Mountain Valley Pipeline, LLC v. 0.94 Acres of Land, Owned by Martin G. Morrison and Patricia A. Boyd

CourtDistrict Court, W.D. Virginia
DecidedMarch 27, 2025
Docket7:22-cv-00317
StatusUnknown

This text of Mountain Valley Pipeline, LLC v. 0.94 Acres of Land, Owned by Martin G. Morrison and Patricia A. Boyd (Mountain Valley Pipeline, LLC v. 0.94 Acres of Land, Owned by Martin G. Morrison and Patricia A. Boyd) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mountain Valley Pipeline, LLC v. 0.94 Acres of Land, Owned by Martin G. Morrison and Patricia A. Boyd, (W.D. Va. 2025).

Opinion

CLERKS OFFICE US DISTRICT COURT AT ROANOKE, VA IN THE UNITED STATES DISTRICT COURT FILED FOR THE WESTERN DISTRICT OF VIRGINIA March 27, 2025 ROANOKE DIVISION LAURA A. AUSTIN, CLERK By: /s/ S. Wray MOUNTAIN VALLEY PIPELINE, LLC, __ ) DEPUTY CLERK ) Plaintiff, ) ) Civil Action No. 7:17-cv-492 Vv. ) Civil Action No. 7:22-cv-317 ) 0.94 ACRES OF LAND, OWNED BY ) By: Elizabeth K. Dillon MARTIN G. MORRISON AND ) Chief United States District Judge PATRICIA A. BOYD, ) ) Defendants. ) MEMORANDUM OPINION Plaintiff Mountain Valley Pipeline (MVP) is constructing an interstate natural gas pipeline. MVP commenced a condemnation action under the Natural Gas Act, 15 U.S.C. § 717 et seq., to acquire easements on numerous properties, including this property located in Roanoke County and owned by defendants (also referred to as landowners) Martin G. Morrison and Patricia A. Boyd. On March 9, 2018, the court entered an order in the primary condemnation case, Mountain Valley Pipeline LLC v. Easements to Construct, Case No. 7:17-cv- 492 (W.D. Va.) (Dkt. No. 727), granting MVP immediate possession of the easements on the property. Now pending before the court is MVP’s motion for summary judgment (Dkt. No. 3).! When the motion was filed, Morrison and Boyd were represented by counsel, but counsel subsequently requested and was granted leave to withdraw, and the defendants submitted a pro se opposition. (Dkt. No. 7.) MVP then filed a reply. (Dkt. No. 8.) The court granted Morrison and Boyd’s motion to file a sur-reply, and the court has considered their sur-reply (Dkt. No. 9).

' Unless otherwise noted, record citations are to the individual case, Case No. 7:22-ev-00317.

The court also has considered the defendants’ second response (Dkt. No. 12), which defendants filed after receiving the court’s Roseboro2 notice (the Roseboro response). For the reasons discussed herein, the court will deny MVP’s motion for summary judgment. I. BACKGROUND MVP filed a complaint for condemnation of easements on a tract of land owned by

defendants, designated as MVP parcel VA-RO-4115, Roanoke County Tax Parcel ID 063.00-01- 20.00-0000. In particular, MVP sought a temporary/permanent access easement of 0.94 acres over the property, which—according to MVP’s appraiser—totals approximately 44 acres. The easement was over an existing road. The court granted partial summary judgment to MVP and granted it immediate possession of this and other properties along the pipeline route for construction. (Case No. 7:17-cv-492, Dkt. Nos 339, 340.) With regard to this particular tract, the court set security for the tract and granted MVP possession effective upon its making the required deposit and posting the required bond, which MVP did. (Id., Dkt. No. 589.) The court later opened a separate matter, 7:22-cv-317, for the determination of just compensation for this

property. In its motion for summary judgment, MVP explains that it no longer needs the easement on this property for the pipeline. It is nonetheless “willing to pay to defendants the full amount of just compensation for this property.” (Mot. Summ. J. ¶ 3, Dkt. No. 3.) MVP includes with its motion an appraisal by Jared L. Schweitzer, completed in 2018. (Schweitzer Report 5, Case No. 7:17-cv-492, Dkt. No. 379-6.) Using the comparable sales method, Schweitzer determined that the value of the land before the take was $145,000. (Id. at 27.) He determined that just compensation for the permanent easement was $2,750, which is 90% of the area inside the

2 Roseboro v. Garrison, 528 F.2d 309 (4th Cir. 1975). easement. (Id. at 29.) Because the easement was along a preexisting road, Schweitzer concluded that there were no damages to the residue. (Id. at 30.) He did not separately appraise the temporary easement. In response, the landowners raise a number of arguments. Some of these arguments are unrelated to the issue of just compensation, and they are not properly before the court in this

condemnation action.3 The landowners also claim that the map used by MVP is “inaccurate and not based upon actual facts, deeds[,] or surveys.” (Opp’n to Mot. Summ. J. (Opp’n) 1–2, Dkt. No. 7.) Specifically, they claim that it was based on Roanoke County GIS data, rather than deeds or surveys. (Id.) In their Roseboro response, defendants submitted their own exhibits, including a survey, and they contend that it shows different property lines than what was originally on MVP’s proposed route.4 (See generally Dkt. No. 12.)

3 For example, defendants reiterate certain complaints that they raised before the Federal Energy Regulatory Commission (FERC) prior to the MVP condemnation lawsuit being filed in this court. (Opp’n 2–3, 5– 6.) But as the Fourth Circuit has repeatedly recognized, collateral challenges to FERC’s decisions are not appropriate in these condemnation proceedings and cannot be addressed by this court. Mountain Valley Pipeline, LLC v. 6.56 Acres of Land, 915 F.3d 197, 221 (4th Cir. 2019). Likewise, defendants insist that MVP accessed portions of their property outside the easement in the complaint and outside the portion on which the court granted immediate possession. (Opp’n 4 (stating that MVP used the right-of-way on the property “at least once including a parcel that there was not a preliminary injunction on”).) Based on this allegation and other requests for relief, the landowners request that “the claim of eminent domain . . . be revoked.” (Opp’n 4.) It is unclear to the court precisely what defendants seek via their request for “revocation,” particularly because MVP already has stated it is no longer seeking title to the permanent easement. In any event, these types of issues may be pursued—if at all—in a civil action sounding in trespass or inverse condemnation or some other civil claim, not in this condemnation suit brought by MVP. This includes defendants’ claim that MVP crews accessed portions of the property where they did not have permission to go, as well as their request that the court issue an order that “all references on maps regarding ‘MVP Access Road Meacham Rd’ regardless of location . . . be removed. E.g. Roanoke County maps, Google Maps etc. People are trying to use this as an excuse to have access to this private road.” (Opp’n 6.) These issues are separate from the limited issues in this condemnation proceeding. Mountain Valley Pipeline, LLC v. W. Pocahontas Props. Ltd. P’ship, 918 F.3d 353, 363 (4th Cir. 2019) (claims that MVP was going to take more property than represented in its complaint or that there was damage to property outside MVP’s complaint “is irrelevant in the condemnation proceeding”); Columbia Gas Transmission, LLC v. 76 Acres, More or Less, in Baltimore & Harford Cntys., 701 F. App’x 221, 229 (4th Cir. 2017) (“Any claims for a taking beyond what was described in the district court’s order must be brought by the [landowners] in a separate action.”).

4 Relatedly, defendants take issue with the court’s prior orders in this case. They appealed at least some of those orders, such as the court’s orders granting immediate possession of the various easements, and those orders were affirmed. Similarly, defendants challenge the accuracy of Schweitzer’s appraisal, contending that he relied on the inaccurate map and GIS records and did not “set foot on the land.”5 They further contend that—contrary to MVP’s assertion—they have an appraisal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Mountain Valley Pipeline, LLC v. 0.94 Acres of Land, Owned by Martin G. Morrison and Patricia A. Boyd, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mountain-valley-pipeline-llc-v-094-acres-of-land-owned-by-martin-g-vawd-2025.