Columbia Gas Transmission, LLC v. 76 Acres, More or Less, in Baltimore & Harford Counties

701 F. App'x 221
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 13, 2017
Docket15-2547, 15-2569, 16-1017
StatusUnpublished
Cited by15 cases

This text of 701 F. App'x 221 (Columbia Gas Transmission, LLC v. 76 Acres, More or Less, in Baltimore & Harford Counties) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Gas Transmission, LLC v. 76 Acres, More or Less, in Baltimore & Harford Counties, 701 F. App'x 221 (4th Cir. 2017).

Opinion

Unpublished opinions are not binding precedent in this circuit.

DAVIS, Senior Circuit Judge:

This appeal arises from a condemnation proceeding commenced by Appellant/Cross-Appellee Columbia Gas Transmission, LLC (“Columbia”). Columbia took by eminent domain certain easements (both permanent and temporary) over the properties of Appellees/Cross-Appellants Lambert and Ledley Boyce, Robert Boyer, and Margaret Kenney (collectively “the Landowners”). 1 Following a jury trial, the Landowners were awarded compensation for Columbia’s taking. Columbia now appeals, principally arguing that the district court erroneously permitted the jury to modify the size of the taking that Columbia sought. Columbia, also asserts error in several of the district court’s evidentiary rulings. The Landowners cross-appeal from a pre-trial decision of the district court granting Columbia immediate possession of the easements.

We conclude that the district court erred by permitting the Boyces to contest the size of the temporary easement on their property, which resulted in a disproportionate damages award for the temporary easement. Accordingly, we vacate the jury’s award with respect to the temporary easement on the Boyces’ property and remand for a new trial as to that issue only. We otherwise affirm.

I.

Columbia is a natural gas company that was authorized by the Federal Energy Regulatory Commission (“FERC”) to exercise the right of eminent domain in order to construct a natural gas pipeline in Har-ford and Baltimore Counties, in central *224 Maryland. 2 On January 15, 2014, Columbia commenced a condemnation action seeking to acquire certain easements — both permanent and temporary — over the Landowners’properties. As described in the complaint, the permanent easements would permit Columbia to “construct, operate, maintain, replace, repair, remove or abandon” the proposed pipeline and would extend twenty-five feet in either direction from the pipeline. J.A. 564-65. The temporary construction easements were described as being “twenty-five (25) to fifty (50) feet on either side of and adjoining the permanent easements and serve the purpose of enabling Columbia to construct [the pipeline] or to later relocate the pipeline or lay additional pipelines and to conduct all activities incident thereto, including restoration or cleanup activities.” J.A. 564. The complaint also provided the relative sizes of the easements that Columbia sought:

• Boyce permanent easement: 0.68 acres
• Boyce temporary easement: 0.38 acres
• Boyce additional temporary easement: 0.32 acres
• Boyer permanent easement: 0.67 acres
• Boyer access road use: 0.09 acres
• Boyer temporary easement: 0.29 acres
• Boyer additional temporary easement: 0.12 acres
• Kenney permanent easement: 0.9965 acre
• Kenney temporary construction easement: 0.4664 acres
• Kenney temporary construction license: 0.0101 acres

J.A. 565-66.

Columbia moved for partial summary judgment, seeking immediate possession of the easements described in the complaint. The Landowners opposed the motion, arguing that the district court did not have the authority to grant Columbia possession of the easements prior to holding a trial to determine just compensation. The district court granted the motion and (after requiring Columbia to post a bond) issued a preliminary injunction permitting Columbia to take immediate possession of the easements and begin constructing the pipeline. The size and location of the temporary and permanent easements listed in the district court’s order granting immediate possession were the same as those in the complaint. Thereafter, Columbia began constructing the pipeline across the Landowners’ properties.

Before trial, Columbia filed two motions in limine relevant to this appeal. First, it moved to exclude the testimony of the Landowners’ expert, Jennifer Hanna, arguing that it did not meet the reliability standard established in Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993). The district court denied this motion, finding that because Columbia was challenging Hanna’s conclusions rather than her qualifications or methodology, a Daubert hearing was not necessary. Second, Columbia sought to exclude claims made by some of the Landowners that the size of the temporary easements that Columbia actually took were larger than the easements described *225 in the district court’s order granting immediate possession. The district court denied this motion as well, finding that the sizes of the temporary easements were triable issues of fact.

Trial to determine the just compensation owed to the Landowners for Columbia’s taking took place after Columbia completed the construction of the pipeline but while it was still restoring some portions of the Landowners’ property. At the conclusion of trial, the jury returned a verdict awarding the Landowners the following damages:

• Boyce permanent easement: $29,216
• Boyce temporary easement: $50,104
• Boyce remainder: $167,011
• Boyer permanent easement: $27,872
• Boyer temporary easement: $6,144
• Boyer remainder: $93,948
• Kenney permanent easement: $43,268
• Kenney temporary easement: $7,639
• Kenney remainder: $130,668

J.A. 2152-53.

After the district court entered judgment in the amounts listed above (less certain amounts that Columbia previously paid to the Landowners), Columbia moved for a new trial. The district court denied that motion, and these timely cross-appeals followed.

II.

A.

Columbia’s main contention on appeal is that the district court erroneously permitted the Landowners and the jury to modify the size of the taking that Columbia sought, specifically the temporary easements on the Boyces’ (and the now-dismissed Turks’) properties. Columbia also argues that the district court repeated this error in its charge to the jury and that the jury instructions permitted the Landowners to receive double recovery for certain harms related to the temporary easements. Columbia raises two additional issues: it argues that the district court should have excluded testimony by the Landowners’ expert and that the jury’s verdict is not supported by sufficient evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mountain Valley Pipeline, LLC v. 0.32 Acres of Land
127 F.4th 437 (Fourth Circuit, 2025)
McNulty v. Casero
D. Maryland, 2020
Mountain Valley Pipeline, LLC v. Simmons
307 F. Supp. 3d 506 (U.S. District Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
701 F. App'x 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-gas-transmission-llc-v-76-acres-more-or-less-in-baltimore-ca4-2017.