City of Chicago Ex Rel. Charles Equipment Co. v. United States Fidelity & Guaranty Co.

491 N.E.2d 1269, 142 Ill. App. 3d 621, 96 Ill. Dec. 809, 1986 Ill. App. LEXIS 2094
CourtAppellate Court of Illinois
DecidedMarch 31, 1986
Docket85-1285
StatusPublished
Cited by11 cases

This text of 491 N.E.2d 1269 (City of Chicago Ex Rel. Charles Equipment Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chicago Ex Rel. Charles Equipment Co. v. United States Fidelity & Guaranty Co., 491 N.E.2d 1269, 142 Ill. App. 3d 621, 96 Ill. Dec. 809, 1986 Ill. App. LEXIS 2094 (Ill. Ct. App. 1986).

Opinion

PRESIDING JUSTICE SULLIVAN

delivered the opinion of the court:

This appeal is from certain orders of the trial court in an action to recover upon bonds given in connection with contracts for the construction of a public works project.

The record discloses that on August 12, 1982, Klein Construction Company (Klein) entered into a general contract with the city of Chicago (city) for the construction of a police station and, pursuant to the provisions of section 1 of “An Act in relation to bonds of contractors entering into contracts for public construction” (Ill. Rev. Stat. 1981, ch. 29, par. 15) (the Bond for Public Works Act), and the terms of the general contract itself, delivered to the city a performance and payment bond issued by United States Fidelity & Guaranty Company (defendant) as surety thereon.

Subsequently, Cresent Electric Company (Cresent) 1 subcontracted with Klein to provide certain materials and labor for the project, including the furnishing and installation of an emergency generator. In accordance with the terms of the subcontract, Cresent delivered a subcontractor’s bond issued by defendant Statewide Insurance Company (Statewide) naming Klein as obligee thereunder. On October 18, 1982, Cresent executed a written order for the purchase of the generator from Charles Equipment Company (plaintiff). The generator was delivered to Cresent in late May 1983, together with an invoice requesting payment of the agreed-upon price of $138,620.

Upon receipt from Cresent of (1) a payment request for $219,546 which included the cost of the generator, (2) a written waiver of lien rights for that amount, and (3) a sworn statement that “all Labor has been Paid in full. Materials from paid up stock delivered to the job site in our own trucks,” on July 28, 1983, Klein paid Cresent the amount requested.

On September 2, 1983, plaintiff filed its verified notice of claim with the city under the Mechanics’ Liens Act (Ill. Rev. Stat. 1981, ch. 82, par. 23), and the Bond for Public Works Act against monies due from the city to Klein as general contractor and/or to Cresent as Klein’s subcontractor in the amount of $138,620, and on November 18, filed a two-count complaint seeking judgment against defendant and Statewide as sureties on their respective bonds. The complaint alleged in, in essence, that it had performed its subcontract with Cresent by supplying the generator; that it had not been paid therefor; and that under the terms of their respective bonds, defendant and Statewide were liable for the amount due.

Defendant’s amended answer raised as affirmative defenses that (1) in accordance with the subcontract, Klein had paid Cresent for the generator furnished by plaintiff; (2) plaintiff had breached the no-lien provision of the Klein-Cresent contract by filing its lien claim; (3) as third-party beneficiary of the bond given by Statewide as surety for Cresent, it (defendant) was entitled to indemnification by Statewide for any unsatisfied claims by plaintiff against Cresent; and (4) the generator did not conform to the general contract specifications.

In its answer, Statewide maintained that only Klein, the named obligee on the bond, could assert the rights thereunder and also asserted as affirmative defenses that (1) Klein had breached the terms of its subcontract with Cresent; (2) its bond was not governed by the provisions of the Bond for Public Works Act; and (3) the generator did not comply with city specifications.

On April 27, 1984, plaintiff moved for summary judgment against defendant, and on May 23, defendant filed a counterclaim against Statewide alleging, inter alia, that (1) as surety for the obligee (Klein) of Statewide’s bond, it was a third-party beneficiary thereunder and, thus, entitled under the terms of the bond to indemnification from Statewide “against any and all loss or damage directly arising by reason of the failure of Cresent to (a) faithfully perform the subcontract, and (b) pay all just claims for labor and materials furnished in the completion of said subcontract by persons, firms or corporations having direct contracts with Cresent,” and also (2) that Statewide’s refusal to pay plaintiff constituted a breach of that contract which exposed it (defendant) to potential liability to Cresent’s suppliers.

On August 15, 1984, after argument by counsel, the trial court granted plaintiffs motion for summary judgment against defendant, and on December 14, amended the order to include prejudgment interest of $4,872.87. Following a hearing on April 3, 1985, the court (1) reduced the amount of prejudgment interest to reflect a prior payment by defendant to plaintiff; (2) granted plaintiffs motion (a) for a finding that the August 15 order of summary judgment as modified by the December order was final and appealable under Supreme Court Rule 304(a) (103 Ill. 2d R. 304(a)); (b) to voluntarily dismiss its complaint against Statewide; and (3) denied defendant’s motion for summary judgment against Statewide. This appeal followed.

Opinion

Defendant first contends that summary judgment for plaintiff was improper, arguing that under the well-settled maxim of surety law— that the liability of the surety cannot exceed that of its principal — its obligation to plaintiff was discharged when Klein, its principal, disbursed funds to Cresent to pay for the generator in reliance on Cresent’s sworn statement that all charges for labor and materials listed on its payment request had been paid; and that, therefore, while plaintiff might have a valid claim against Cresent or its surety, Statewide, no right of action exists against it, as surety for the general contractor. We disagree.

Although we do not dispute the basic common law tenet that payment and performance by the principal extinguishes the liability of the surety, the instant action was predicated upon and is governed exclusively by the Bond for Public Works Act, which provides:

“Sec. 1. All officials, boards, commissions or agents of this State, or of any political subdivision thereof in making contracts for public work of any kind to be performed for the State, or a political subdivision thereof shall require every contractor for such work to furnish, supply and deliver a bond to the State, or to the political subdivision thereof entering into such contract, *** with good and sufficient sureties. *** [S]uch bond, among other conditions, shall be conditioned for the completion of the contract, for the payment of material used in such work and for all labor performed in such work, whether by subcontractor or otherwise.
Each such bond is deemed to contain the following provisions whether such provisions are inserted in such bond or not:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rogers v. Tyson Foods, Inc.
895 N.E.2d 97 (Appellate Court of Illinois, 2008)
MQ Construction Co. v. Intercargo Insurance Co.
Appellate Court of Illinois, 2000
MQ Construction Co. v. Intercargo Insurance
742 N.E.2d 820 (Appellate Court of Illinois, 2000)
Walker Process Equipment v. Advance Mechanical System, Inc.
668 N.E.2d 132 (Appellate Court of Illinois, 1996)
Aluma Systems, Inc. v. Frederick Quinn Corp.
564 N.E.2d 1280 (Appellate Court of Illinois, 1990)
Deerfield Management Co. v. Ohio Farmers Insurance
529 N.E.2d 243 (Appellate Court of Illinois, 1988)
Northwest Water Commission v. Carlo v. Santucci, Inc.
516 N.E.2d 287 (Appellate Court of Illinois, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
491 N.E.2d 1269, 142 Ill. App. 3d 621, 96 Ill. Dec. 809, 1986 Ill. App. LEXIS 2094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chicago-ex-rel-charles-equipment-co-v-united-states-fidelity-illappct-1986.