Multiplastics, Inc. v. Arch Industries, Inc.

348 A.2d 618, 166 Conn. 280, 1974 Conn. LEXIS 893
CourtSupreme Court of Connecticut
DecidedApril 16, 1974
StatusPublished
Cited by27 cases

This text of 348 A.2d 618 (Multiplastics, Inc. v. Arch Industries, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Multiplastics, Inc. v. Arch Industries, Inc., 348 A.2d 618, 166 Conn. 280, 1974 Conn. LEXIS 893 (Colo. 1974).

Opinion

*282 Bogdanski, J.

The plaintiff, Multiplasties, Inc., brought this action to recover damages from the defendant, Arch Industries, Inc., for the breach of a contract to purchase 40,000 pounds of plastic pellets. Prom a judgment rendered for the plaintiff, the defendant has appealed to this court.

The facts may be summarized as follows: 1 The plaintiff, a manufacturer of plastic resin pellets, agreed with the defendant on June 80,1971, to manufacture and deliver 40,000 pounds of brown polystyrene plastic pellets for nineteen cents a pound. The pellets were specially made for the defendant, which agreed to accept delivery at the rate of 1000 pounds per day after completion of production. The defendant’s confirming order contained the notation “make and hold for release. Confirmation.” The plaintiff produced the order of pellets within two weeks and requested release orders from the defendant. The defendant refused to issue the release orders, citing labor difficulties and its vacation schedule. On August 18,1971, the plaintiff sent the defendant the following letter: “Against P. O. 0946, we produced 40,000 lbs. of brown high impact *283 styrene, and you have issued no releases. You indicated to us that you would be using 1,000 lbs. of each per day. We have warehoused these products for more than forty days, as we agreed to do. However, we cannot warehouse these products indefinitely, and request that you send us shipping instructions. We have done everything we agreed to do.” After August 18, 1971, the plaintiff made numerous telephone calls to the defendant to seek payment and delivery instructions. In response, beginning August 20, 1971, the defendant agreed to issue release orders but in fact never did.

On September 22, 1971, the plaintiff’s plant, containing the pellets manufactured for the defendant, was destroyed by fire. The plaintiff’s fire insurance did not cover the loss of the pellets. The plaintiff brought this action against the defendant to recover the contract price.

The trial court concluded that the plaintiff made a valid tender of delivery by its letter of August 18, 1971, and by its subsequent requests for delivery instructions; that the defendant repudiated and breached the contract by refusing to accept delivery on August 20,1971; that the period from August 20, 3.971, to September 22,1971, was not a commercially unreasonable time for the plaintiff to treat the risk of loss as resting on the defendant under General Statutes § 42a-2-510 (3); and that the plaintiff was entitled to recover the contract price plus interest.

General Statutes § 42a-2-510, entitled “Effect of breach on risk of loss,” reads, in pertinent part, as follows: “(3) Where the buyer as to conforming goods already identified to the contract for sale repudiates or is otherwise in breach before risk of *284 their loss has passed to him, the seller may to the extent of any deficiency in his effective insurance coverage treat the risk of loss as resting on the buyer for a commercially reasonable time.” 2 The defendant contends that § 42a-2-510 is not applicable because its failure to issue delivery instructions did not constitute either a repudiation or a breach of the agreement. The defendant also argues that even if § 42a-2-510 were applicable, the period from August 20, 1971, to September 22, 1971, was not a commercially reasonable period of time within which to treat the risk of loss as resting on the buyer. The defendant does not claim that the destroyed pellets were not “conforming goods already identified to the contract for sale,” as required by General Statutes § 42a-2-510 (3), nor does it protest the computation of damages. With regard to recovery of the price of goods and incidental damages, see General Statutes §42a-2-709 (1) (a).

The trial court’s conclusion that the defendant was in breach is supported by its finding that the defendant agreed to accept delivery of the pellets at the rate of 1000 pounds per day after completion of production. The defendant argues that since the confirming order instructed the plaintiff to “make and hold for release,” the contract did not specify an exact delivery date. This argument fails, however, because nothing in the finding suggests that the notation in the confirming order was part of the agreement between the parties. Since, as the trial court found, the plaintiff made a proper tender of delivery, beginning with its letter of August 18, *285 1971, 3 the plaintiff was entitled to acceptance of the goods and to payment according to the contract. General Statutes §§ 42a-2-507 (1), 42a-2-307.

The defendant argues that its failure to issue delivery instructions did not suffice to repudiate the contract because repudiation of an executory promise requires, first, an absolute and unequivocal renunciation by the promisor, and, second, an unambiguous acceptance of the repudiation by the promisee. Ya ffe v. Glens Falls Indemnity Co., 115 Conn. 375, 378, 161 A. 521; Wells v. Hartford Manilla Co., 76 Conn. 27, 35, 55 A. 599. Anticipatory repudiation is now governed by General Statutes §§ 42a-2-609 to 42a-2-611, which in some respects alter the prior law on the subject. The present case does not involve repudiation of an executory promise, however, since the defendant breached the contract by failing to accept the goods when acceptance became due.

The defendant next claims that the plaintiff acquiesced in the defendant’s refusal to accept delivery by continuing to urge compliance with the contract and by failing to pursue any of the remedies provided aggrieved sellers by General Statutes § 42a-2-703. In essence, the defendant’s argument rests on the doctrines of waiver and estoppel, which are available defenses under the Uniform Commercial Code. General Statutes §§ 42a-l-103, 42a-l-107, 42a-2-209; Mercanti v. Persson, 160 Conn. 468, 477-79, 280 A.2d 137; see 1 Anderson, Uniform Commercial Code (2d Ed.) §§1-103:31, 1-103:51. The defendant has not, however, shown those defenses *286 to apply. Waiver is the intentional relinquishment of a known right. Brauer v. Freccia, 159 Conn. 289, 295, 268 A.2d 645. Its existence is a question of fact for the trier. Brauer v. Freccia, supra. The trial court did not find that the' plaintiff intentionally acquiesced in the defendant’s breach of their agreement, thereby waiving its right to take advantage of that breach. Indeed, the plaintiff’s repeated attempts to secure compliance seem inconsistent with the possibility of waiver. See Bradford Novelty Co. v. Technomatic, Inc., 142 Conn. 166, 112 A.2d 214, for an example of acquiescence in delayed performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RBC Nice Bearings, Inc. v. SKF USA, Inc.
78 A.3d 195 (Connecticut Appellate Court, 2013)
Polyviou v. Nolasco, No. Cvnh 9712-8591 (Jul. 16, 1999)
1999 Conn. Super. Ct. 9234 (Connecticut Superior Court, 1999)
Polyviou v. Nolasco, No. Cvnh 9712-8591 (Apr. 27, 1999)
1999 Conn. Super. Ct. 5170 (Connecticut Superior Court, 1999)
Rinaldi v. Rinaldi, No. Fa92-0111973s (Jan. 6, 1999)
1999 Conn. Super. Ct. 859 (Connecticut Superior Court, 1999)
Dichello v. Holgrath Corp.
715 A.2d 765 (Connecticut Appellate Court, 1998)
Milford Housing Authority v. Zahornasky, No. Cv96 0055790s (Apr. 23, 1997)
1997 Conn. Super. Ct. 4604 (Connecticut Superior Court, 1997)
Majernicek v. Hartford Casualty Insurance
688 A.2d 1330 (Supreme Court of Connecticut, 1997)
Financial Planning Assoc. Inc. v. Silverman, No. 95-0321635 (Mar. 11, 1996)
1996 Conn. Super. Ct. 1536 (Connecticut Superior Court, 1996)
L.R. Yelding Associates, Inc. v. Belcher, No. Cv94-0246868s (May 19, 1995)
1995 Conn. Super. Ct. 5395 (Connecticut Superior Court, 1995)
Heyman Associates No. 1 v. Insurance Co. of Pennsylvania
653 A.2d 122 (Supreme Court of Connecticut, 1995)
Harlach v. Metropolitan Prop. Liab. Co., No. 504502 (May 1, 1991)
1991 Conn. Super. Ct. 4624 (Connecticut Superior Court, 1991)
Hanover Insurance v. Fireman's Fund Insurance
586 A.2d 567 (Supreme Court of Connecticut, 1991)
Armac Industries, Ltd. v. Citytrust
525 A.2d 77 (Supreme Court of Connecticut, 1987)
Evergreen Manor Associates v. Michel
495 A.2d 1119 (Connecticut Appellate Court, 1985)
Olean v. Treglia
463 A.2d 242 (Supreme Court of Connecticut, 1983)
Loda v. H. K. Sargeant & Associates, Inc.
448 A.2d 812 (Supreme Court of Connecticut, 1982)
New York Annual Conference of the United Methodist Church v. Fisher
438 A.2d 62 (Supreme Court of Connecticut, 1980)
Society for Savings v. Chestnut Estates, Inc.
409 A.2d 1020 (Supreme Court of Connecticut, 1979)
McLemore v. Richardson
343 A.2d 229 (Connecticut Superior Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
348 A.2d 618, 166 Conn. 280, 1974 Conn. LEXIS 893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/multiplastics-inc-v-arch-industries-inc-conn-1974.