M.P.G. Construction, Inc. v. Department of Transportation & Development

878 So. 2d 624, 2003 La.App. 1 Cir. 0164, 2004 La. App. LEXIS 771, 2004 WL 691511
CourtLouisiana Court of Appeal
DecidedApril 2, 2004
DocketNo. 2003 CA 0164
StatusPublished
Cited by6 cases

This text of 878 So. 2d 624 (M.P.G. Construction, Inc. v. Department of Transportation & Development) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.P.G. Construction, Inc. v. Department of Transportation & Development, 878 So. 2d 624, 2003 La.App. 1 Cir. 0164, 2004 La. App. LEXIS 771, 2004 WL 691511 (La. Ct. App. 2004).

Opinion

J^PETTIGREW, J.

Unsuccessful bidder on highway construction project brought action against the State of Louisiana, through the Department of Transportation and Development (“DOTD”), seeking to enjoin the award of the contract. After writs were exhausted, successful bidder intervened and joined DOTD’s reconventional demand for damages against unsuccessful bidder for delay of the project. Cross motions for summary judgment were filed by both sides. The trial court granted summary judgment and dismissed DOTD and inter-venor’s claims for damages, attorney fees, and costs. From this judgment, DOTD and intervenor have appealed.

FACTS

On August 25, 1999, the DOTD accepted bids, post advertisement, for State Project No. (“SPN”) 283-08-0114 known as the Crescent City Connection Bridge No. 1, Repainting Segment 2, Main Bridge Superstructure, Route: U.S. 90 (Business), Orleans and Jefferson Parish (“the project”). Prior to the project having been awarded, DOTD discovered an error and, consequently, exercised its right to reject all bids and re-advertise the project. Following re-advertisement of the project, bids were again received, opened, and publicly read on December 15,1999.

Certified Coatings of California, Inc. (“Certified Coatings”) was the low bidder. M.P.G. Construction, Inc. and Alpha Painting & Construction Co., Inc., a Joint Venture (collectively “M.P.G./Alpha”), was the next lowest bidder. On January 10, 2000, M.P.G./Alpha filed a Petition for Preliminary Injunction, Permanent Injunction, Declaratory Judgment and Mandamus seeking to prevent DOTD from awarding the project and entering into a contract with Certified Coatings. On January 18, 2000, DOTD filed a Response and Recon-ventional Demand for Dissolution, Damages and Attorney Fees. Certified Coatings filed a Petition of Intervention on January 19, 2000.

A hearing on M.P.G./Alpha’s Request for Preliminary Injunction was held on January 21, 2000. Following this hearing, the trial court concluded that DOTD had committed no error in its award of the project to Certified Coatings and, accordingly, denied M.P.G./Alpha’s request for injunctive relief. M.P.G./Alpha thereafter filed an | ¡Application for Supervisory Writs and Injunction with this court as well as a devolutive appeal seeking expedited review of the trial court’s denial of injunctive relief.

The contract for the project was signed on February 9, 2000. In response to the writ action, 2000-CW-0237, this court issued an order, dated February 15, 2000, commanding that “the award and signing of the. contract and/or issuance of work orders and the performance of any work orders under the contract be stayed pending further orders” from the court. Thereafter, this court dissolved the order staying execution of the contract, and in a per curiam opinion in the writ action concluded on July 12, 2000,1 found that the [627]*627trial court had committed no error. M.P.G./Alpha later sought Supervisory and/or Remedial Writs to the Louisiana Supreme Court that were similarly denied on August 30, 2000.2 Accordingly, this court later dismissed the appeal as “moot”, and writs were ultimately denied by the supreme court.3

While DOTD alleged that it pursued execution of the contract immediately, the stay delayed the start of the project for five months. Certified Coatings claimed that solely as a result of the legal action brought by M.P.G./Alpha, it had experienced an escalation in the labor, equipment, and insurance costs necessary to perform work on the project. On April 12, 2002, DOTD filed a Supplemental Recon-ventional Demand seeking damages and fees resulting from M.P.G./Alpha’s enjoining of the project and “perfecting a sus-pensive appeal without bond.” Certified Coatings filed its First Amending and Supplemental Reconventional Demand on April 18, 2002. Therein, Certified Coatings claimed that M.P.G./Alpha had been “successful in securing a preliminary injunction” from this court.

On June 10, 2002, M.P.G./Alpha filed a Motion for Summary Judgment wherein it alleged that it had never alleged a violation of the Louisiana Public Bid Law (R.S. 38:2211 |4et seq.), only violations of La. R.S.48:255 A, the statute that provides for the establishment of DOTD bid requirements and formalities. On July 16, 2002, DOTD filed a Cross Motion for Partial Summary Judgment with respect to the issue of liability. Certified Coatings later filed a similar Cross Motion for Partial Summary Judgment on August 5, 2002. A hearing was held on the Motion for Summary Judgment filed by M.P.G./Alpha and the Cross Motions for Partial Summary Judgment filed by DOTD and Certified Coatings on September 30, 2002. Following the hearing, the trial judge granted M.P.G./Alpha’s motion for summary judgment and dismissed with prejudice all claims, demands, and causes of action made against it. A final judgment to this effect was later signed by the trial court on November 18, 2002.

DOTD and Certified Coatings have separately appealed from the judgment of November 18, 2002.

ASSIGNMENT OF ERRORS

In connection with their appeal in this matter, DOTD and Certified Coatings allege that the trial court committed the following errors:

1. In determining that, legally, injunc-tive relief was not granted when DOTD was enjoined from awarding the contract, when DOTD and Certified Coatings were enjoined from signing the contract, when DOTD was enjoined from issuing work orders and/or DOTD and Certified Coatings were enjoined from performing any work on the Project;
2. In determining that M.P.G./Alpha was not legally liable to DOTD and Certified Coatings for damages and attorney’s fees under La.Code Civ. P. art. 3608; and
3. In determining that M.P.G./Alpha was not legally liable for attorney’s fees and costs under La. R.S. 38:2220.4.

[628]*628SUMMARY JUDGMENT

A motion for summary judgment is a procedural device used to avoid a full-scale trial when there is. no genuine issue of material fact. Johnson v. Evan Hall Sugar Coop., Inc., 2001-2956, p. 3 (La.App. 1 Cir. 12/30/02), 836 So.2d 484, 486. Summary | ¿judgment is properly granted if the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue of material fact and that mover is entitled to judgment as a matter of law. La.Code Civ. P. art. 966(B). Summary judgment is favored and is designed to secure the just, speedy, and inexpensive determination of every action. La.Code Civ. P. art. 966(A)(2); Thomas v. Fina Oil and Chemical Co., 2002-0338, pp. 4-5 (La. App.l Cir. 2/14/03), 845 So.2d 498, 501-502.

On a motion for summary judgment, the burden of proof is on the mover. If, however, the movant will not bear the burden of proof at trial on the matter that is before the court on the motion for summary judgment, the movant’s burden on the motion does not require that all essential elements of the adverse party’s claim, action, or defense be negated. Instead the mover must point out to the court that there is an absence of factual support for one or more elements essential to the adverse party’s claim, action, or defense. Thereafter, the adverse party must produce factual evidence sufficient to establish that he will be able to satisfy his evidentia-ry burden of proof at trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Broadmoor, LLC v. ERNEST N. MORIAL
896 So. 2d 251 (Louisiana Court of Appeal, 2005)
Love v. AAA Temporaries, Inc.
897 So. 2d 671 (Louisiana Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
878 So. 2d 624, 2003 La.App. 1 Cir. 0164, 2004 La. App. LEXIS 771, 2004 WL 691511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mpg-construction-inc-v-department-of-transportation-development-lactapp-2004.