MSEJ, LLC v. Transit Casualty Co.

280 S.W.3d 621, 2009 Mo. LEXIS 33, 2009 WL 837718
CourtSupreme Court of Missouri
DecidedMarch 31, 2009
DocketSC 89663
StatusPublished
Cited by9 cases

This text of 280 S.W.3d 621 (MSEJ, LLC v. Transit Casualty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MSEJ, LLC v. Transit Casualty Co., 280 S.W.3d 621, 2009 Mo. LEXIS 33, 2009 WL 837718 (Mo. 2009).

Opinion

MICHAEL A. WOLFF, Judge.

Introduction

This appeal tests the ability of the circuit court to enforce its deadline for submitting claims in the long-running Transit Casualty receivership. Ten years ago, MSEJ bought some claims that date back to the 1980s. It now asserts that the receivership statute allows it one more chance to present those claims before the final curtain falls.

The circuit court correctly held that the curtain has fallen.

History

Transit Casualty Company is an insurance company that was declared insolvent by the circuit court on December 3, 1985. All of its policies were canceled, and it entered receivership under the supervision of the court and a “special deputy receiver” appointed to represent the director of the department of insurance, the nominal receiver. The receivership court set a “bar date” — that is, a deadline of December 31, 1987 — for the filing of claims against the company’s receivership estate. The receiver was charged with handling outstanding claims and winding down the insolvent business. In 1986, pursuant to section 375.670.1 1 , the receivership court issued an administrative order stating that the court would “from time to time issu[e] serially numbered Administrative Orders relative to administration, procedures, systems, goals and actions to be taken by the Receivership and those involved in the Receivership.” 2

In 1987, the receivership court issued Administrative Order 13, adopting Rule 75, which was to govern the procedure for bringing claims. Although the bar date was December 31, 1987, Rule 75.6(b) outlined a test for determining whether to allow a post-bar-date claim. The special deputy receiver was to consider whether “a. the claimant did not know of the Claim prior to the December 31, 1987 bar date; b. the claimant filed the Claim with the Receivership as promptly as reasonably possible upon learning of the Claim; c. the Claim is covered by the policy; and d. allowance of the Claimant’s late-filed Claim will not prejudice the orderly administration of the liquidation of the Receivership.” Claims filed after the bar date were allowed only if the special deputy receiver determined that they passed the test prescribed by Rule 75.6(b). 3

The circuit court as receivership court issued Administrative Order 49, which established a final, once-and-for-all time limit on the filing of claims. Administrative Order 49 stated that “to expedite the closure of the Receivership ... all claimants, including those that have already filed policyholder protection proof of claim forms, must file the existing evidence of their current unresolved claims ... by 3/15/01. *623 After that date no new claims or evidence of claims shall be accepted by the Special Deputy Receiver.”

One of Transit’s policy holders was the Johns-Manville Corporation, which purchased six umbrella liability policies. Manville timely filed proof of claims against Transit. A proof of claim is notice given to the receiver that the claim holder asserts that it is entitled to payment. In 1998, MSEJ purchased from Manville all of its outstanding claims against Transit at the time it entered receivership. Three years after MSEJ purchased Manville’s interest in the receivership, MSEJ filed $19 million in additional claims. There was no additional proof submitted with these claims beyond a one-page letter stating MSE J’s position that it was entitled to payment of the new, unsupported claims. The proof of claim failed to include the names of policyholders or the dates or details of any alleged injuries incurred by the policyholders. MSEJ did not supply any of this information prior to March 15, 2001, the date specified as the claim termination deadline in Administrative Order 49.

The special deputy receiver determined that there was insufficient evidence to support the March 2001 claim. In May 2001, the receiver mailed its notice of determination to MSEJ. MSEJ filed a request for review the next month. Section 375.1214 provides for appeal from denials of claims by a receiver. The matter is appealed to a referee, who makes findings of fact and conclusions of law and enters a recommendation concerning the claim. Id. Here, MSEJ filed for appeal to the referee. On September 7, 2005, MSEJ attempted to submit supplemental evidence to the referee, who refused to consider the evidence not previously submitted to the special deputy receiver. The referee determined that the March 2001 cutoff barred consideration of supplemental evidence and upheld the receiver’s denial of the March 1, 2001 claim. Further, the referee determined that MSEJ “should be estopped from making any further claims” because MSEJ and its assignor Manville previously had told the receiver that it would be making no further claims against the Transit estate. MSEJ moved for reconsideration in the circuit court pursuant to section 375.1214.2. Because the circuit court failed to rule on the motion within 90 days the motion was considered overruled. MSEJ appealed. After opinion in the court of appeals, this Court granted transfer pursuant to Mo. Const, art. V, § 10.

Standard of Review

In this case, the referee did not observe -witness testimony but instead reviewed depositions and documentary evidence. The trial court relied on the referee’s findings of fact and conclusions of law. Despite the documentary nature of the evidence, this Court — though it need not defer to credibility determinations made by the trial court — “defers to the trial court as the finder of fact in determinations as to whether there is substantial evidence to support the judgment and whether that judgment is against the weight of the evidence, even where those facts are derived from pleadings, stipulations, exhibits and depositions.” Business Men’s Assur. Co. of America v. Graham, 984 S.W.2d 501, 506 (Mo. banc 1999). In other words, even though this Court has the same opportunity to review the evidence as does the circuit court, the law allocates the function of fact-finder to the circuit court.

Did the circuit court err in finding that MSEJ failed to support its claims?

The first issue before this Court is whether the circuit court erred in holding *624 that MSEJ failed, prior to March 2001, to adduce sufficient evidence of its claim. This Court holds that it did not err. Local Rule 75.19(c) states that in cases of contested claims, “[t]he burden of proof shall be the same as the burden of proof established by the law of the State of Missouri for contested judicial claims against an insurance carrier.” In Missouri, that burden rests on the insured or its assignees— in this case, MSEJ. See Johnston v. Sweany, 68 S.W.3d 398, 401 (Mo. banc 2002) (“The burden of proof upon the question of compliance with the provisions of a policy ordinarily rests upon the insured, if he seeks to recover indemnity under the policy, or upon the injured party who stands in the shoes of the insured.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. D.W.
558 S.W.3d 589 (Missouri Court of Appeals, 2018)
State of Missouri, ex rel, Chris Koster, Attorney General v. Mark Bailey
493 S.W.3d 423 (Missouri Court of Appeals, 2016)
In re Ambassador Insurance Company, Inc.
2015 VT 4 (Supreme Court of Vermont, 2015)
Pearson v. Koster
367 S.W.3d 36 (Supreme Court of Missouri, 2012)
Mapes v. Director of Revenue
361 S.W.3d 29 (Missouri Court of Appeals, 2011)
State v. Williams
334 S.W.3d 177 (Missouri Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
280 S.W.3d 621, 2009 Mo. LEXIS 33, 2009 WL 837718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/msej-llc-v-transit-casualty-co-mo-2009.