Muchow v. SCHAFFNER Et Ux.

119 A.2d 568, 180 Pa. Super. 413, 1956 Pa. Super. LEXIS 584
CourtSuperior Court of Pennsylvania
DecidedNovember 16, 1956
DocketAppeal, 182
StatusPublished
Cited by16 cases

This text of 119 A.2d 568 (Muchow v. SCHAFFNER Et Ux.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muchow v. SCHAFFNER Et Ux., 119 A.2d 568, 180 Pa. Super. 413, 1956 Pa. Super. LEXIS 584 (Pa. Ct. App. 1956).

Opinion

Opinion by

Ervin, J.,

This is an action of scire facias upon a mechanic’s lien brought by Fred Muchow, a contractor, against Cus J. Schaffner, Jr., and Dorothy R. Schaffner, his wife, to recover for labor and materials actually expended in the construction of a building on the property of the defendants. After trial in the Court of Common Pleas of Allegheny County the jury returned a verdict for the plaintiff for the full amount of his claim, including interest, totalling $2,073.28. During the trial, at the conclusion of the plaintiff’s case, the defendants’ motion for compulsory nonsuit was refused. Defendants’ motions for judgment n.o.v. and for a new trial were overruled by the court below and this appeal followed.

We will not consider the contention of defendants that the lower court committed error in refusing the motion for compulsory nonsuit. It has long been settled law in this Commonwealth that no appeal lies from the refusal to grant a compulsory nonsuit. Carroll v. Hannon, 289 Pa. 65, 137 A. 127; Shapiro v. Phil *416 adelphia, et al., 306 Pa. 216, 159 A. 29; Morgan v. Duquesne Boro., 29 Pa. Superior Ct. 100.

In reviewing the record we will consider the facts and the reasonable inferences therefrom in a light most favorable to the plaintiff as we are required to do: Harris v. DeFelice, 379 Pa. 469, 109 A. 2d 174; Dauphin Deposit Trust Company v. Lumbermens Mutual Casualty Company, 171 Pa. Superior Ct. 86, 90 A. 2d 349. Thus viewed, the following factual situation is presented. On January 9, 1950, the plaintiff and Gus J. Schaffner, Jr., one of the defendants, entered into a written agreement providing for the erection of a two-story concrete-block building by the plaintiff on the premises of the defendants. The agreement provided, inter alia, that plaintiff would, in the construction of the building, dig 3 feet for the footer, that all walls were'to be 33 courses high above the footer and there were to be 6 pilasters of hard common brick 16 x 16 from footer to top beams. The building was to be approximately 30 feet long and 27 feet 8 inches wide with ceilings to be 10 feet. The agreement also provided “All extra work to be paid for at the rate of $1.50 per hr. plus cost of material.” The price agreed upon for the job was $2,737.00. The plaintiff commenced work on the construction of the building and shortly after excavation was begun he concluded that the ground would not support the building with a footer only three feet deep and that it would be necessary to dig deeper to properly place the footer. Plaintiff testified he called this condition to the attention of the defendant, Gus J. Schaffner, Jr., and that the following conversation took place between him and Schaffner: “We went three feet and I called Gus and I said, ‘Gus, we Avill have to go deeper for a footer. That ground Avon’t hold the building.’ Pie said, ‘That’s all right, go ahead.’ I said, ‘It will be extra Avork ac *417 cording to the contract.’ He said, ‘That’s all right. Don’t worry about extra work. We are going to have extra work all the way through on this building. Don’t worry about it. I’ll pay for it whatever it is. Forget the contract.’ And I said, ‘All right’. And we did that work.” This testimony was corroborated by the testimony of one of the workmen. Plaintiff completed the erection of the building which, when finished, was materially different from the structure contemplated in the original written agreement. Plaintiff thereupon demanded payment on the basis of an oral contract on a time and material basis and when defendants refused payment he filed his claim in the total amount of $4,351.07 representing labor charges in the amount of $1,975.50 and charges for materials totalling $2,-375.57. In his claim plaintiff made no allowances for payments received but during the trial he acknowledged that he had received certain payments and that some of the materials had been paid for by the defendants. The total of these payments was $2,724.97, leaving a balance due plaintiff, according to his contention, of $1,626.10 with interest from March 11, 1950. The defendants contend the total charges on the basis of the written agreement, would amount to $2,737.00 plus their estimate of extras of $273.45 or a total charge for the building of $3,010.45. Defendants also asserted a counterclaim for $943.53 on the basis of additional expenditures they were required to make in order to complete the building after plaintiff refused to do so.

The pivotal issue here involved can be stated as follows: Was the original written agreement of the parties providing for the construction of a building at a fixed price of $2,737.00 with provision for payment of extra work at a stipulated hourly rate of $1.50 plus cost of materials superseded by an oral agreement providing for payment on a time and material basis?

*418 The parties to a contract may rescind it by making a new contract inconsistent therewith. Klugh Estate, 362 Pa. 166, 66 A. 2d 822. Moreover, “The agreement to rescind or modify need not be express. Mutual assent to abandon a contract, like mutual assent to form one, may be inferred from the attendant circumstances and conduct of the parties.” Williston on Contracts (Rev. Ed.), Vol. YI, §1826. Section 408, Restatement of Contracts, states: “A contract containing a term inconsistent with a term of an earlier contract between the same parties is interpreted as including an agreement to rescind the inconsistent term in the earlier contract. The parties may or may not at the same time agree to rescind all the other provisions of the earlier contract. . . .” As stated by Judge Reno in Priester v. Milleman, 161 Pa. Superior Ct. 507, 516, 55 A. 2d 540: “The parties to a written contract may always show that it was subsequently abandoned in whole or in part, modified, changed or a new one substituted, and this may be established by an express parol agreement or actions necessarily involving the alterations. Achenbach v. Stoddard, 253 Pa. 338, 98 A. 604. The agreement to modify need' not be expressed in words; it may be inferred from acts and declarations of the parties inconsistent with the original contract. Weldon and Kelly Co. v. Pavia Co., 354 Pa. 75, 46 A. 2d 466.” In the instant case, when confronted with the impossibility of erecting the building with footers three feet deep, the defendant stated to the plaintiff — “Forget the contract.” Ellis Van Newkirk, one of the workmen, also testified that defendant told plaintiff “Forget the contract. I told you when you started working for me that I wanted the building done, a good building — you would get paid for all the material and time it took to build this building. Forget about the contract.” These unequivocal declarations were not made *419 solely in reference to the provision in the written agreement calling for footers three feet in depth but in apparent contemplation of many other changes anticipated by the defendant who also stated — “We are going to have extra work all the way through on this building.” His prophetic accuracy is fully substantiated by the fact the completed structure was materially different from that contemplated by the written agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Helpin v. Trustees of the University of Pennsylvania
969 A.2d 601 (Superior Court of Pennsylvania, 2009)
North Wales Associates, Inc. v. Intown Properties, Inc.
152 F. Supp. 2d 643 (E.D. Pennsylvania, 2001)
Elder v. Orluck
483 A.2d 474 (Supreme Court of Pennsylvania, 1985)
Rumbaugh v. Beck
491 F. Supp. 511 (E.D. Pennsylvania, 1980)
Jones v. Commonwealth
407 A.2d 922 (Commonwealth Court of Pennsylvania, 1979)
Churilla v. Barner
409 A.2d 83 (Superior Court of Pennsylvania, 1979)
Trustees of First Presbyterian Church v. Oliver-Tyrone Corp.
375 A.2d 193 (Superior Court of Pennsylvania, 1977)
Trustees of First Presbyterian Church v. Oliver Tyrone Corp.
72 Pa. D. & C.2d 410 (Alleghany County Court of Common Pleas, 1974)
Kersey Manufacturing Co. v. Rozic
215 A.2d 323 (Superior Court of Pennsylvania, 1965)
Wathen v. Brown
189 A.2d 900 (Superior Court of Pennsylvania, 1963)
Grasavage Unemployment Compensation Case
186 A.2d 46 (Superior Court of Pennsylvania, 1962)
Kirk v. Brentwood Manor Homes, Inc.
159 A.2d 48 (Superior Court of Pennsylvania, 1960)
Fritz v. Lyons
138 A.2d 182 (Superior Court of Pennsylvania, 1958)
McRoberts v. Phelps
138 A.2d 439 (Supreme Court of Pennsylvania, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
119 A.2d 568, 180 Pa. Super. 413, 1956 Pa. Super. LEXIS 584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muchow-v-schaffner-et-ux-pasuperct-1956.