co. v. Koerner, 13 Ind. App. 372, 55 Am. St. 231, and authorities therein cited. Also, Hamilton v. Home Ins. Co., 137 U. S. 370, 11 Sup. Ct. 133, 34 L. Ed. 708.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vachier v. McCormick, Alcaide & Co.
86 P.R. 677 (Supreme Court of Puerto Rico, 1962)
Vachier v. McCormick
86 P.R. Dec. 714 (Supreme Court of Puerto Rico, 1962)
Maitland v. Reed
77 N.E. 290 (Indiana Court of Appeals, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
58 N.E. 543, 26 Ind. App. 105, 1900 Ind. App. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/munk-v-kanzler-indctapp-1900.