Muehlstedt v. City of Lino Lakes

473 N.W.2d 892, 1991 Minn. App. LEXIS 731, 1991 WL 133193
Court of Appeals of Minnesota·Decided July 23, 1991·No. C2-90-2317, C4-90-2321, C7-90-2717 and C6-90-2725·Published·Cited by 8 cases

Opinion

OPINION

CRIPPEN, Judge.

During road construction, trees on the property of respondent Kenneth Muehlst-edt, as well as those from the right of way, were cut and then buried on Muehlstedt’s property. When the buried trees later interfered with respondent’s attempts to build a house, he sued those involved with the road construction. A special jury verdict awarded respondent compensatory and punitive damages against various defendants. Following a new trial on damages, another jury awarded respondent less compensatory damages but more punitive damages. The trial court granted defendants a third trial if respondent did not accept a punitive damages remittitur, and this reduction was accepted. Defendants appeal, principally on the award of punitive damages, and respondent challenges the remit-titur and the trial court’s attorney fees determinations. We reverse and modify in part.

FACTS

In 1979 respondent paid $15,000 for three parcels of land, including Lots 11 and 12 in Lino Lakes, Minnesota. In 1984 respondent petitioned the city for road access to his properties. This request was granted and the city engineer, appellant John Davidson, who was also employed by appellant Tolz, King, Duvall, Anderson & Associates, Inc. (TKDA), drafted the necessary documents for construction of the road. The plans required that trees removed from the right of way be disposed of “off site” and that all other work be done on the right of way unless permission was obtained for workers to enter the abutting private property.

*895 The prime road construction contractor, appellant Northern Asphalt, Inc., subcontracted tree removal to appellant Dell Contracting. Prior to starting work, Davidson and Dell’s representative, appellant John Vickaryous, discussed tree removal. A subsequent telephone conversation between Vickaryous and Davidson occurred during tree removal. Vickaryous used a bulldozer to knock down trees on Lot 11 and to dig a hole in which the trees from respondent’s property and the right of way were buried.

Upon learning that trees were being buried on his land, respondent, who was planning to build a house on Lot 12, called Davidson. As a result, respondent, Davidson and Vickaryous all met on the site to discuss what had happened. During this conversation Davidson allegedly offered to remove the trees.

The next spring respondent built his house. In order to install his septic system, respondent had to have his contractor remove 38 truckloads of trees and refill the hole at a cost of $17,165. Respondent then sued the city, Davidson, TKDA, Northern, Dell, and Vickaryous.

At trial, conflicting testimony was entered regarding the contents of the Vickar-yous-Davidson telephone call. Also, testimony conflicted as to whether respondent consented to the burial of the trees during the on-site conversation. Testimony further conflicted regarding the number and type of respondent’s trees bulldozed by Vickaryous. The jury returned a special verdict awarding respondent $25,818 for the destroyed trees and $17,165 in compensatory damages for the burial of trees. The jury also assessed punitive damages against Vickaryous, Dell, Davidson, and TKDA. After statutory trebling of the compensatory damages for the destroyed trees, the award totaled $180,619.

Appellants moved for JNOV, noting respondent had offered no evidence of appellants’ abilities to pay punitive damages. The trial court denied the JNOV motion but found all damages excessive except the award for tree burial. The trial court then offered respondent the choice between a new trial or reduced awards on the damages deemed excessive.

Respondent opted for a new trial and in those proceedings he presented evidence of the appellants’ abilities to pay punitive damages. The trial court told the second jury that it was not to consider whether punitive damages were appropriate, and submitted the damages questions to the jury. The second jury awarded respondent $15,785 as compensatory damages for the bulldozed trees and assessed punitive damages greater than those assessed by the first jury against the same defendants, including a $500,000 assessment against TKDA. After statutory trebling of the tree loss award, damages in the second trial totaled $617,355. 1

Finding the punitive damages assessment against TKDA excessive, the trial court again granted respondent a choice between a new trial and an award of $100,-000 in punitive damages against TKDA. Respondent accepted the reduced award.

ISSUES

1. Are treble damages for injury to trees and punitive damages mutually exclusive? Did the trial court otherwise err in its approach to punitive damages?

2. Is the evidence sufficient to support special verdict findings? Did the trial *896 court abuse its discretion by allowing certain evidence of compensatory damages, or in its rulings on attorney fees.

ANALYSIS

1. Punitive Damages

The primary elements of the appeal are respondent’s challenge on the use of the final remittitur and TKDA’s allegation that the remaining $100,000 punitive damage award is still excessive. To reach a conclusion on these contentions, we also must address specific challenges to the entire punitive damage award.

a. Treble and Punitive Damages

By statute, compensatory damages for trees cut from the land of another are trebled. Minn.Stat. § 561.04 (1988). In Johnson v. Jensen, 446 N.W.2d 664 (Minn.1989), the supreme court held inappropriate the recovery of both treble damages and punitive damages for trespass largely in the form of damage to trees and shrubs. Id. at 666.

Here, the special verdict form allowed punitive damages to be assessed only for the burial of trees on respondent’s property, not for the damages to respondent’s trees. The jury instructions similarly required the jury to distinguish the trespass to respondent’s trees from trespass to respondent’s real estate. We conclude that the trial court’s instructions and the special verdict form are lawful. 2

b. Vicarious Liability

By statute, punitive damages can properly be awarded against an employer if the employee worked in a managerial capacity and acted in the scope of employment. See Minn.Stat. § 549.20, subd. 2(c) (1990). Here, Davidson was a TKDA manager. TKDA, however, argues that under Shetka v. Kueppers, Kueppers, Von Feldt & Salmen, 454 N.W.2d 916 (Minn.1990), the trial court erred in allowing assessment of punitive damages. We disagree.

Shetka involved an unsuccessful attempt to use the financial status of an alleged tortfeasor’s partners to determine a punitive damages award. Shetka, 454 N.W.2d at 919. Thus, Shetka addressed the measuring of punitive damages under Minn. Stat. § 549.20, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Muehlstedt v. City of Lino Lakes, 473 N.W.2d 892, 1991 Minn. App. LEXIS 731, 1991 WL 133193 (Mich. Ct. App. 1991).

473 N.W.2d 892 (Muehlstedt v. City of Lino Lakes) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

DeWitt v. London Road Rental Center, Inc.
899 N.W.2d 883 (Court of Appeals of Minnesota, 2017)
Steven Wrolstad v. Benjamin Napper
Court of Appeals of Minnesota, 2016
Carpenter v. Countrywide Home Loans, Inc.
250 S.W.3d 697 (Supreme Court of Missouri, 2008)
Peterson v. BASF Corp.
657 N.W.2d 853 (Court of Appeals of Minnesota, 2003)
Redburn v. Ferlitto
565 N.W.2d 35 (Court of Appeals of Minnesota, 1997)
Independent School District No. 622 v. Keene Corp.
495 N.W.2d 244 (Court of Appeals of Minnesota, 1993)
TXO Production Corp. v. Alliance Resources Corp.
419 S.E.2d 870 (West Virginia Supreme Court, 1992)