McMahon Contracting, L.P. v. City of Carrollton

277 S.W.3d 458, 2009 WL 104779
CourtCourt of Appeals of Texas
DecidedMarch 17, 2009
Docket05-07-01626-CV
StatusPublished
Cited by50 cases

This text of 277 S.W.3d 458 (McMahon Contracting, L.P. v. City of Carrollton) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMahon Contracting, L.P. v. City of Carrollton, 277 S.W.3d 458, 2009 WL 104779 (Tex. Ct. App. 2009).

Opinion

OPINION

Opinion by

Justice LANG.

McMahon Contracting, L.P. brought suit against the City of Carrollton, claiming the *461 City owed McMahon payment for retain-age due under a street replacement contract and additional compensation for “extra work” performed at City’s direction. McMahon specifically plead claims for breach of contract, quantum meruit, and interest and attorney fees under the Prompt Payment Act. See Tex. Gov’t Code Ann. §§ 2251.001-.055 (Vernon 2008). The trial court granted summary judgment in City’s favor. McMahon timely perfected this appeal.

In three issues, McMahon asserts trial court error in granting summary judgment on McMahon’s breach of contract claims. Specifically, McMahon contends, pursuant to Texas Rule of Civil Procedure 166a(c), City’s motion was insufficient as a matter of law because: (1) it did not specify the legal grounds supporting summary judgment or specify which elements of McMahon’s pleaded causes of action were “conclusively negated” by the summary judgment evidence enumerated in City’s motion, (2) there is a conflict in the summary judgment evidence as to City’s contention that McMahon “failed to be 100% complete” within the time specified, (3) there is no pleading or summary judgment evidence to show McMahon failed to be “100% complete” by the contract time, and (4) there is no pleading to support and there is conflicting evidence regarding City’s position that compensation for extra work could not be recovered.

In a cross-point on appeal, City argues because of its governmental immunity 1 the trial court lacked subject matter jurisdiction over McMahon’s claims for quantum meruit and for interest and attorney fees under the Prompt Payment Act. McMahon agrees governmental immunity was not waived for its quantum meruit claim, but contends governmental immunity was waived for the Prompt Payment Act claim.

We conclude McMahon did not demonstrate City’s immunity was waived on the Prompt Payment Act claim. However, we conclude further that City was not entitled to summary judgment on McMahon’s breach of contract claims. Accordingly, we reverse the trial court’s summary judgment, render judgment that City’s plea to the jurisdiction is sustained regarding its governmental immunity on the Prompt Payment Act and quantum meruit claims, and remand to the trial court the breach of contract claims for retainage and “extra work” for further proceedings.

I. FACTUAL AND PROCEDURAL BACKGROUND

On July 17, 2001, the City of Carrollton entered into a street replacement contract with McMahon. The contract included a specific “quality of workmanship” provision regarding City’s “general design standards” for cracks in pavement and stated “stress cracks of any nature” were “subject to being removed and replaced at the discretion of the Director of Public Works *462 at no additional cost.” McMahon’s work was to be “100% complete” by March 10, 2003. The record reflects, in accordance with the contract, City retained part of the payments allegedly due to McMahon. Also, the contract provided for a change order procedure and specifically stated claims for extra work would “not be paid unless the work covered by such claims was authorized in writing by the Owner.” Finally, the contract required McMahon to provide City with a detailed cost estimate, upon request, for any proposed extra work.

The parties do not dispute that McMahon did not complete the project by the contractual completion date. On April 28, 2003, City provided McMahon with a six-page “final punchlist” that listed all work City required McMahon to perform before City considered the project completed. The list included replacement of several cracked street panels.

During June and July 2003, City and McMahon engaged in a series of correspondence arguing about whether replacement of the cracked street panels constituted “warranty” work for which City would pay or whether it was work covered under the contract requiring the cracked panels be removed and replaced at no cost to City. City asserted its request for street panel replacement was not warranty work “but part of a punchlist of items that need to be repaired to accept this project.” McMahon asserted the cracks were “not the results of any defective material or workmanship” and it was “not responsible for repairing the cracks.” On July 22, 2003, McMahon sent City a letter requesting City approve a panel replacement list if City “agree[d] with the panel locations and the measurements.” City’s superintendent signed the panel replacement sheets on July 24, 2003.

McMahon performed the panel replacement work and sent City a request for payment, in the amount of $70,056.80, for “extra work performed” to replace the street panels. In its reply, City asserted “[t]he replacement of the panels was to repair faulty work” and no payment was due because the work was performed prior to project acceptance and without an approved change order.

McMahon filed suit to recover sums retained by City from payments due under the contract and also sums for alleged “extra work,” and in the alternative, for quantum meruit. Also, McMahon sought pre- and post-judgment interest and attorney fees under the Prompt Payment Act. See generally Tex. Gov’t Code Ann. §§ 2251.001-.055. City responded by filing a plea to the jurisdiction, asserting governmental immunity had not been waived. The trial court denied the plea to the jurisdiction. City pursued an interlocutory appeal to this Court. We reversed and dismissed the case, deciding against McMahon’s argument that section 51.057 of the local government code, which stated governmental entities could “sue and be sued,” waives a city’s immunity from suit. See City of Carrollton v. McMahon Contracting, L.P., 134 S.W.3d 925 (Tex.App.Dallas 2004), rev’d on other grounds, 197 S.W.3d 387 (Tex.2006) (per curiam). In the meantime, the Texas Supreme Court decided Tooke v. City of Mexia, wherein it agreed with the proposition we stated in our conclusion regarding the effect of section 51.057. See Tooke, 197 S.W.3d at 332. Then, based upon Tooke, the Texas Supreme Court affirmed our decision in the interlocutory appeal of this ease and remanded this case to the trial court to consider the application of the newly enacted local government code sections 271.151-.160. See McMahon Contracting, 197 S.W.3d at 387.

*463 Upon remand to the trial court, City filed a revised plea to the jurisdiction, a first amended original answer, and a motion for summary judgment. City’s motion asserted four grounds for summary judgment, which we quote below:

(a) Plaintiff failed to be “100% complete” with the work within the time specified in the contract for completion.
(b) No extra work was performed on the project except as authorized by Change Order No. 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marcia Slack v. Robert Charles Shreve, Jr.
Court of Appeals of Texas, 2024
Kenneth R. Cade v. State Farm Lloyds
Court of Appeals of Texas, 2024
Robert A. Adams, III v. City of Pineland
Court of Appeals of Texas, 2024
Vassar Group, Inc. v. Heeseon Ko
Court of Appeals of Texas, 2019
St. John Missionary Baptist Church v. Flakes
547 S.W.3d 311 (Court of Appeals of Texas, 2018)
NBL 300 Group Ltd. v. Guadalupe-Blanco River Authority
537 S.W.3d 517 (Court of Appeals of Texas, 2017)
County of Galveston v. Triple B Services, LLP
498 S.W.3d 176 (Court of Appeals of Texas, 2016)
Linda Fitzerman v. Classic Americana, LLC
Court of Appeals of Texas, 2016
City of Midland v. M.T.D. Environmental, L.L.P.
429 S.W.3d 800 (Court of Appeals of Texas, 2014)
Weir Bros., Inc. v. Longview Economic Development Corp.
373 S.W.3d 841 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
277 S.W.3d 458, 2009 WL 104779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmahon-contracting-lp-v-city-of-carrollton-texapp-2009.