Lemartec Corp. v. Entsorga W. Va., LLC

386 F. Supp. 3d 726
CourtUnited States District Court
DecidedFebruary 13, 2019
DocketCivil Action No.: 3:18-CV-22
StatusPublished

This text of 386 F. Supp. 3d 726 (Lemartec Corp. v. Entsorga W. Va., LLC) is published on Counsel Stack Legal Research, covering United States District Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lemartec Corp. v. Entsorga W. Va., LLC, 386 F. Supp. 3d 726 (usdistct 2019).

Opinion

GINA M. GROH, CHIEF JUDGE

Now before the Court is Defendant Berkeley County Solid Waste Authority's (the "Solid Waste Authority") Second Motion for Summary Judgment, [ECF No. 74] filed on November 8, 2018. Plaintiff Lemartec Corporation ("Lemartec") filed a Response in Opposition [ECF No. 82] on November 28, 2018. The Defendant filed a Reply in Support of its Motion [ECF No. 83] on December 12, 2018. Accordingly, the matter has been fully briefed and is now ripe for review. For the following reasons, the motion is granted in part.

I. Factual and Procedural Background

This lawsuit arises from the construction of a waste-to-fuel processing plant in Martinsburg, West Virginia (the "Project"). ECF No. 1, 18. The background of the Project is as follows. In 2010, the Solid Waste Authority entered into a long-term lease with Defendant Entsorga West Virginia, LLC ("Entsorga WV"). Under the lease, Entsorga WV was tasked with developing a processing plant that could turn solid waste into fuel. In March 2016, Entsorga WV appointed Chemtex International, Inc. ("Chemtex") to serve as the general contractor on the Project. Chemtex entered into a subcontract with Lemartec. Shortly thereafter, Chemtex assigned its interest in the subcontract to its wholly-owned subsidiary, Biochemtex S.p.A. ("Biochemtex"). Throughout the Project, Lemartec alleges that Pier Cella ("Mr. Cella") acted as an agent of Entsorga WV and/or Defendant Entsorga USA, Inc. ("Entsorga USA"), and, in that capacity, actively participated in all aspects of the Project. Lemartec states that Biochemtex failed to pay Lemartec for the services and materials it provided to the Project. Lemartec further alleges that the financial situation with Biochemtex caused Lemartec to consider terminating its relationship with the Project.

However, in June 2017, Entsorga WV terminated the contract with Biochemtex and began direct negotiations with Lemartec to complete the work on the Project. Lemartec asserts that Entsorga WV promised to pay Lemartec for all the work performed on the Project, including the work performed as a subcontractor for Biochemtex. Thereafter, the parties reached an agreement and executed a Memorandum of Understanding and Limited Notice to Proceed ("MOU"). Lemartec recommenced construction in August 2017. Lemartec alleges that Entsorga WV failed to pay Lemartec for the services it performed, so Lemartec stopped work on the *729Project. On February 7, 2018, Lemartec filed a mechanic's lien against the Project, claiming that Entsorga WV owes it $ 1,694,192.60.

On the same day, Lemartec filed the complaint in this action seeking enforcement of the mechanic's lien and alleging breach of contract, or in the alternative, unjust enrichment against Entsorga WV and the Solid Waste Authority. As an alternative ground of recovery, Lemartec alleged tortious interference of contract by Entsorga USA. Specifically, Lemartec stated that Entsorga USA's director Mr. Cella intentionally interfered with the MOU between Lemartec and Entsorga WV by "influencing and/or directing Entsorga WV to reject Lemartec's performance." ECF No. 1 at 8.

On April 5, 2018, Entsorga USA filed a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) arguing that "Lemartec cannot plead or prove an essential element of their case-that the intentional act of interference be by a party outside the contractual relationship or expectancy." ECF No. 18 at 5. Specifically, Entsorga USA averred that it is a member and agent of Entsorga WV, and so, it is not a party outside the contractual relationship or expectancy. The Court granted the motion to dismiss but granted Lemartec leave to amend its complaint.

On June 22, 2018, Lemartec filed a motion for leave to amend its complaint. ECF No. 38. The amended complaint sought to add additional causes of action against the initial Defendants-Entsorga WV, Entsorga USA, and the Solid Waste Authority. The amended complaint also added new Defendants who are "responsible for Lemartec's damages and who participated substantially in the project in question." ECF No. 39 at 2. On September 6, 2018, the Court granted leave to amend in part. ECF No. 52.

The Amended Complaint charges: (1) enforcement of mechanic's lien; (2) breach of contract; (3) in the alternative, unjust enrichment or quantum meruit; (4) in the alternative, failure to post bond; and (5) joint venture. Now, the Solid Waste Authority moves for summary judgment on Counts I, II, IV and V. ECF No. 74.

II. Applicable Legal Standards

Summary judgment is appropriate "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). A genuine issue exists "if the evidence is such that a reasonable jury could return a verdict for the non-moving party." Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Thus, the Court must conduct "the threshold inquiry of determining whether there is the need for a trial-whether, in other words, there are any genuine factual issues that properly can be resolved only by a finder of fact because they may reasonably be resolved in favor of either party." Id. at 250, 106 S.Ct. 2505.

The party opposing summary judgment "must do more than simply show that there is some metaphysical doubt as to the material facts." Matsushita Elec. Indus. Co., ltd. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Harrods Limited v. Sixty Internet Domain Names
302 F.3d 214 (Fourth Circuit, 2002)
Armor v. Lantz
535 S.E.2d 737 (West Virginia Supreme Court, 2000)
Hurley v. Allied Chemical Corp.
262 S.E.2d 757 (West Virginia Supreme Court, 1980)
Moss Iron Works v. County Court
109 S.E. 343 (West Virginia Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
386 F. Supp. 3d 726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lemartec-corp-v-entsorga-w-va-llc-usdistct-2019.