M.T.D. Environmental, L.L.P. v. City of Midland

315 S.W.3d 606, 2010 Tex. App. LEXIS 4824, 2010 WL 1948319
Court of Appeals of Texas·Decided June 24, 2010·No. 11-09-00004-CV·Published·Cited by 4 cases

Opinions

OPINION

TERRY McCALL, Justice.

M.T.D. Environmental, L.L.P. (MTD) filed this suit against the City of Midland (the City) under the Payment for Goods and Services Act (the Prompt Payment Act). Tex. Gov’t Code Ann. §§ 2251.001-.055 (Vernon 2008). MTD sought payment of an unpaid invoice, alleging that it had completed performance under its contract with the City. The City sought summary judgment on the ground that a release provision in the contract barred MTD’s cause of action for breach of contract. In response, MTD claimed that the release provision was void because Section 2251.004 of the Prompt Payment Act prohibits the waiver of any right or remedy granted under the Act. The trial court granted summary judgment to the City. We reverse and remand.

Background Facts

MTD entered into a contract with the City to grind and haul yard waste materials (e.g., tree limbs) at two locations in Midland County: the Smith Road location and the city landfill. The contract provided that MTD would be paid $12.25 per ton for yard waste ground at both locations and $125 per truckload hauled from the Smith Road location to the city landfill. After MTD completed the work at the Smith Road location, the City paid the invoices that MTD presented. MTD then moved to the city landfill location to finish the mulch grinding there. After completing its grinding at the city landfill, MTD calculated that it had ground 8,213 tons of material. MTD then submitted an invoice to the City requesting payment of $100,609.25.

A dispute arose between MTD and the City over the amount of work actually performed at the city landfill. The City notified MTD of the dispute, and MTD submitted a reduced invoice; however, the parties continued to disagree on the amount of work actually performed and the amount to be paid. As a result, MTD was not paid for the grinding at the city landfill, and it filed this suit.

[608]*608The City moved for summary judgment on the ground that MTD’s claim for breach of contract was barred because the contract between the parties contained a clause that released any breach of contract claim MTD had or might have in the future against the City. The City asserted that the Prompt Payment Act did not apply to MTD’s claim because there was a bona fide dispute between the parties. To support its motion for summary judgment, the City filed the affidavit of Kay Snyder, Director of Utilities for the City. Snyder stated in her affidavit that, after the work was performed, a dispute arose over the amount of material that MTD ground and that, as a result of the dispute, MTD had not been paid. The City moved for partial summary judgment on the alternative ground that the contract between the parties contained a “Waiver of Attorney Fees” clause that barred MTD’s recovery of attorney’s fees. The trial court granted summary judgment to the City.

MTD presents three issues on appeal: (1) the trial court erred in granting summary judgment because genuine issues of material fact exist; (2) the trial court erred in granting summary judgment on the ground that the Prompt Payment Act does not apply because a bona fide dispute existed between the parties; and (3) the trial court erred in granting summary judgment on the ground that the release and waiver provisions in the contract barred its claim.

Standards of Review

A trial court must grant a traditional motion for summary judgment if the moving party establishes that no genuine issue of material fact exists and that it is entitled to judgment as a matter of law. Tex.R. Civ. P. 166a(c); Lear Siegler, Inc. v. Perez, 819 S.W.2d 470, 471 (Tex.1991). In order for a defendant to be entitled to summary judgment, it must either disprove an element of each cause of action or establish an affirmative defense as a matter of law. Am. Tobacco Co. v. Grinnell, 951 S.W.2d 420, 425 (Tex.1997). Once the movant establishes a right to summary judgment, the nonmovant must come forward with evidence or law that precludes summary judgment. City of Houston v. Clear Creek Basin Auth., 589 S.W.2d 671, 678-79 (Tex.1979). When reviewing a traditional summary judgment, the appellate court considers all the evidence and takes as true evidence favorable to the nonmov-ant. Am. Tobacco Co., 951 S.W.2d at 425; Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548A9 (Tex.1985). The appellate court “must consider whether reasonable and fair-minded jurors could differ in their conclusions in light of all of the evidence presented” and may not ignore “undisputed evidence in the record that cannot be disregarded.” Goodyear Tire & Rubber Co. v. Mayes, 236 S.W.3d 754, 755, 757 (Tex.2007). Summary judgments are subject to de novo review.

Interpreting statutes is a legal matter also subject to de novo review. Bragg v. Edwards Aquifer Auth., 71 S.W.3d 729, 734 (Tex.2002). Determining legislative intent is the overriding goal of statutory interpretation. Cont’l Cas. Co. v. Downs, 81 S.W.3d 803, 805 (Tex.2002). We first look to the plain and common meaning of the words used by the legislature. Tex. Gov’t Code Ann. § 311.011 (Vernon 2005); Kroger Co. v. Keng, 23 S.W.3d 347, 349 (Tex.2000). Statutes are interpreted by considering the entire statute, not just disputed provisions. Thomas v. Cornyn, 71 S.W.3d 473, 481 (Tex.App.-Austin 2002, no pet.). Courts must interpret a statute to promote its underlying purpose and the policies it embodies. Nw. Nat’l County Mut. Ins. Co. v. Rodriguez, 18 S.W.3d 718, 721 (Tex.App.-San Antonio 2000, pet. denied).

[609]*609Whether a release or waiver clause is enforceable or void is also a question of law that appellate courts review de novo. Ranger Ins. Co. v. Ward, 107 S.W.3d 820, 824 (Tex.App.-Texarkana 2003, pet. denied).

The Contract

A release or waiver is an agreement by one party to surrender its own cause of action against the other party. Dresser Indus., Inc. v. Page Petroleum, Inc., 853 S.W.2d 505, 508 (Tex.1993). The contract between MTD and the City contained the following release clause:

10. RELEASE: NOTWITHSTANDING ANY OTHER PROVISIONS, [MTD] HEREBY RELEASES, ACQUITS, RELINQUISHES AND FOREVER DISCHARGES [THE CITY] FROM ANY AND ALL DEMANDS, CLAIMS, DAMAGES AND CAUSES OF ACTION OF ANY KIND WHATSOEVER WHICH [MTD] HAS OR MIGHT HAVE IN THE FUTURE, INCLUDING BUT NOT LIMITED TO BREACH OF CONTRACT, QUANTUM MERUIT.

Free access — add to your briefcase to read the full text and ask questions with AI

M.T.D. Environmental, L.L.P. v. City of Midland, 315 S.W.3d 606, 2010 Tex. App. LEXIS 4824, 2010 WL 1948319 (Tex. Ct. App. 2010).

315 S.W.3d 606 (M.T.D. Environmental, L.L.P. v. City of Midland) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Midland v. M.T.D. Environmental, L.L.P.
429 S.W.3d 800 (Court of Appeals of Texas, 2014)
M.T.D. Environmental, L.L.P. v. City of Midland
315 S.W.3d 606 (Court of Appeals of Texas, 2010)