Mundy v. Gentilly Oaks, Inc.

82 So. 2d 849, 228 La. 509, 1955 La. LEXIS 1384
Supreme Court of Louisiana·Decided June 30, 1955·No. No. 42387·Published·Cited by 6 cases

Opinion

SIMON, Justice.

Writs with a stay order were granted to review the ruling of the district judge overruling exceptions of misjoinder of parties defendant and of improper cumulation of actions filed by relators to plaintiff’s suit against them as defendants.

This case was before us on two separate but consolidated appeals prosecuted by the plaintiff from judgments sustaining exceptions of no cause of action and dismissing the suit as to some of the cited defendants.1 In that instance we affirmed the judgment of thé lower court dismissing plaintiff’s suit against the defendants City of New Orleans, Sewerage & Water Board of New Orleans (hereinafter referred to as S & W B), and the Houston Fire & Casualty Insurance Company of Houston, Texas (hereinafter referred to as Houston Fire), and we reversed said judgment insofar as it dismissed the suit against defendant Bradford wherein his exception of no cause of action was sustained. Consequently, the remaining parties defendant against whom damages for various claims are made are: (1) Gentilly Oaks, Inc., hereinafter re[513]*513ferred to as Gentilly Oaks; (2) Southern Engineering & Construction Co., hereinafter referred to as Southern; (3) George E. Bradford, hereinafter referred to as Bradford; (4) United States Fidelity & Guaranty Company, hereinafter referred to as U. S. F. & G.

In our former opinion, supra, following a complete statement of the facts, the following observation was made:

“If exceptions of misjoinder of parties and improper cumulation of actions were presented for our consideration we might be inclined to sustain them, for the suit involves several separate and unrelated demands and there is a lack of community interest among all of the cited defendants. But exceptions of that nature were not passed upon by the trial judge; hence, our review is limited to the matters to which the mentioned two appeals pertain.” Mundy v. Gentilly Oaks, Inc., 227 La. 118, 78 So. 2d 530, 532.

Subsequently, the remaining defendants, relators herein, filed and re-urged the exceptions of misjoinder of parties defendants and improper cumulation of actions. These exceptions were overruled and we granted writs of certiorari, prohibition and mandamus to review the correctness of the trial court’s ruling.

Relators complain that the plaintiff has cumulated numerous unrelated claims against them in one suit. The cumulated causes of action complained of rise out of various transactions entered into by parties herein, plaintiff as well as the parties originally named as party defendants, for the development of a real estate subdivision, including the construction of some 283 houses, on land situated in New Orleans and owned by Gentilly Oaks.

To the end of developing the Gentilly Oaks Subdivision, on July 25, 1951, Gentilly Oaks contracted with S & W. B to obtain the necessary sewerage collection system and water distribution system for the subdivision. The Houston Fire became surety in said contract to the extent of $11,320.

On February 4, 1952, Southern entered into contract with S & W B wherein Southern agreed to perform the work in connection with the installation of the sewerage and water distribution systems in the subdivision. The U. S. F. & G. intervened as surety in this contract, as well as the one executed between S & W B and Gentilly Oaks on July 25, 1951, to the extent of $163,700.

Gentilly Oaks, having previously contracted with the City of New Orleans for the construction of the roadways and grading system, thereafter on February 29, 1952, contracted with Southern to- do and perform said work.

On May 7, 1952, the City of New Orleans by written agreement between it, Gentilly Oaks and Southern assumedly --took official cognizance of the contract previously entered into between Gentilly Oaks and Southern in connection with said [515]*515roadways and grading system, and in Connection therewith U. S. F. & G. executed the bond in the sum of $50,000 as surety with Gentilly Oaks and Southern as principals, in favor of the City of New Orleans to protect it from any damage resulting from a default in the construction of said works.

In performance of the contracts it had undertaken for Gentilly Oaks, Southern subcontracted on May 1, 1952, with the plaintiff, James W. Mundy, by execution of two' separate written contracts, one relating to the installation of water mains and sanitary sewers, the other to the construction of storm sewers.

Plaintiff alleges that he vigorously prosecuted the work undertaken by him by virtue of said written subcontracts until July 3, 1952, when Southern prohibited him from further performance thereof; that from May 1, 1952 to July 3, 1952, he completed certain works, as is shown by Engineers’ Certificates of Completed Work and extensions thereof, issued by F. G. Stewart, Civil Engineer, for which he alleges he was entitled to be paid the sum of $122,922.15. He further alleged that he was entitled to be paid the sum of $9,054.85 for “extras” allegedly performed under said subcontracts.

Plaintiff asserts that despite Southern’s wrongful act of barring him from further performance of his obligation, he was retained in Southern’s employ until August 2, 1952. That Southern also continued to use plainti&’s machinery and equipment until August 18, 1952, but that he has received no remuneration for his services nor for the use of his machinery and equipment.

Plaintiff further alleges that on October 22, 1952, Southern abandoned its contract, assigning same to Bradford; that thereafter Bradford entered into three written subcontracts with plaintiff, dated, respectively, at Birmingham, Alabama, on November 3 and 26, 1952, and at New Orleans, Louisana, on November 18, 1952, under which plaintiff continued his contractual operations until Bradford wrongfully excluded him from further performance of the remaining works, and that he has not been paid for work performed.

Plaintiff alleges that both Bradford and Southern maliciously conspired to breach their subcontracts with him; that they libeled and slandered him to the detriment of his financial and professional reputation.

Plaintiff recorded private and public work liens totalling $125,745.48 against the relators to secure the sum allegedly due him under his several subcontracts.

Hence, the causes of action arising out of the various transactions relating to the development of Gentilly Oaks Subdivision, as urged by plaintiff in his original, first and second supplemental petitions are as, follows:

1— Against Southern for breaches of the two separate written subcontracts, executed on May 1, 1952, and for breaches of alleged oral contracts for extra work performed [517]*517and for supplies and machinery furnished in connection therewith before and after July 2, 1952.

2— Against George E. Bradford, assignee of Southern’s contracts, for breaches of the three written subcontracts- between plaintiff and Bradford above referred to.

3— Against Bradford and Southern for $100,000 additional damages resulting from alleged conspiracy and malicious breach of said contracts.

4— Against Bradford for $100,000 additional damages, resulting from alleged slander and libel.

Free access — add to your briefcase to read the full text and ask questions with AI

Mundy v. Gentilly Oaks, Inc., 82 So. 2d 849, 228 La. 509, 1955 La. LEXIS 1384 (La. 1955).

82 So. 2d 849 (Mundy v. Gentilly Oaks, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

St. Pe v. Neal
534 So. 2d 993 (Louisiana Court of Appeal, 1988)
Mid-South Car & Truck Rental v. Moore
516 So. 2d 1224 (Louisiana Court of Appeal, 1987)
Finn v. EMPLOYERS'LIABILITY ASSURANCE CORPORATION
141 So. 2d 852 (Louisiana Court of Appeal, 1962)
McKnight v. Scott
130 So. 2d 681 (Louisiana Court of Appeal, 1961)
Dupre v. Consolidated Underwriters
99 So. 2d 522 (Louisiana Court of Appeal, 1957)
Greater Baton Rouge Port Commission v. Morley
93 So. 2d 912 (Supreme Court of Louisiana, 1957)