Municipal Energy Agency of Nebraska v. FERC

CourtCourt of Appeals for the D.C. Circuit
DecidedJune 9, 2026
Docket25-1086
StatusUnpublished

This text of Municipal Energy Agency of Nebraska v. FERC (Municipal Energy Agency of Nebraska v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipal Energy Agency of Nebraska v. FERC, (D.C. Cir. 2026).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 25-1086 September Term, 2025 FILED ON: JUNE 9, 2026

MUNICIPAL ENERGY AGENCY OF NEBRASKA, ET AL., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

XCEL ENERGY SERVICES INC., INTERVENOR

Consolidated with 25-1111

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

Before: SRINIVASAN, Chief Judge, GARCIA, Circuit Judge, and EDWARDS, Senior Circuit Judge.

JUDGMENT

This cause was considered on the record, the briefs of the parties, and oral argument held on January 13, 2026. The court has given the issues full consideration and has determined that they do not warrant a published opinion. See D.C. Cir. R. 36(d). For the reasons stated below, it is

ORDERED and ADJUDGED that the petitions for review be DISMISSED in part and DENIED in part.

***

The Municipal Energy Agency of Nebraska, a not-for-profit wholesale electricity supply organization that provides power and energy-related services to dozens of participating municipal communities in Colorado, Iowa, Nebraska, and Wyoming, and three Colorado cities – Aspen, Glenwood Springs, and Center (“the Colorado Cities”) – are customers of the Public Service Company of Colorado (“Public Service”), an electric utility. The Colorado Cities object to Public Service’s decision to raise rates to fund a new infrastructure project, the “Power Pathway,” from which the Colorado Cities assert they will reap no benefits. The Federal Energy Regulatory Commission (“FERC”) denied the Colorado Cities’ complaint challenging the increased rate. The Colorado Cities then filed petitions for review with the court. The Colorado Cities argue that FERC’s decision was arbitrary and capricious because the agency failed to make two findings that were necessary to support its orders in favor of Public Service. We disagree. First, the court lacks jurisdiction to evaluate whether FERC made the first finding because the Colorado Cities failed to raise this issue in their petition for rehearing before the agency. Second, the Colorado Cities’ claim as to the second finding is at odds with the record, so the claim offers no basis to support the petitions for review.

I. BACKGROUND

The Federal Power Act requires that electric utilities set rates that are “just and reasonable.” 16 U.S.C. § 824d(a). The “just and reasonable” standard includes a “cost-causation principle” pursuant to which “[a]ll approved rates must ‘reflect to some degree the costs actually caused by the customer who must pay them.’” City of Lincoln v. FERC, 89 F.4th 926, 930 (D.C. Cir. 2024) (citation omitted). When utilities raise rates to fund system improvements, it is “just and reasonable” to allocate the cost of improvements among all network customers, regardless of how directly they benefit from the improvement, so long as the system is an integrated network. This is called “rolled-in” rate treatment. See, e.g., Algonquin Gas Transmission Co., 47 FERC ¶ 61,048, 61,154 (1989) (“[The] Commission . . . ha[s] followed a long-standing policy of rolling in costs where a system operates on an integrated basis to the benefit of all its customers.”). However, rolled-in rate treatment may not be appropriate when certain “special circumstances exist,” for example when lines are built in “remote areas that serve limited customers,” where transmission facilities could not “transmit power on a system-wide basis,” or for “customer-specific distribution facilities.” Buckeye Power, Inc. v. Am. Transmission Sys., 148 FERC ¶ 61,174, 61,968-69 (2014). The party challenging the rate has the “burden of showing that the existing rate is unjust or unreasonable.” Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022) (citing 16 U.S.C. § 824e(b)).

The dispute in this case concerns whether rolled-in rate treatment is appropriate to fund Public Service’s $1.7 billion Power Pathway project. The Power Pathway is a new transmission system designed to integrate renewable energy resources. Public Service announced that, to pay for the Power Pathway, it would raise rates charged to customers, including the Colorado Cities.

The Colorado Cities contested the rate increase in a complaint filed with FERC. They argued that it was “unjust and unreasonable” for Public Service to require them to help fund the Power Pathway because they would not have “direct connections” to the Power Pathway and “ha[d] already transitioned to renewable resources.” J.A. 425, 429-30 (citation omitted). The Colorado Cities further alleged that the proposed rate increase was unfair because “multiple other

2 beneficiaries . . . [we]re not allocated costs.” J.A. 428. FERC denied the complaint. FERC found that “[Public Service’s] transmission system operates as an integrated network,” and the “Power Pathway will become part of that network.” J.A. 445. Thus, FERC explained that, “[g]iven a finding that the system operates as an integrated whole, transmission costs have generally been rolled-in, absent a finding of special circumstances.” Id. (citation omitted). FERC acknowledged that the Colorado Cities believed special circumstances should exempt them from rolled-in rate treatment, but FERC concluded that there were no special circumstances in play in this situation.

The Colorado Cities timely petitioned for rehearing. They argued that FERC’s rejection of their alleged special circumstances was arbitrary and capricious. FERC denied the petition for rehearing. It explained that the petition for rehearing “essentially repeat[ed] contentions in the[] Complaint,” which FERC “addressed in the [initial] Order.” J.A. 492. The Colorado Cities now petition for review by this court, asserting, first, that FERC did not find that Public Service operated as an integrated system, and second, that FERC did not find whether special circumstances existed.

II. ANALYSIS

A.

We dismiss the Colorado Cities’ first challenge to FERC’s orders – namely, that FERC failed to make a required finding that the Power Pathway is part of an integrated system – because this challenge was never properly raised with FERC in the first instance.

Under 16 U.S.C. § 825l(b), “[n]o objection to the order of [FERC] shall be considered by the [reviewing] court unless such objection shall have been urged before [FERC] in the application for rehearing unless there is reasonable ground for failure so to do.” So “parties seeking judicial review of [FERC’s] orders under the Federal Power Act must ‘first petition for rehearing of those orders and must themselves raise in that petition all of the objections urged on appeal.’” Ameren Servs. Co. v. FERC, 893 F.3d 786, 793 (D.C. Cir. 2018) (citation omitted). Arguments must be raised “with ‘specificity’” and “may not be preserved either ‘indirectly’ or ‘implicitly.’” Id. (citations omitted). This requirement “is jurisdictional,” and “we have no discretion to disregard it.” Entergy Ark., LLC v. FERC, 109 F.4th 583, 590 (D.C. Cir. 2024) (citation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coalition of MISO Transmission v. FERC
45 F.4th 1004 (D.C. Circuit, 2022)
City of Lincoln v. FERC
89 F.4th 926 (D.C. Circuit, 2024)
Entergy Arkansas, LLC v. FERC
109 F.4th 583 (D.C. Circuit, 2024)
Pacific Gas and Electric Company v. FERC
113 F.4th 943 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Municipal Energy Agency of Nebraska v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipal-energy-agency-of-nebraska-v-ferc-cadc-2026.