Muller Elec. Corp. v. EI DUPONT DE NEMOURS & CO.

450 So. 2d 746, 1984 La. App. LEXIS 8803
CourtLouisiana Court of Appeal
DecidedMay 14, 1984
Docket83-CA-822
StatusPublished
Cited by6 cases

This text of 450 So. 2d 746 (Muller Elec. Corp. v. EI DUPONT DE NEMOURS & CO.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muller Elec. Corp. v. EI DUPONT DE NEMOURS & CO., 450 So. 2d 746, 1984 La. App. LEXIS 8803 (La. Ct. App. 1984).

Opinion

450 So.2d 746 (1984)

MULLER ELECTRIC CORPORATION
v.
E.I. DUPONT DE NEMOURS & CO., INC., and Kendall Construction Co., Inc.

No. 83-CA-822.

Court of Appeal of Louisiana, Fifth Circuit.

May 14, 1984.

*747 Jerome P. Halford, New Orleans, for plaintiff-appellant.

Reuter, Reuter, Reuter & Pizza, Arthur C. Reuter, Jr., New Orleans, for Kendall Const. Co., Inc., defendant-appellee.

Before BOUTALL, C.J., and CHEHARDY and DUFRESNE, JJ.

CHEHARDY, Judge.

Plaintiff, Muller Electric Corporation, instituted this suit on a contract and to enforce a materialman's lien against Kendall Construction Co., Inc., and E.I. Dupont De Nemours & Co., Inc.

The record reflects the following facts:

On February 11, 1980, Dupont entered into a contract with Kendall Construction, the primary contractor, to build a laboratory and storage plant in St. John the Baptist Parish. Kendall in turn contracted with Muller Electric on June 9, 1980 to perform the electrical work on the project. Neither contract was recorded in the parish records.

When a large portion of the bill remained unpaid after the work was completed in 1982, plaintiff filed its lien and instituted this suit. Subsequently a settlement was reached whereby Dupont was dismissed from the suit after it paid plaintiff the retainage of $25,002.03, and plaintiff reserved its right to proceed against Kendall for the matters still in dispute. The contested items concern two claims for extras in the sum of $4,473 and $376, clean up charges of $425.96, and interest and costs.

Following trial, judgment was rendered in favor of plaintiff for the sum of $376 on one invoice, $156 for recordation and filing of the materialman's lien, and "interest on all amounts paid, both pursuant to the compromise heretofore entered into between the parties, and amounts awarded herein."

Judgment was rendered in favor of Kendall Construction Co., Inc., in the sum of $425.96 allowed as a chargeback against plaintiff, and plaintiff's claim against defendant for $4,473 under Invoice No. 8420 was dismissed. Each party was ordered to bear its own cost.

Plaintiff has appealed and defendant has answered the appeal.

In this court plaintiff-appellant contends the trial court erred in (1) disallowing the # 4,473 claim; (2) allowing the chargeback of $425.96; and (3) failing to allow it to recover court costs.

*748 Relative to appellant's first contention, the bill for $4,473 represents the cost of labor and material for furnishing and installing control wiring for 26 exhaust fans and four air handling units, including connections, firestats, solenoid valves and stop/start push buttons. (A firestat is a devise enabling a unit to cut off the motor in the event of fire.)

Plaintiff contends this was extra work not contemplated by the contract, plans or specifications. Defendant contends it was part of plaintiff's contractual obligation.

From the documentary evidence and the testimony of the witnesses it is clear that a problem existed in interpretation of the specifications prior to the time plaintiff submitted its bid.

John Tauzy, plaintiff's electrical estimator, prepared the original bid. He reviewed all of the specifications and noted a conflict in the section dealing with controls.

The electrical specifications called for some work relative to exhaust fans under the supervision of the mechanical or control contractor, and the mechanical specifications defined the control work as part of the mechanical contractor's responsibility.

Tauzy called the electrical engineer employed by the architect and discussed the apparent conflict with him. After this conversation he concluded it was not part of the electrical contractor's responsibility and submitted his bid accordingly.

While the work was in progress Tauzy received a letter from Emile Babst & Co., Inc., the industrial and mechanical contractor, indicating their control contractor, Johnson Controls, was questioning the firestat installation on the equipment fans. Johnson proposed to furnish the firestats to Muller, with Muller to provide the installation and wiring.

Tauzy replied by phone and letter that the specifications called for the electrical contractor to connect the firestats for single phase fans if the fans were associated with the lab hoods or benches and not if the firestats were associated with other lab equipment.

Tauzy then wrote to Mr. Charles Zammit at Kendall Construction, enclosing Babst's letter, stating plaintiff's position with reference to the controls—namely that Muller would connect the firestats to the single phase exhaust fans and that all other control wiring was the responsibility of the control contractor.

John Baxter, assistant general superintendent of Kendall Corporation, answered Tauzy's letter indicating the power wiring was plaintiff's responsibility and ordered it to proceed with the work immediately to maintain job progress.

Baxter testified the specifications were ambiguous and that they did not clearly provide what areas the firestats, solenoid and valves were part of. He noted it was specified everywhere in the control documents, but he decided it was part of the electrical contract because the plans show it in the power wiring and not in the control wiring. He authorized Muller to provide the power to the fan motors, keep records, and submit a claim.

Tauzy testified the additional work was done by Muller and daily time and material records were kept at Baxter's direction, and each record was signed by a representative of Kendall Construction Co. Tauzy stated it is not customary to keep time and material sheets for work clearly covered under a contract, nor is it customary or necessary for the contractor to sign time or material sheets for work done on the job. Baxter acknowledged the request to keep time and material sheets, but indicated it was only for the purpose of considering the claim.

If we were to adopt plaintiff's position the invoice covers extra work not called for under the contract. If we were to adopt Kendall's interpretation, the work performed was provided for by the contract.

With respect to the interpretation of agreements our Civil Code provides:

"When the intent of the parties is doubtful, the construction put upon it, by the manner in which it has been executed by both, or by one with the express or *749 implied assent of the other, furnishes a rule for its interpretation." LSA-C.C. art. 1956.

Since Baxter acknowledged the contract was ambiguous and accurate records were kept to verify the work performed, we conclude Kendall is responsible for payment for the extra work involved, and we will amend the judgment accordingly.

Relative to appellant's second contention, the contract provides for daily clean-up work.

Tauzy testified whenever there was trash on the job the foreman requested a truck to take trash to the dump. The trash consisted principally of boxes for lighting fixtures, receptacles, switches and extra pipe cut off and not used. Tauzy visited the job site on four occasions.

Mr. Muller, vice president of Muller Electric, handled all of the billing. He received the bill for clean-up work in April 1980 and immediately called Michael Gurtler, president of Kendall Corporation. Gurtler told him the bill was being sent to all subcontractors in case they did not do their own clean up, and advised him to ignore the bill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peyton Place, Condominium Associates, Inc. v. Guastella
18 So. 3d 132 (Louisiana Court of Appeal, 2009)
Law Offices of Robert M. Becnel v. Ancale
829 So. 2d 573 (Louisiana Court of Appeal, 2002)
Penton v. Schuster
732 So. 2d 597 (Louisiana Court of Appeal, 1999)
Brown on Behalf of Brown v. Gen. Motors Corp.
662 So. 2d 531 (Louisiana Court of Appeal, 1995)
Lynch v. Hanover Ins. Co.
611 So. 2d 121 (Louisiana Court of Appeal, 1992)
Versai Management, Inc. v. Monticello Forest Products Corp.
479 So. 2d 477 (Louisiana Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
450 So. 2d 746, 1984 La. App. LEXIS 8803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muller-elec-corp-v-ei-dupont-de-nemours-co-lactapp-1984.