Mundy v. Stevens

61 F. 77, 9 C.C.A. 366, 1894 U.S. App. LEXIS 2160
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 23, 1894
DocketNo. 15
StatusPublished
Cited by5 cases

This text of 61 F. 77 (Mundy v. Stevens) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mundy v. Stevens, 61 F. 77, 9 C.C.A. 366, 1894 U.S. App. LEXIS 2160 (3d Cir. 1894).

Opinion

ACHESON, Circuit Judge.

In treating this case, we will consider, first, the seventh assignment of error, which is based upon the following exception, namely:

[82]*82“Counsel for defendants except to so much of the charge as states that the verdict should be for the plaintiff unless the jury find that the defendants believed, on August 16, that the plaintiff would not finish the work by January 1.”

This was the only exception to the charge, which wás very full,— covering every branch of the case. The exception, it will be perceived, does not quote any part of the charge, but goes only to the supposed general effect thereof iff the one particular mentioned. It rests upon the following clause of the agreement of February 2,1892, between Stevens (party of the first part) and Mundy & Co. (parties of the second part):

“(9) In case the party of the first part shall fail to perform this contract, so as to endanger the forfeiture of the contract with the war department, the parties of the second part shall have the right to proceed to the completion of the work, in order to keep good their above-mentioned contract with the war department.”

The defendants below (the plaintiffs in error) did not ask the court to give the jury any special instructions with reference to this provision of the contract or its bearing upon the pending controversy. So far as the record shows, they did not present their views upon that subject to the court otherwise than by the brief and ■vague exception above quoted. Here, as the case is presented in the printed argument, two points are made, namely:

“(1) The real question was, had Stevens, August 16, 1892, endangered the forfeiture of the contract, the judge’s charge rather conceding this, and treating it as waived ? (2) The evidence is conclusive, requiring the court to say, as matter of law, that Stevens had then so endangered forfeiture as to justify Mundy & Oo. resuming the plant under the contract.”

But we think it would have been plain error had the court so instructed the jury. The contract of February 2, 1892, whereby Stevens agreed to perform the work which Mundy & Oo. had undertaken to do by their contract with the United States government, expressly provided that Stevens was to do the work “within the times fixed by said'contract and the extensions thereof, granted or to be granted.” It is, then, very clear that Stevens was entitled to the benefit of the extension of the time of performance until January 1, 1893, which the government had granted in the first week-of August, 1892. Hence Mundy & Co. had no right to oust Stevens at the very beginning of the extended time without good reason shown. The case, therefore, was not one for peremptory instructions. ■Whether Mundy & Co. had justifiable cause for taking possession of the plant and work on August 16th was submitted to the jury for their determination, the question being presented to them in two aspects. First, however, the jury were instructed that if, prior to that date, there had been an absolute or substantial failure by Stevens to comply with his contract, he was not entitled to recover anything, and whether he had so failed was referred to the jury. Then the charge proceeded thus:

“The defendants further assert [and thus we approach the real subject of controversy between these parties, in the judgment of the court] that the plaintiff absolutely abandoned the work, voluntarily, in August; and that, even if he did not, he was then so far behind in its performance that he could not have completed it by the end of the year, when the government re[83]*83quired it to be completed, or, at least, tliai they were justified by past and ex-: is ting circumstances in believing that be would not so complete it within the time. Herein is embraced the substance of the defense.”

Now it is to be observed that the defendants below took no specific exception to this portion of the charge as misstating the real subject-matter of controversy or unduly narrowing the issues.

The court next proceeded to submit to the jury the question whether Stevens, the plaintiff, had abandoned the work when die defendants .Mundy & Co. took possession, with instructions that, if they so found, the plaintiff could not recover. Finally, the court submitted to the jury the question whether the plaintiff was so far behind in his work on August Kith that Mundy & Co. were justified in believing that he would not complete the work by the end of the year. Here the court said:

"The only serious source of danger to the contract at the time referred to was from failure to complete the work by the end of the year. The efforts of the engineer in charge were intended principally, as it would seem from past experience, to hasten the work. I repeat that the only real source of danger- was involved in the question whether the plaintiff would complete the work within the period named. If you find from the evidence that Mundy & Oo. were justified in believing, from all the circumstances, that the plaintiff would not complete it within the year, then they were justified in turning- him out, and resuming the work themselves; otherwise, they were not.”

And the jury were further instructed that all the circumstances existing at the time the plant was seized by the defendants, and all past experience respecting the work,—the plaintiff’s prior failures and Ms conduct,—were to be taken into account in determining the question whether or not the defendants were justified in believing that the plaintiff would not finish the work by the last of the year, and that if they so believed, or were justified in so believing, they were justified in turning the plaintiff out, and he could not recover. We are not convinced that the defendants below had any right to complain of the manner in which the case was submitted to the jury. From our examination of the evidence, we do not discover that on August 16, 1892, there was any real danger of the forfeiture of Mundy & Oo.’s contract with the government other than from the possible failure to complete the work within the extended time. By the extension in August, presumably, the government had waived past delinquencies. Moreover, the unconfradicted testimony is that the extension was unconditional,—not dependent upon an increase of the plant. Our conclusion, then, is that the seventh assignment of error is without substantial merit, and, accordingly, it is overruled.

All the other assignments of error relate to the liability of the sureties in the bond of February 2, 1892, and they will be considered together. The bond was conditioned for the payment to Stevens by Mundy & Co. of all moneys received by them for work done under the contract with the government, “as provided in the agreement of even date herewith” between Mundy & Co. and Stevens. Turning to that agreement, we find that, by the fourth paragraph thereof, Mundy & Oo. (parties of the second part) bound themselves to pay to Stevens (party of the first part) the contract price for all work done-[84]*84by him as the moneys therefor were received by them from the government. The sixth paragraph of this agreement bound Stevens to pay to Mundy & Co. the consideration or sum of $179,000, as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper Investments v. Conger
775 P.2d 76 (Colorado Court of Appeals, 1989)
United States v. Tyler
220 F. Supp. 386 (N.D. Iowa, 1963)
United States v. Merchants Mutual Bonding Company
220 F. Supp. 163 (N.D. Iowa, 1963)
United States v. Freel
92 F. 299 (U.S. Circuit Court for the District of Eastern New York, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
61 F. 77, 9 C.C.A. 366, 1894 U.S. App. LEXIS 2160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mundy-v-stevens-ca3-1894.