MQ Construction Co. v. Intercargo Insurance Co.

CourtAppellate Court of Illinois
DecidedDecember 29, 2000
Docket1-99-3424 Rel
StatusPublished

This text of MQ Construction Co. v. Intercargo Insurance Co. (MQ Construction Co. v. Intercargo Insurance Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MQ Construction Co. v. Intercargo Insurance Co., (Ill. Ct. App. 2000).

Opinion

THIRD DIVISION

December 29, 2000

No. 1--99--3424

MQ CONSTRUCTION CO., INC., ) Appeal from the

) Circuit Court of

Plaintiff-Appellee, ) Cook County.

)

  1. )

INTERCARGO INSURANCE COMPANY, ) Honorable

) Loretta C. Douglas,

Defendant-Appellant. ) Judge Presiding.

JUSTICE BURKE delivered the opinion of the court:

Defendant Intercargo Insurance Company, a surety on a public construction bond, appeals from an order of the circuit court entering judgment in favor of plaintiff MQ Construction Co., Inc. on plaintiff's claim against defendant's bond for money owed to plaintiff for certain construction work it performed on a public construction project.  On appeal, defendant contends that the trial court erred in finding that December 12, 1996, was the "last day of work" of plaintiff on the project for purposes of determining whether plaintiff filed a timely notice of its claim against defendant's bond as required by the Illinois Public Construction Bond Act (Bond Act) (30 ILCS 550/2 (West 1996)).  For the reasons set forth below, we reverse.  

The city of Chicago (City) hired Roadworks, Inc. (Roadworks) as the general contractor for a public works construction contract  known as "project No. S-5-020, 1995 Model Block Group 21-A" (project).  Plaintiff entered into an "agreement" with Roadworks for certain work on the project, which included: "Type 4 curb removal; Type 4 curb replacement; 5" PCC mainwalk; 5" PCC for the disabled; 8" PCC driveway; Type 3 curb removal; Type 3 curb replacement."  Although a complete contract is not contained in the record, portions of the "General Conditions and Special Conditions" for the City's project contract provided:

"The Contractors shall not be entitled to demand or receive final payment until all the stipulations, provisions and conditions as set forth in the contract have been complied with, and the work has been accepted by the Commissioner, whereupon the City will, at the expiration of 30 calendar days after such completion and acceptance, pay the whole account of money due the contractor under the contract.

The acceptance by the Contractor of the final payment above mentioned shall operate as and shall be a release to the City from all claims or liability under this contract, or for any act or neglect of the city relating to or connected with this contract.  

***

Contractor's Responsibility for Work

The Work shall be under the charge and care of the Contractor until final acceptance by the Commissioner, including all "Punch List" work, unless otherwise specified in the Contract Documents.  

The Work will not be considered as completed and accepted until a written notice from the Commissioner, confirming the Final Completion and acceptance of all Work, including "Punch List" Work has been received by the Contractor."  

On April 3, 1995, Roadworks, with defendant acting as surety, obtained a "Contractors's Performance Bond" in which it agreed to be bound to the City for $783,989.55 for the work, labor, and materials used on the project.  Between April 24, 1995, and May 12, 1995, plaintiff performed its work on the project pursuant to its agreement with Roadworks.  On June 6, 1995, plaintiff sent an "invoice" to Roadworks for "full and final payment" pursuant to the agreement.  The invoice itemized the work performed, listed the "total" for the work as $146,796.20, indicated that a previous payment had been made for $70,000, and demanded payment of $81,796.20.  

In December 1996, plaintiff received a copy of a "memorandum" and an accompanying "Preliminary Punch List" sent to Roadworks from the project director for the City.  The document stated, in part: "Final payment shall be withheld until both preliminary and final punch list items are completed to the city's satisfaction."  Items 1, 3 through 8, and 10 on the punch list required patching or replacing certain sections of sidewalk that plaintiff had originally constructed in April or May 1995, but which had been "marred after pouring and after the wet cement had cured, or which had cracked subsequent to installation."  On December 12, plaintiff returned to the project site and performed the punch list items related to its work and did not perform any further work on the project after that date.  Plaintiff did not issue an invoice to Roadworks for the work plaintiff performed on December 12.    

On January 17, 1997, plaintiff filed an "Original Contractor's Mechanic's Claim for Lien" against the City and Roadworks to recover the balance of $81,796.20 for the work plaintiff performed in "April, May, and June" 1995.  On January 28, defendant received a copy of plaintiff's claim on defendant's bond for the project and requested that plaintiff complete a "Proof of Claim" form and supply other documentation supporting plaintiff's claim.  Plaintiff completed the "Proof of Claim," indicating on the form that it last furnished labor, materials, supplies, and services in connection with the claim on December 12, 1996.  

On April 8, 1997, defendant denied liability for plaintiff's claim, stating that its investigation revealed that plaintiff "completed its original contract work" in June 1995 and that plaintiff's work in December 1996 was "corrective and cosmetic" and did not extend the time that plaintiff was required to make a claim against the "contractor's bond."  Because plaintiff had not filed a claim against the bond within 180 days of the completion of its work in June 1995, as required by section 2 of the Bond Act, defendant denied the claim.  

On June 12, 1997, plaintiff filed a verified complaint for declaratory judgment, alleging that it provided labor and materials on December 12, 1996, to cure punch list deficiencies "pursuant to its obligations to Roadworks," and that it properly filed a lien 36 days after the "last item of work" pursuant to the Bond Act.  The complaint requested that the trial court declare that plaintiff was entitled to coverage under the "Contractor's Performance Bond" and that defendant was obligated to provide coverage for plaintiff's loss pursuant to the terms of the bond.  

Defendant filed a section 2--615 motion to dismiss the complaint (735 ILCS 5/2--615 (West 1996)), arguing that plaintiff's case was inappropriate for declaratory relief because (1) plaintiff did not seek a determination of the construction of an ambiguous statute or contract provision,  (2) plaintiff only sought the enforcement of a right "after the fact" and not a declaration of present rights, and (3) section 2 of the Bond Act (30 ILCS 550/2 (West 1996)) "provided a specifically enacted and far more appropriate remedy than a declaratory judgment action."  The parties entered an agreed order which, among other things, struck the prayer for relief of plaintiff's verified complaint for declaratory judgment, and granted plaintiff leave to file an amended complaint.

Plaintiff filed an amended complaint which contained allegations similar to those in the original complaint but requested judgment in plaintiff's favor in the amount of $81,796.20, plus interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Reed
302 N.E.2d 131 (Appellate Court of Illinois, 1973)
People v. Maya
473 N.E.2d 1287 (Illinois Supreme Court, 1985)
In Re Application for Judgment & Sale of Delinquent Properties
656 N.E.2d 1049 (Illinois Supreme Court, 1995)
Stojkovich v. Monadnock Building
666 N.E.2d 704 (Appellate Court of Illinois, 1996)
Miller Bros. Industrial Sheet Metal Corp. v. La Salle National Bank
255 N.E.2d 755 (Appellate Court of Illinois, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
MQ Construction Co. v. Intercargo Insurance Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mq-construction-co-v-intercargo-insurance-co-illappct-2000.