Moss Iron Works v. County Court

109 S.E. 343, 89 W. Va. 367, 26 A.L.R. 319, 1921 W. Va. LEXIS 185
CourtWest Virginia Supreme Court
DecidedNovember 1, 1921
StatusPublished
Cited by21 cases

This text of 109 S.E. 343 (Moss Iron Works v. County Court) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moss Iron Works v. County Court, 109 S.E. 343, 89 W. Va. 367, 26 A.L.R. 319, 1921 W. Va. LEXIS 185 (W. Va. 1921).

Opinion

Lynch, Judge:

Stated in somewhat different language, but in effect the same as that contained in the order certifying them, the questions to be discussed are these: Is the property of a county, the court house and jail and the lot on which they stand, within the meaning of the mechanic’s lien law, as amended and reenacted by ch. 6, Acts, 1917, ch. 75, Code 1918? If not, is the county court liable for the unpaid debts due a subcontractor for materials, equipment and labor furnished by him and installed in a court house and jail? The questions the demurrer of the county court of Jackson county raised, and the answer of the circuit court of that county was in the negative.

The Jackson county court contracted with Prescott Construction Company May 24, 1917, seven days after the revised statute became effective, to construct and repair the county court house and jail, furnish all the labor and material and perform all the work necessary for that purpose, according to the plans and specifications incorporated in the contract, and made part of it, for a consideration payable as the work progressed. The original amount was $67,133.00, later [370]*370increased to $100,000.00 by extras authorized by the county court.

Subsequently, Prescott Construction Company contracted with Huntington Iron Works to furnish some of the materials and perform certain parts of the work provided for in the original and amended contract and specifications, payments therefor to be made upon the same terms and conditions, those to be made to Prescott Construction Company. These contracts the architect, L. J. Dean, approved when submitted for his approval, as required by the agreement with the county" court.

Huntington Iron Works began to furnish the materials and perform the work, it undertook to furnish and do, soon after the date of its contract with Prescott Construction Company, complied with the terms and conditions so prescribed, and completed it November 15, 1919, and Dean accepted it December 31, 1919, as completed; and although the county court paid Prescott Construction Company for the work it was to perform and did perform, the latter company did not pay Huntington Iron Wofks the amount due it, but left unpaid a balance of $6,380.39. For this balance Huntington Iron Works in due form prepared and caused to be recorded in the office of the county clerk of Jackson county a notice of mechanic’s lien, and perfected such lien in all respects in compliance with the mechanic’s lien statute. At least there seems to be no objection as to any lack of formality in the effort to procure a formally perfect lien.

Having become indebted to the plaintiff, The Moss Iron Works, in the sum of $4,242.15, and to the plaintiff, Wheeling Metal & Manufacturing Company in the sum of $1,833.01, in some manner not disclosed in the bill, Huntington Iron Works assigned and transferred to each of. them, out of the $6,640.39, the amounts due them respectively, and to enforce payment of the lien is the object of this suit.

Plaintiffs invoke the' provisions of sections 12 and 14 of chapter 6, Acts 1917, chapter 75, Code 1918, as authority for the liens and the right to enforce them by á sale of the court house and jail, and the ground on which they stand. By section 12, the state board of control, county courts, boards [371]*371of education, boards of trustees and all other legal bodies having authority to contract for the erection, construction, improvement, alteration or repair of any public building or structure, used or to be used for public purpose, are directed in so contracting to require the person or persons to whom it shall award any such contract to execute a good, valid, solvent and sufficient bond, in an amount at least equal to the reasonable cost of the materials, machinery, equipment and labor required in the completion of the contract, upon the condition that in the event such contractor shall fail to pay in full for such materials, machinery, equipment and labor used by him in the erection, construction, improvement, alteration or repair of such public building, or other structures used or to be used for public purposes, the bond and the sureties thereon shall be liable to the person who has furnished such material, machinery, equipment or labor for the full payment of the expenses incurred by him in that behalf. This bond the section requires to be filed with the secretary of such board or other legal body, or other custodian of its papers and records.

According to section 14, the contractor is to be deemed and treated as the agent of the owner of the building, or other structure, and the improvements appurtenant thereto, and his interest in the lot on which the building is erected, improved or repaired, or onto which it is removed, and the owner and his property is liable for the full and true value of all work and labor done, and materials, machinery and equipment furnished by a sub-contractor, if the owner fails to require the contractor to execute a bond in the amount at least equal to the reasonable costs of such material, machinery and equipment, and labor performed, or to be performed pursuant to the terms of the contract, or fail to record the contract and bond, when so given, or accepts a bond 'for a less amount.

As the statute before the amendment contained the same general mechanic’s and labor liens provisions, without specific reference to property, real or personal, belonging to the public, or purchased and held for public use, as interpreted in Hall’s Safe & Lock Co. v. Scites, 38 W. Va. 691, it did not [372]*372apply to such, buildings. That was a suit to enforce a mechanic’s lien against the court house and grounds of Wayne county. The first point of the syllabus reads: “The public buildings of a county are wholly exempt from the operation of the mechanic’s lien law, and can not be sold under execution or other process.” The statute then in force had the same general provisions as the amended statute, except insofar as section 12 enlarges earlier statutes in the particular noted. The mechanic’s lien law, as it appears in the 1894 code, that being the law construed in Hall’s Safe & Lock Co. v. Scites, cited, says: “Every material man, workman, laborer, mechanic or other person performing labor or furnishing any material or machinery under a contract with a principal contractor, or his subcontractor for the construction, alteration, repair, or removal of any houses or other structures provided for in a contract between the owners thereof, or his authorized agent, and such principal contractor shall have a lien to secure the value of the labor performed, and the material or machinery furnished — upon such house or other structure” etc.

Notwithstanding this broad and comprehensive language, language sufficiently broad and comprehensive to include a county court house and jail, and it was so considered by plaintiff in that case, the circuit court and this court held otherwise, and refused to approve and enforce the pretended lien. This holding is justified by an abundance of authority. Does either section of the revised mechanic’s lien statute warrant the application of any other rule or principle 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemartec Corp. v. Entsorga W. Va., LLC
386 F. Supp. 3d 726 (U.S. District Court, 2019)
Patton v. Vanterpool
806 S.E.2d 493 (Supreme Court of Georgia, 2017)
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
Rayborn v. Housing Authority of Washington County
164 So. 2d 494 (Supreme Court of Alabama, 1964)
Cunningham v. County Court of Wood County
134 S.E.2d 725 (West Virginia Supreme Court, 1964)
Parkins v. Londeree
124 S.E.2d 471 (West Virginia Supreme Court, 1962)
Petros v. Kellas
122 S.E.2d 177 (West Virginia Supreme Court, 1961)
Ward v. County Court of Raleigh County
93 S.E.2d 44 (West Virginia Supreme Court, 1956)
Harbert v. County Court of Harrison County
39 S.E.2d 177 (West Virginia Supreme Court, 1946)
Carroll v. Ragsdale
15 S.E.2d 210 (Supreme Court of Georgia, 1941)
Webb v. Crane Co.
80 P.2d 698 (Arizona Supreme Court, 1938)
Martin v. Holtville High School Bldg.
145 So. 491 (Supreme Court of Alabama, 1933)
Hibner v. Ebersbach
157 S.E. 178 (West Virginia Supreme Court, 1931)
Tug River Lumber Co. v. Smithey
148 S.E. 850 (West Virginia Supreme Court, 1929)
State Ex Rel. West Virginia Sand & Gravel Co. v. Royal Indemnity Co.
128 S.E. 439 (West Virginia Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
109 S.E. 343, 89 W. Va. 367, 26 A.L.R. 319, 1921 W. Va. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moss-iron-works-v-county-court-wva-1921.