Muhly v. Espy

877 F. Supp. 294, 25 Envtl. L. Rep. (Envtl. Law Inst.) 21382, 1995 U.S. Dist. LEXIS 2180, 1995 WL 77965
CourtDistrict Court, W.D. Virginia
DecidedJanuary 18, 1995
DocketCiv. A. 94-0634-R
StatusPublished
Cited by5 cases

This text of 877 F. Supp. 294 (Muhly v. Espy) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muhly v. Espy, 877 F. Supp. 294, 25 Envtl. L. Rep. (Envtl. Law Inst.) 21382, 1995 U.S. Dist. LEXIS 2180, 1995 WL 77965 (W.D. Va. 1995).

Opinion

MEMORANDUM OPINION

TURK, District Judge.

Plaintiffs brought this action pursuant to the citizen suit provision of the Administrative Procedure Act (APA) seeking a Writ of Mandamus to compel the Defendants to perform alleged non-discretionary duties. 5 U.S.C. § 702 and 28 U.S.C. § 1361. They claim they were excluded from the “scoping” process conducted by the Defendants in conjunction with Appalachian Power Company’s (APCo) proposal for the construction of a high-voltage transmission line. 1 By denying their participation, the Plaintiffs believe the Defendants have acted in violation of the National Environmental Policy Act (NEPA) and the regulations promulgated to implement its provisions. 42 U.S.C. §§ 4321-4370c and 40 C.F.R. § 1501.7(a)(1), (e) (1993). 2 In addition, the Plaintiffs claim that their constitutional rights to equal protection and due process of law have been violated. Insisting that they have no other remedy, they seek an order from this court instructing the Defendants to reopen the scoping process to include their input. 3

The matter is presently before the court on the Defendants’ motion to dismiss. Fed. R.Civ.P. 12(b)(1) and 12(b)(6). The Defendants base their motion on several grounds. First, they argue that the court does not *296 have jurisdiction to hear the Plaintiffs’ claims because no final agency action has taken place and because the Plaintiffs have failed to exhaust all available administrative remedies. Further, based on the character of the injuries the Plaintiffs claim to have sustained, the Defendants believe they lack standing to allege violations of NEPA. Lastly, they argue that the remedy of mandamus is inappropriate because scoping is a process left entirely to agency discretion.

A hearing on the Defendants’ motion was held before this court on December 16, 1994. At that hearing, counsel for both sides appeared and presented oral argument. The court took the motion under advisement and suggested that the parties’ attempt to reconcile their differences. Unfortunately, the parties have informed the court that settlement is not probable. As such, this matter is now ripe for the court’s decision.

Having thoroughly reviewed the record, the parties’ pleadings, and the pertinent case and statutory law, the court finds that it must grant the Defendants’ motion. No final agency action has occurred with respect to APCo’s proposal. Therefore, the court does not have jurisdiction to intervene in this matter.

I. BACKGROUND

On March 5, 1991, APCo submitted an application to the United States Department of Agriculture’s Forest Service (USFS) requesting authorization for right-of-way running two hundred feet wide and twelve miles long. If granted, the easement will be used to construct a 765kV high-voltage transmission line across lands under the jurisdiction of the Forest Service, the National Park Service, and the United States Army Corps of Engineers. (Compl.Ex. A). Specifically, the federal land under consideration involves a section of Jefferson National Forest (JNF), as well as, segments of the Appalachian National Scenic Trail, and New River at Blue Stone Lake. (CompLEx. B). 4

After initial consideration of the proposal, the federal agencies determined that construction of such a line constituted a “major federal action,” which could significantly affect the environment. See 40 C.F.R. § 1508.18 (1993). Thereafter, USFS was selected as the lead agency to analyze the project’s potential impact and to prepare the requisite Draft Environmental Impact Statement (DEIS) and the Final Environmental Impact Statement (FEIS). See 40 C.F.R. §§ 1502.1-1503.4 (1993). The National Park Service and the US Army Corps of Engineers were designated as cooperating agencies for these activities.

Under NEPA, federal agencies are required to develop alternatives to proposed major federal actions, including the option of “no action”. NEPA § 102(2)(C)(iii); 102(2)(E) and 40 C.F.R. §§ 1502.1, 1502.14 (1993). In this case, that required the development of alternative routes to the corridor identified in APCo’s proposal to the USFS. 5 In a letter entitled “Friends of the Forest” and dated November 18, 1991, JNF’s Forest Supervisor stated that preliminary alternative routes would be considered from areas in Botetourt, Roanoke, Craig and Giles counties *297 in Virginia. (Tier One Counties) (Compl.Ex. B).

As the initial step in the agencies’ studies, the USFS had a Notice of Intent (NOI) published in the Federal Register on November 21, 1991. 40 C.F.R. § 1508.22 (1993). The publishing of the NOI marked the beginning of the public’s involvement in the process known as “scoping”. See (Compl.Ex. C). After the NOI was published, a series of letters and update briefings were issued by the USFS and JNF. The purpose of this correspondence was to keep the public aware of the progression of the agencies’ studies and to invite citizens to public meetings where they could voice their opinions. The record reveals that at least six of these meetings were conducted during the scoping process, however, none of them were held in the Plaintiffs’ counties. (Compl.Ex. D).

On November 22, 1992, a third briefing paper was issued by JNF. The newsletter stated that, “an important milestone in the analysis of the proposal was reached on May 22, 1992, with the completion of the first step in the public involvement (scoping) process.” (Compl.Ex. D). Under a heading entitled “What’s Next”, the document stated that the federal agencies would now begin to decide which of the issues raised by the scoping were significant enough to be discussed more fully in the DEIS and FEIS. (Compl.Ex. D).

The Plaintiffs maintain that, prior to June of 1994, the Defendants never indicated that any areas, other than those in Tier One Counties, were under consideration as possible alternative routes for the APCo line. However, this changed on June 21, 1994, when the USFS published a “Revised Notice” that indicated that the areas under consideration included, not only Tier One Counties, but also, parcels in Montgomery, Bland, and Pulaski counties. (Tier Two Counties). 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Vaughan v. New York State Dept. of Transp.
2024 NY Slip Op 00106 (Appellate Division of the Supreme Court of New York, 2024)
Pinney v. Nokia
216 F. Supp. 2d 474 (D. Maryland, 2002)
In Re Wireless Telephone Radio Frequency Emissions
216 F. Supp. 2d 474 (D. Maryland, 2002)
Walliser v. Mineta
33 F. App'x 826 (Seventh Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
877 F. Supp. 294, 25 Envtl. L. Rep. (Envtl. Law Inst.) 21382, 1995 U.S. Dist. LEXIS 2180, 1995 WL 77965, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muhly-v-espy-vawd-1995.