Moscow Hardware Co. v. Regents of the University of Idaho

113 P. 731, 19 Idaho 420, 1911 Ida. LEXIS 19
CourtIdaho Supreme Court
DecidedFebruary 25, 1911
StatusPublished
Cited by8 cases

This text of 113 P. 731 (Moscow Hardware Co. v. Regents of the University of Idaho) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moscow Hardware Co. v. Regents of the University of Idaho, 113 P. 731, 19 Idaho 420, 1911 Ida. LEXIS 19 (Idaho 1911).

Opinions

SULLIVAN, J.

This action was brought by the Moscow Hardware Co. against the Regents of the University of Idaho and the state of Idaho.

As a first cause of action, the plaintiff alleges that between October 1, 1906, and April 1, 1907, it delivered and furnished building material, hardware, finishings, goods, wares and merchandise to be used in the construction of the building known as the “Agricultural Building” of the University of the State of Idaho, of the value of $1,468.45, and that there remains due thereon the sum of $1,174.77; that said goods, wares and merchandise were furnished to Colson & Son, who were the contractors, with the actual knowledge of the de[424]*424fendants, and that said goods, wares and merchandise were placed in the building for the use and benefit of the defendants.

For a second cause of action, it is alleged that between October 10, 1906, and April 1, 1907, the plaintiff sold and delivered to the defendant upon the order of Colson & Son, goods, wares and merchandise and building material to be used, and which were used, in the construction and erection of the foundation of the Administration Building of the University of Idaho, and that said goods and materials were delivered on the grounds near where the foundation was being constructed in the city of Moscow; that Colson & Son were in charge of the work in procuring said material and in the construction of said foundation, and were doing said work under the direction and authority and with the knowledge and consent of the defendants and as its agents and representatives; that on or about February 13, 1907, the Board of Regents discharged Colson & Son and took into its possession all the goods, wares and merchandise, hardware and building material which plaintiff had delivered as aforesaid, and appropriated the same to their own use and benefit; that the defendants, nor either of them, has paid for the same or any part thereof, the reasonable value of which materials, merchandise, etc., is $414.38, with interest thereon.

As a third cause of action, plaintiff alleges that between October 1, 1906, and January 1, 1907, the Standard Lumber Co. delivered to the defendants upon the order of J. A. Colson & Son, goods, wares, merchandise, lumber and building materials to be used in and which were actually used in the construction and erection of said foundation, with the knowledge and consent of the defendants; that on or about February 13, the defendants, said Board of Regents, discharged Colson & Son, and took into their possession all of the goods, wares, merchandise, lumber and building materials which had been delivered by said Lumber Co., and kept and used the same in the building and construction of the foundation of the Administration Building; that said merchandise and material [425]*425were of tbe reasonable value of $560.10, which sum is due and unpaid, with interest thereon.

As a fourth cause of action it is alleged that between August 1, 1906, and March 1, 1907, the Standard Lumber Co. delivered and furnished building materials, lumber, goods, wares and merchandise to be used in the construction of the building known as the Agricultural Building of the University of Idaho, at the request and upon the order of the agents, servants and persons in charge of the work of construction; that said merchandise and materials so furnished for the construction of the Agricultural Building were of the reasonable value of $4,096.45, no part of which has been paid except the sum of $1,846.50, leaving a balance due of $3,249.91, with interest thereon; that said claim was presented to the board and rejected.

For a fifth cause of action, it is alleged that between November 1, 1906, and January 1, 1907, W. A. Lauder sold and delivered to the defendants upon the order of J. A. Colson & Son, goods, wares, merchandise and sand to be used in and which were actually used in the construction and erection of the foundation of the Administration Building of the University of Idaho, and that said merchandise and material and sand were delivered on the ground belonging to defendants at or near the foundation; that Colson & Son were in charge of the work of construction of said foundation and were doing the work under the direction and authority and with the knowledge and consent of the Board of Regents; that on February 13, 1907, the Board of Regents discharged Colson & Son and took and received into their possession all of the said goods, merchandise and sand which had been delivered by Lauder, and have kept and used the same in the building and construction of said foundation, and still keep and appropriate all of the same, the reasonable value of which is $540; that there is now due the said sum of $540, with legal interest thereon.

For a sixth cause of action, it is alleged that between August 1, 1906, and March 1, 1907, Lauder delivered and furnished sand and other building materials to be used in the [426]*426construction of the building known as the Agricultural Building of the University of the State of Idaho; that said materials and sand were of the reasonable value of $4,340.90, no part of which has been paid except the sum of $2,183.35, and that there is now due thereon the sum of $2,157.55, with interest thereon; and prays for a recommendatory judgment for the sum of $9,946.92, principal and interest, as provided by see. 10 of art. 5 of the constitution of the state of Idaho, and for such other and further relief as may be just and equitable.

The answer denies many of the material allegations of the eomplaint; denies that the Board of Regents is a corporation, and denies that the Board of Regents or the state is owing the plaintiff in any sum whatever on any cause of action set forth in the complaint. The cause was referred to a referee to take the evidence in the case, and in the return of the referee is found a stipulation by the parties to the effect that no question shall be raised with reference to the Regents of the University of the State of Idaho being a corporation; also that in the construction of the Agricultural Building, on the 17th of July, 1906, the contract was awarded to Colson & Son by the executive committee of the Board of Regents, which was thereafter approved by the Board of Regents and the contract was entered into and bond furnished for the completion of said building; that thereafter on the 29th of March, 1907, the Board of Regents, through its executive committee, gave Colson & Son written notice that unless they proceeded to work on the Agricultural Building within three days that they would forfeit their contract and would complete the work themselves; and on the 1st of April, 1907, the Regents of the University declared the contract forfeited and thereafter completed the •,construction of the building themselves. It is further stipulated that a contract was let to Colson & Son to complete the work for the foundation of the Administration Building and an agreement was entered into on October 10, 1906, with Colson & Son to construct said foundation. Colson & Son failed to furnish the bond required by the contract, and on the 12th of February, 1907, [427]*427the Board of Regents, through its agents, ordered them to ■cease work by reason of the failure to furnish the bond, and Colson & Son did cease work on said foundation, and the Board of Regents thereafter, through its agents, took complete charge of the work and completed the foundation. It is also stipulated that E. J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sadid v. Idaho State University
837 F. Supp. 2d 1168 (D. Idaho, 2011)
Renninger v. State
213 P.2d 911 (Idaho Supreme Court, 1950)
Dreps v. Board of Regents of the University
139 P.2d 467 (Idaho Supreme Court, 1943)
State ex rel. Black v. State Board of Education
196 P. 201 (Idaho Supreme Court, 1921)
First National Bank v. Regents of University
140 P. 771 (Idaho Supreme Court, 1914)
First National Bank v. Regents of the University of Idaho
113 P. 735 (Idaho Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
113 P. 731, 19 Idaho 420, 1911 Ida. LEXIS 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moscow-hardware-co-v-regents-of-the-university-of-idaho-idaho-1911.